HomeMy WebLinkAboutEDB SA No 5 CDM Smith Strategic Planning Ph 2 EXECUTIVE SUMMARY
AGENDA ITEM:
Proposed Supplemental Agreement No. 5 to Professional Engineering Services Agreement 18/19 No. 3 to
provide Professional Engineering Services with CDM Smith,Inc. (CDM Smith)for the Strategic Planning
Phase II effort
Date: March 31, 2022
BACKGROUND:
The Clay County Utility Authority(CCUA)staff request authorization to engage CDM Smith's assistance
with the next phase of the Strategic Planning process. CCUA began the strategic planning effort in July
2021. CCUA and the CDM Smith team successfully completed the first phase of the strategic planning
effort in February 2022 that identified areas for strategic focus. We continue to make significant progress
es with the CDM Smith team on other major components: the Integrated Water Resource Plan (IWRP) and
a Rate Study and the Employee Training and Incentive Program. These planning efforts and workplans to
co
a advance all areas of strategic focus will be combined into one report (the Strategic Plan) through the
o Strategic Planning Phase II effort.
r
c
L
CCUA staff considers the Strategic Plan important for the long-term view of the utility's customer service,
ce
infrastructure investments, rates and financing, staffing, technology, and regulatory compliance. We will
fashion the Strategic Plan as an actionable plan with defined objectives and performance measures to be
implemented over time as the utility grows.
Staff requested a Scope of Services and Fees from CDM Smith for the support and subject matter experts
needed to assist the Senior Leadership Team (SLT) in developing the Strategic Plan. CDM Smith will
designate a representative who will participate in workshops to provide information and direction to the
SLT in the development of the Strategic Plan. The proposed supplemental agreement provides for
compensating the CDM Smith team on a time and materials basis.
Staff intends to present the final Strategic Plan to the Board of Supervisors for input, consideration, and
adoption. Staff considers the adoption of a Strategic Plan by the Board of Supervisors essential for the
development of the utility as well as effective communication with many external stakeholders over time.
BUDGET:
Staff budgeted for this expense in the operating budget.
//JDJ(Author)
//JW,KO,and AB(Review)
//JDJ(Final)
Executive Summary Supplemental Agreement No. 5 CDM Smith
Page 1
CCNA:
CCNA, F.S. s. 287.055, does apply to the use of a consultant under continuing contract. The estimated
cost of this study does not exceed$500,000. Staff negotiated this Supplemental Agreement in compliance
with F.S. s. 287.055. Staff and the consultant negotiated the scope and fee, based on established contract
rates, for the professional services at a compensation which CCUA determines is fair, competitive, and
reasonable.
RECOMMENDATION:
Staff respectfully recommends approval of Supplemental Agreement No. 5 with CDM Smith, Inc., for
$249,000 to complete this Strategic Planning Phase II effort.
ATTACHMENTS:
Supplemental Agreement No. 5
Scope and Fee Proposal
//JDJ(Author)
//JW,KO,and AB(Review)
//JDJ(Final)
Executive Summary Supplemental Agreement No. 5 CDM Smith
Page 2
Supplemental Agreement No. 5 to Professional Engineering Services Agreement
18/19 No. 3 to provide Professional Engineering Services with CDM Smith, Inc for the
Strategic Planning Phase II
Engineer: Shayne Wood, P.E. Owner: Clay County
CDM Smith, Inc. Utility Authority
4651 Salisbury Road, Suite 420
Jacksonville, FL 32256
Date: April 5, 2022
Item: Description of Services:
Provide professional engineering services as
requested and identified in the attached scope of
services and fee proposal.
Phase 2 Evaluation & Determination
Task 1 Kickoff Meeting
Task 2 Strategic Planning Workshops
Task 3 Task 4
Subject Matter Expert Participation
Management Consulting Review and Input
Task 5 Strategic Planning Document
Task 6 Project and Quality Management
Total Lump Sum Price Not to Exceed Without Prior Authorization $249,000
This document, along with the Scope and Fee Proposal, shall become an amendment to the Professional
Engineering Services Agreement 18/19 No. 3 and all provisions of the Agreement will apply hereto.
Accepted by: Date:
Engineer:
Shayne Wood, P.E.
CDM Smith, Inc.
Accepted by: Date:
Owner:
Jeremy Johnston, PE, MBA,
Executive Director
Clay County Utility Authority
CLAY COUNTY UTILITY AUTHORITY
CIVIL AND ENVIRONMENTAL CONTINUING SERVICES
RFQ 18/19 NO.3
March 2022
WORK ORDER NO. 5
This Authorization, when executed, shall be incorporated in and become part of the Agreement for
Professional Services between Clay County Utility Authority (Authority), and CDM Smith Inc.
(CONSULTANT), dated May 28, 2019 hereafter referred to as the Contract.
BACKGROUND
The population growth within Clay County continues to accelerate. The Authority anticipates the
population growth within Clay County will result in the utility doubling in size over the planning horizon
of 20 to 25 years. The Authority also anticipates the growth in the population served by the utility will
require new, as well as improvements to existing infrastructure, increased staffing levels, improved
processes, and procedures, as well as investments in new technology. The Authority intends to either
maintain or improve levels of services to the customers served by the utility systems. The Authority
initiated a strategic planning process to evaluate and develop a plan to adapt, improve, or develop
internal organizational structures, processes, staffing, processes, and technology investments over the
to 20-to-25-year planning horizon.
The Authority intends to engage the Consultant in the next phase of the strategic planning process.The
Authority defines the objective of the next phase of this strategic planning process as a formal report
that will be presented to the Board of Supervisors for consideration and adoption. The Authority and
Consultant will build upon the Strategic Planning Phase I completed in February 2022. The Authority
and Consultant will incorporate other areas of work currently underway (the Integrated Water
Resource Planning, Rate Study, the Employee Training and Incentive Program, etc.) into the strategic
planning report.
The Authority's Senior Leadership Team (SLT) will lead and direct the development of the strategic
planning report. The Consultant will provide support in the writing and development of the strategic
planning report. The Consultant will provide an analyst or engineer to attend SLT meetings/workshops
to receive information and direction. When needed, the Authority requested access to subject matter
experts for development and refinement of subject areas to be addressed in the strategic planning
report.
SCOPE OF SERVICES
The following tasks describe the scope of services to develop a Strategic Plan for the Authority.
TASK 1—KICKOFF MEETING
CONSULTANT will hold an Initial Approach Discussion with the Executive Director to solidify schedule,
refine the document development approach, and review the Strategic Planning Outline topics in
relation to the Strategic Plan Roadmap Priorities prior to the first SLT meeting.
TASK 2—STRATEGIC PLANNING WORKSHOPS
CONSULTANT will participate in up to 20 SLT meetings discussing the Authority's approach,
implementation plan, and priority for the items listed in the attached Strategic Planning Outline.
CONSULTANT will document the outcomes of the discussions during each of the SLT Meetings. These
summaries will become the basis for the strategic planning document.
Following completion of each SLT meeting, CONSULTANT will develop a written draft deliverable
combining the discussions from the SLT Meetings. The draft will be submitted to the SLT for review
and comment.
TASK 3— SUBJECT MATTER EXPERT(SME) PARTICIPATION
During the SLT meetings to develop the strategic plan, CONSULTANT may provide subject matter
experts to participate and provide input during the meetings.The SME staff are anticipated to be:
• William Adams—Operations & Maintenance
• Joseph Ridge—Asset Management and Financials
• James Carolan—GIS and Information Systems
• Bryan Cully—CIP and Engineering
• Karen Counes—Workforce Development and Human Resources
TASK 4— MANAGEMENT CONSULTING REVIEW AND INPUT
After review of the draft strategic planning document sections by the SLT(Task 2), CONSULTANT will
provide Management Consultants to review the content and approach developed. CONSULTANT will
provide written comments and discuss recommendations and comments with the Authority's Executive
to
Director.
TASK 5—STRATEGIC PLANNING DOCUMENT
Following review of the draft strategic planning document and incorporation of any review
comments from Task 4, CONSULTANT will engage technical writers and graphic artists to finalize the
individual sections of the Strategic Planning Document.
TASK 6—PROJECT MANAGEMENT
Activities performed under this task consist of those general functions required to perform required
administrative tasks, maintain the project on schedule, within budget, and that the quality of the work
products defined within this scope of services is consistent with CONSULTANT's standards and
AUTHORITY's requirements. Specific activities include project quality review of deliverables, periodic
internal team meetings, project start up and invoicing, and general administration of the Contract.
ASSUMPTIONS
1. SLT meetings will occur approximately once every two weeks. Up to 20 SLT meetings are
budgeted
2. 48 hours of CONSULTANT time has been budgeted per meeting for preparation,
documentation, and review of comments.
3. The SLT meeting topics will typically be structured so that one subject matter expert will be
needed for each meeting. 8 hours of SME time have been budgeted for each SLT meeting.
4. After each SLT Meeting, 20 hours have been budgeted for Management Consultant Review of
outcomes and summaries.
5. CONSULTANT level of effort is on a time and material basis. The level of participation is limited
to the upper limit unless otherwise amended.
DELIVERABLES SUMMARY
TASK DESCRIPTION FORMAT
1 Meeting Summary of the Initial Approach Discussion *.pdf
2 Up to 20 SLT Meeting Summaries documenting discussions *.docx or *.pdf
and outcomes from the meeting for SLR review.
4 Review comments on up to 20 SLT Meeting Summaries. *.docx or *.pdf
Review comments will be provided as annotated meeting
summaries, and a general write up outlining a general or
global comments.
5 Final Strategic Planning Document *.pdf
TIME OF COMPLETION/SCHEDULE
The CONSULTANT will begin work within 14 calendar days of receiving Notice to Proceed (NTP)from the
Authority. The estimated deliverables schedule associated with Tasks 1-5 are outlined below.A more
detail schedule will be presented within 30 calendar days after NTP. Note, some tasks will be occurring
concurrently.
TASK DESCRIPTION SCHEDULE
to
1 Meeting Summary of the Initial Approach Discussion Within 5 days
2 Up to 20 SLT Meeting Summaries documenting discussions Within 5 days of each
and outcomes from the meeting for SLR review. meeting
4 Review comments on up to 20 SLT Meeting Summaries. Within 2 weeks of SLT
Review comments will be provided as annotated meeting approval of draft
summaries, and a general write up outlining a general or
global comments.
5 Final Strategic Planning Document Within 30 days of final
SLT meeting
COMPENSATION AND PAYMENT
CONSULTANT will complete the work described in Tasks 1 through 5 on a time and materials basis not to
exceed $249,000. Invoices will be submitted monthly based on labor hours at the contractual billing rate
plus other direct costs.This upper limit will not be exceeded without prior written authorization by the
AUTHORITY. Estimated time and materials compensation for the various tasks are estimates only, and
the estimated values of the individual tasks can be exceeded, but the total upper limit for the project
cannot exceed.
EXHIBIT A
CONTRACT FEE SUMMARY
CLAY COUNTY UTILITY AUTHORITY
CIVIL AND ENVIRONMENTAL CONTINUING SERVICES
.....................................................................................
...............................................................................................................................................................................
Project :Proposal Number
CCUA Strategic Plan 2022 RFQ 18/19 NO.3
Name of Consultant iDate of Proposal
CDM Smith Inc. i 3/22/2022
PART:is l:X00W RELATtDM'ill$T$ . i.:E:.:
Labor Costs Hourly Estimated
Billing Rate Hours TOTAL
Engineer Grade 10/Expert 255.00 32 $ 8,160.00
Engineer Grade 9/Senior Professional 245.00 114 $ 27,930.00
Engineer Grade 8/Senior PM 215.00 248 $ 53,320.00
Engineer Grade 7/Senior Engineer 184.00 - $ -
Engineer Grade 5/6/Professional Engineer 153.00 - $ -
Eingineer Grade 3/4/Engineer 138.00 - $ -
Engineer Grade 2 123.00 1,240 $ 152,520.00
Engineer Grade 1 92.00 - $ -
Senior Tech Support 123.00 - $ -
Staff Technician 107.00 - $ -
Senior Field Tech 114.00 - $ -
Staff Field Tech 83.00 - $ -
Contract Administrator 123.00 - $ -
Document Control Specialist 101.00 12 $ 1,212.00
Administrative 86.00 40 $ 3,440.00
LABOR SUB-TOTAL •
1,686 i $ 246,582.00
DIRECT COSTS
Transportation,Per Diem and Equipment
Presentation Boards .
Reproduction .•
MISCELLANEOUS DIRECT COSTS SUB-TOTAL $ 2,418.00
SUBCONTRACTS
•
SUB-CONTRACT SUB-TOTAL •
TOTAL AMOUNT OF CONTRACT $ 249,000.00