Loading...
HomeMy WebLinkAboutFYI CO#2 with E. Vaughn Rivers, Inc for Maint Building Change Order PROJECT:(Name and address) CHANGE ORDER NUMBER: 2 OWNER CCUA New Warehouse and Site DATE: 03/15/2022 Improvements ARCHITECT 3176 Old Jennings Road CONTRACTOR ❑ Middleburg FL 32068 CONTRACTOR:(Name and address) ARCHITECT'S PROJECT NUMBER: 1483 FIELD E.Vaughan Rivers, Inc. CONTRACT DATE:11/01/2021 OTHER El 1882 Bellair Blvd.Park,Park, FL 32073 CONTRACT FOR: CCUA New Warehouse and Site Improvements The Contract is changed as follows: (Include,where applicable, any undisputed amount attributable to previously executed Construction Change Directives.) EVR:General Requirements 3,012.00 PAC:Add Bollards to East Canopies 10,260.00 PAC: Storm Structure/Sanitary Conflict Labor 1,000.00 PAC:ST 1 Modifications 2,500.00 PAC:ST5 Modifications 1,250.00 Insurance 450.55 Contractor Fee 1,847.26 c a, cc The original Contract Sum was $ 3,486 118.00 E The net change by previously authorized Change Orders $ 5,743.42 The Contract Sum prior to this Change Order was $ 3,491,861.42 d' The Contract Sum will be increased by this Change Order in the amount of $ 20,319.81 The new Contract Sum,including this Change Order,will be $ 3,512,181.23 The Contract Time will be changed by ( 0)days. The date of Substantial Completion as of the date of this Change Order,therefore,is (NOTE:This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive.) NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER.Owipe} J{4, Ai,,, attfi-P 4, E.Vaughan Rivers,Inc. btt, `(�° ��" u+i(i+ ,4 lAtt ARCHITECT(Firm name) CONTRACTOR(Firm name) OWNER(Firm name) 1882 Bellair Blvd j 6 61 d �w'�''fir (aril /329 zmit7st,i .4V i 5Th C Orange Park,FL 32073 y✓\; • © .$ ADDRESS AD%��j -' A DRESS Y(SO W•"'��''Jr:• r l�f' a imik Pi4vto 5 SNi✓s/ Stephen Rivers,Vice President ^ PE (Typed name) (Typo name (Typed name) EY.cc hK l— Vcc 1/17 ZO2 2 017V zDzz -a`-6 ^ �7 R DATE c E DATE Change Order Request#1 E. Vaughan Rivers, Inc. PROPOSED CHANGE ORDER TO: CCUA ATTN: Teri Shoemaker FROM: Stephen Rivers PROJECT: CCUA Warehouse SUBJECT: Clump Order 2 REQUESTED BY: EVR REF./DATE: 3/31/2022 DESCRIPTION OF WORK: SUB COST G.C.COST EVR:General Requirements $3,012 00 PAC:Add Bollards to East Canopies $10,260.00 PAC:Storm Structure I Sanitary Conflict Labor $1,000.00 PAC:ST 1 Modifications $2,500.00 PAC:ST 5 Modifications $1,250.00 tO Subtotal: $ 15,010.00 $ 3,012.00 General Liability Insurance: $ 450.55 Contractor Fee $ 1.847.26 TOTAL PRICE CHANGE I$ 20,319.81 Attachments: GENERAL REQUIREMENTS LABOR COST Hourly Rate Hours Total Superintendent $ 93.00 16 $ 1,488.00 Project Manager $ 89.00 16 $ 1,424.00 Total Cost $ 2,912.00 UPDATE RECORDS COST County Recording Fee $ 50.00 Drawing Reproduction $ 50.00 Total Cost $ 100.00 to License#CBC1260724—CUC1225348 Email:office@pacbuildersinc.com PREMIER AMERICi N Construction, Inc Business Address: 4613 U.S. Highway 17 Fleming Island, FL 32003 Mailing Address: PO Box 8668 Fleming Island, FL 32006 Revised CO #4 Proposal Date: 2/10 1 2022 Submitted To: EV Rivers 1882 Bellair Blvd Orange Park, FL Project Location: CCUA Maintenance Building Scope of Work: -Furnish and install 18 total Bollards for Generator Canopies to -To be installed per detail provided ...$570 Each Total for a qty of 18...$10,260.00 SU SMARM NOME OWN I O Q OF OVERHEAD DOORS 4-4 cONVE1ITOP i ;•�►+—rDIA ire IONGlEAWDUIY STEEL PIPE COM/41U VO 4 CONCREIEIPAINFWIFE S m NY .:a R ONDCOKREIE 1 ••— • r • • �� ,r:cotiat IE Imat 12 EXTERIOR BOLLARD A1002 *um vr.r.c License#CBC1260724—CUC1225348 Email:office@pacbullderslnc.com PREMIER I MERICI N Construction, Inc Business Address; 4613 U.S. Highway 17 Fleming Island,FL 32003 Mailing Address: PO Box 8668 Fleming Island, FL 32006 CO #7 Conflict Structure Proposal Date 3/8/2022 Submitted To: EV Rivers 1882 Bellair Blvd Orange Park, FL Project Location: CCUA Maintenance Building Scope of Work: to Furnish material and labor to modify Storm Structure for Sanitary Conflict: Option#1 r & Labor to modify structure: cost is$1000.00 T Option#2 _ 7act 81=Duettfe-fron--Steeve:-cost-ts1102- Labor to modify structure: cost is 1000.00 r-slat-for-rriatcwio Optional#3 8-R1l eii s-$8-16.28. Labor to modify structure: cost is$1000.00 Tom!-ier erysl-aR License#CBC1260724—CUC1225348 Email:office@pacbuildersinc,com PREMIER i MERIC1 N Construction, Inc License Address: 4613 U.S. Highway 17 Fleming Island, FL 32003 Mailing Address: PO Box 8668 Fleming Island,FL 32006 CO #8 ST#1 Modification Proposal Date 3/10/2022 Submitted To: EV Rivers 1882 Bellair Blvd Orange Park, FL 32073 Project Location: CCUA Maintenance Building 3176 Old Jennings Road Middleburg, FL.32068 Scope of Work: to Furnish material and labor to modify Storm Structure#1 for the purposes as described in RFI#16. This would require lowering the entire structure#1. A cutout would be required in the south side of the structure to match the existing pipe. This will require the top of structure to be added to specified grade. Cost for materials and labor: $2500.00 License#CBC1260724—CUC1225348 Email:office@pacbuildersinc.com PREMIER i MERICAN Business Address: 4613 U.S. Highway 17 Construction, Inc Fleming Island,FL 32003 Mailing Address: PO Box 8668 Fleming Island, FL 32006 CO #9 ST#5 Add 12" Riser Proposal Date 3/15/2022 Submitted To: EV Rivers 1882 Bellair Blvd Orange Park, FL 32073 Project Location: CCUA Maintenance Building 3176 Old Jennings Road Middleburg, FL.32068 Scope of Work: to Furnish material and labor to add 12" riser to Storm Structure#5 This would require lowering the entire structure#5.to accommodate North Invert of 12.40 And adding a 12" riser to get top grate elevation to 16.85 Cost for materials and labor: $1250.00 Jj 41g Zv Change Order PROJECT:(Name and address) CHANGE ORDER NUMBER: 2 OWNER n CCUA New Warehouse and Site DATE: 03/15/2022 ARCHITECT Improvements 3176 Old Jennings Road CONTRACTOR Middleburg FL 32068 CONTRACTOR:(Name and address) ARCHITECT'S PROJECT NUMBER: 1483 FIELD E.Vaughan Rivers, Inc. CONTRACT DATE:11/01/2021 OTHER 1882 Bellair Blvd.Park,Park, FL 32073 CONTRACT FOR: CCUA New Warehouse and Site Improvements The Contract is changed as follows: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives.) EVR: General Requirements 3,012.00( iAliV PAC:Add Bollards to East Canopies (i ) 4 y...w,;...v.-.,. y c:z.k (10,260.0e--> IMC:Add Electrical Security Pathways 10,574.30-- PAD VV.1--C -VJ ors"!/ Genesis: Change Order 25715 '.1,vvo,,,z, _Z605.25.� 9 ` c. L rri���x�+ Genesis:Change Order 25760 .,sb.a (;,.Y.b„ti g yv ya may, G� 1 1.1,799.96—? 1 PAC:78 Stone Geoweb Base __!�- _-43;100:00 - S�) I C �� PAC: Storm Structure/Sanitary Conflict Labor ( 1,000.00 , z51 - 9.,L.levuz__ PAC: ST 1 Modifications Vv\ - & 1-L., b((, 2,500.00 PAC: ST 5 Modifications 11r`lYE S tv\Gti,_) ou 0.5 1 , ,250.00 4I 1 5,11 to The original Contract Sum was WAX- LYNC..-c1 c..k- $ 3.486.118.00 The net change by previously authorized Change Orders $ 5.743.42 The Contract Sum prior to this Change Order was $ 3,491,861.42 The Contract Sum will be increased by this Change Order in the amount of $ 91.441.95 The new Contract Sum, including this Change Order,will be $ 3,583,303.37 The Contract Time will be changed by ( 0)days. The date of Substantial Completion as of the date of this Change Order,therefore, is (NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive.) NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. E.Vaughan Rivers, Inc. ARCHITECT(Firm name) CONTRACTOR(Firm name) OWNER(Firm name) 1882 Bellair Blvd a Park, FL 32073 ADDRESS ADDRESS BY(Signature) )4nai BY(Signature) Stephen Rivers,Vice President (Typed name) (Typed name) (Typed name) 3/15/2022 DATE DATE DATE Change Order Request#1 E. Vaughan Rivers, Inc. PROPOSED CHANGE ORDER TO: CCUA ATTN: Teri Shoemaker FROM: Stephen Rivers PROJECT: CCUA Warehouse SUBJECT: Change Order 2 REQUESTED BY: EVR REF./DATE: 3/15/2022 DESCRIPTION OF WORK: SUB COST OL COST EVR: General Requirements $3,012.00 PAC:Add Bollards to East Canopies $10,260.00 IMC:Add Electrical Security Pathways $10,574.30 Genesis: Change Order 25715 $7,605.25 Genesis:Change Order 25760 $1,799.96 PAC:78 Stone Geoweb Base $43,100.00 PAC:Storm Structure/Sanitary Conflict Labor $1,000.00 PAC:ST 1 Modifications $2,500.00 PAC:ST 5 Modifications $1,250.00 tO Subtotal: 1 $ 78,089.51 i$ 3,012 00 General Liability Insurance: $ 2,027.54 Contractor Fee $ 8,312.90 TOTAL PRICE CHANGE I $ 91,441.95 Attachments: