HomeMy WebLinkAboutEDB CO No 1 Admin Building Phase I EXECUTIVE SUMMARY AGENDA ITEM: Ratification of Change Order No. 1 to New Administration Building Expansion Phase I CCUA Project No.: 4020-004 CCUA Financial Project Code: 21013AD Date: February 17, 2023 BACKGROUND: KBT Contracting Group commenced construction of the new Administrative Building Expansion Phase I. After the contract was awarded to KBT Contracting Group, the Bhide and Hall Architects, P.A. (BHA), needed to change the Engineer of Record(EOR)from Michelle Agee P.E.to Jones Edmunds and Associates (JEA). The reason from the change in the EOR was due to Ms. Agee's passing. In taking over the EOR responsibilities,JEA recommended changes to the stormwater conveyance design with the addition of pipe and a storm structure. Because this change in the stormwater conveyance design was after the bid, KBT Contracting is entitled to a change. BHA and JEA completed design efforts without passing these design change costs to CCUA.However,the design change does represent an increase in costs the contractor would be entitled to.BHA and staff agreed the lump sum amount of$36,657.70 represented reasonable costs associated with the required resources f° -a and materials to complete the work. c a) The Board of Supervisors previously authorized staff to approve change orders of$50,000 or 5% of the ° contract cost which ever is less. This direction from the Board of Supervisors is within Board meeting c minutes, not within a readily available staff policy. Staff errored in already authorizing the change order 15 due to the change representing a 7% change in the contracted project costs. Staff requests ratification of staffs action by the Board of Supervisors. Staff will bring a formal update to the purchasing policy with the $50,000 or 5%requirements to prevent such errors in the future. Staff previously disclosed to the Board of Supervisors the current budget for the project. Staff had noted Change Order No. 1 as a separate authorization. The project budget remains consistent with the previously disclosed numbers. BUDGET: Administrative Complex Expansion Budget: $5,125,089 Design and Bidding Services with BHA: $192,444.99 Construction Administrative Services with BHA: $93,071.60 Construction Services with KBT: $4,647,007 Sub-Total Design and Construction Services: $4,932,523.59 Project Contingency: $192,565.41 Physical Security Improvement Evaluation by BHA: $7,200 Change Order No. 1 (Stormwater Conveyance Changes): $36,657.70(Ratification Request) Remaining Project Contingency: $148,707.71 //JDJ //AB //JDJ RECOMMENDATION: Staff request the Board of Supervisors ratify staff's action regarding Change Order No. 1 CCUA Administration Building Expansion Phase I. ATTACHMENTS: Change Order No. 1 dated February 3,2023 BHA's Entitlement Recommendation dated January 30, 2023 //JDJ //AB //JDJ ' I. • / • 1. • 1. 1 1 I i 1 j) 6in*oyl x,prrhrr m prowl pxhh,hrahh.axurrn'our Clay County Utility Authority nuan,1 n.munY,.and mul• /p ,rpfi rmrpaprn. W 3176 Old Jennings Road Middleburg.Florida 32068-3907 Telephone(904)213-5999 Facsimile (904)213-2498 Project New Administration Building Expansion and Site Improvements CCUA Bid No.21/22-All CCUA Project No.4020-004 Change Order No. 1 Date: 2/3/2023 Vendor KBT Contracting Corp. Owner: Clay County Utility Authority 5105 Blanding Boulevard Jacksonville,Florida 32210 • CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO NTP 1/27/2023 1/27/2023 DAYS ADD SUB.COMP 1/12/2024 1/12/2024 FINAL COMP 1/27/2024 1/27/2024 INCREASE OR DECREASE IN ITEM DESCRIPTION OF CHANGE(S) QTY. UNIT PRICE CONTRACT PRICE Contract Increase Additional 48 LF 24"RCP,additional Type"C" $36,657.70 to inlet,and additional demolition of existing 1 sidewalks 1 LS 2 3 4 5 Contract Decrease 1 50.00 2 50.00 3 $0.00 4 $0.00 5 $0.00 ORIGINAL CONTRACT PRICE $4,600,705.00 Net Increases by Change Orders(prior to this change order) $0.00 Net Decreases by Change Orders(prior to this change order) $0.00 Total Net Change by Change Orders(prior to this change order) $0.00 CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $4,600,705,00 NET CHANGE RESULTING FROM THIS CHANGE ORDER $36.557.70 CONTRACT PRICE INCLUDING THIS CHANGE igiDER $4,637,362.70 This document shall an amendmen tlth•contract and all provisions of the contract will apply hereto. Accepted by: Date: ,/3/Z-5 A ' ct ngln (Record Accepted by digErti Date: c t `J !V1 Accepted by: 1� �r r Date: ZO 2 3 —c:U 2 —Ci 7 Qw ',- Project: New Administration Building Expansion and Site Improvements CCUA Bid No.: 21/22-All CCUA Job File No.4020-004 Summary of Change Orders Date Description Contract Net Increase Net Decrease Revised Contract 1/27/2023 Original Contract Price: $4,600,705.00 Change Order No.1:Storm structure&pipe and additional $36,657.70 2/1/2023 sidewalk demolition Summary of Totals: $4,600,705.00 $36,657.70 $0.00 $4,637,362.70 Summary of Totals: Summary of Totals: Summary of Totals: to SECTION 00660 Change Order Request Form Project:New Administration Building Expansion and Site Improvements Project No.: 4020-004 Change Order No.:1 Change in Contract Times (Days) (Days) Original Contract time: Substantial Completion: 350 Ready for Final Payment: 365 Increased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0 Decreased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0 Contract time prior to this C.O.: Substantial Completion: 350 Ready for Final Payment: 365 Increase in time on this C.O.: Substantial Completion: 0 Ready for Final Payment: 0 Decrease in time on this C.O.: Substantial Completion: 0 Ready for Final Payment: 0 Contract time with all approved C.O.s: Substantial Completion: 350 Ready for Final Payment: 365 Change in Contract Price Original Contract Price: $4,600,705.00 Increased from previously approved C.O.: $0.00 Decreased from previously approved C.O.: $0.00 Increase in Contract price this C.O.: $36,657.70 Decrease in Contract price this C.O.: $0.00 Contract price with all approved C.O.s: $4,637,362.70 The undersigned Contractor certifies to the best of my knowledge and belief: (1)all items and amounts shown above are correct; (2) all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3)all previous progress payments received from Clay County Utility Authority(CCUA) ,on account of Work done under the Contract to referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by prior Applications for Payment; (4)title to all materials and deliverables incorporated in said Work or otherwise listed in or covered by this Application for Payment will pass to the CCUA at the time of payment clear of all liens,claims, security interests and encumbrances; (5)payment is due and has not been previously requested for these amounts;(6)no markup has been applied to reimbursable expenses. KBT Contracting Corp,Vice President Contractor Name and Title Cost Break Down Form: (instructions: use a separate form for each individual work item) 00660-1 CCUA Project No.4020-004 CHANGE ORDER REQUEST FORM NEW ADMINISTRATION BUILDING EXPANSION AND SITE IMPROVEMENTS 04-01-2022 SECTION 00660 Change Order Request Farm Iti..r lien l Dili ltu:, l it t Civil Subcontrac orCost(Quote arached) IS 1 S27,432.45 $27,432.45 _ 5%Contractor Fee for Subcontract Cost LS 1 $1.371.62 $1,371.62 Project Manager-Labor Cost HR 16 $62.50 S 1.000.00 Superintendent-Labor Cost HR 48 $59.38 S 2.850.24 Administration-Labor Cost HR 16 $46.88 S 750.08 Executive-Labor Cost HR 8 _ $96.00 $768.00 Additional GL Exposure 2%(General Conditions) LS 1 S683.45 $883.45 15%Contec1or Fee on Contactor Cost LS 1 $907.77 S 907.77 Additional Bond Cost 2.5% LS 1 $894.09 $894.09 Total arm fixed cost eat te exceed amorort $36,657.70 Note:attached supporting documentation RFI No,initiating the change: Description: Change in Scone due to revised civil drawings from bid set. The change reflects additional RCP piping show on drawings,the initial design contained 122 LF and revised provides 164 LF the delta is 42 LF of 24"RCP.An additional structure ST-2 was added to plans and demolition of existing sidewalks were added to the demolition plan. Justification for the request: Additional requested scope of work from revised civil drawings issued on 9/22./22. to State the firm fixed cost not to exceed amount in words: Accepted AV.' - - . Date: ariaWl.- connector Accepted by (• ( ' i 6P• ? zo Accepted by. Wik,%1Ialakt..„..iggi 04>Z 3 —ca7 . 11) 90660-2 cnuA P'oj.a No 4020004 CHANGE ORDER Kama FORM NEW AtIMINLSTIA11011 BUILDING EXPANSION MD SITE IMPROVEMENTS 01-01 2 Bhide & Hall Architects, P.A. AR0011549 117) Architect and FOR Entitlement Recommendations. Change Order No. 1 to New Administration Building Expansion and Site Improvements Contract with KBT Contracting Group. (KBT)Job File No. 4020-004 Date: January 30, 2023 KBT (The Contractor) is providing construction services for the New Administration Building Expansion and Site Improvements Project at the Old Jennings Road facility. Change order 1 is the proposed amount associated with a Change in Scope due to revised civil drawings from bid set. The change reflects additional RCP piping shown on drawings, the initial design contained 122 LF and revised provides for 164 LF the delta is 42 LF of 24" RCP. An additional structure ST-2 was added to plans and demolition of existing sidewalks were added to the demolition plan. to The demolition scope of sidewalk is appropriate when considering the existing sidewalk runs under the new building footprint and the connection of new water service line to the east. (Reference Sheets C101 and C300) Difference in RCP piping.—routed to avoid underground utilities and disturb less site area. VV , .,� ...Vm ,.. . .�\ .. i • r- i I IA BH#000000 1329-C Kingsley Avenue, Orange Park, FL 32073 Page 11 (904)264-1919 I www.bhide-hall.com r LbBhide & Hall Architects, P.A. r-1 AR0011549 Difference in sidewalk demolition: 4N ' /l // . // / / / / // /'/ / / 1=3,,,,di c / / / / / /// // A'/ / / .1.4a / A / / A '..- - ' 4 ..rfr r—T- ,.,-.7;%'. 1' ..AritreAll 1 " i 1•.•:. i 1201.4' : smw wcr,rrc me r. ► oaw aaacsa�s O SKVWEASSNOW MAU.t Y ,,. to / .. / / / . / ./ / // ..-,,r/ / / / / / / / ,..::., L).-• .a6r+: - � .�_ti . •i sksy•.. .,`� : r /....... • .:.......H. .....;;,;.. /I. MOM MUM PR NI II OK NM.NII• /i I'i i//,♦/.Ili I'0 WOW NM ftR 'MR�MV•Of4/S MYO11M / I /�I I �//I' � I I II � I ii BH#000000 1329-C Kingsley Avenue,Orange Park,FL 32073 Page 12 (904)264-1919 I www.bhide-hall.com 1+--) Bhide & Hall Architects, P.A. AR0011549 FOR has reviewed the proposal and responded with the following comments: CO#1—Additional 48 LF of 24"RCP, additional Type "C"inlet(ST-2), and additional demo of existing sidewalks is appropriate. The Contractor submitted a change order request for a lump sum amount of $36,657.70 on December 21, 2022 to perform the work described.The cost includes The Contractor's and their subcontractors' costs with customary overhead and profit. CCUA staff entered negotiations with KBT, and both parties have agreed to pursue a Change Order Request of$36,657.70 and extend the contract time by 00 calendar days. The negotiated lump sum amount represents reasonable costs associated with the required resources and materials to complete the requested work. Budget: to The project construction budget was$4,600,705.00 The project construction budget with Proposed Change Order No. 1 will be$4,637,362.70. Carl Burdick - RA, NCARB Sr. Architect Bhide & Hall Architects, P.A. AAC-000569 Tel: 904-264-1919 MOININOISINY BH#000000 1329-C Kingsley Avenue, Orange Park,FL 32073 Page 13 (904)264-1919 I www.bhide-hall.com