HomeMy WebLinkAboutEDB GP WW LS Project and GP Reclaimed WPS Project EXECUTIVE SUMMARY
AGENDA ITEM:
Proposed award of contract to Sawcross, Inc. for the Governor's Park Wastewater Lift Station and
Reclaimed Water Storage and Pump Station Project(GP LS/RWPS Project) Bid No. 2022/2023-A06
CCUA Project No.: 2211-0042
CCUA Financial Job No.: 22003SP
Date: March 3,2023
BACKGROUND:
The subject project consists of one (1) of three (3)project components to provide wastewater treatment
service and reclaimed water service in both the Peters Creek and Governor's Park service territories. The
Governor's Park Lift Station will transmit wastewater to the expanded Peters Creek Water Reclamation
Facility(WRF). The Governor's Park Reclaimed Water Storage and Pump Station will receive reclaimed water
from the Peters Creek WRF to serve the future customers in the Governor's Park and surrounding developments.
The other components of the Peters Creek WRF expansion were or are being presented under separate
a executive summaries for the Board's consideration and approval. The Board of Supervisors approved
the site civil portion of the Governor's Park site at the January 3,2023,Board meeting. The main Peters
Creek WRF and pipelines are being presented at today's meeting.
Staff advertised the GP LS/RWPS Project on CCUA's Bonfire Procurement Platform on October 20,
cc
2022, and in the Florida Times Union on October 24, 2022. At the February 17, 2023, Bid Opening,
CCUA received(3)three bids from the following Contractors:
Contractors Submitting Bids I Bid Amount
'Petticoat-Schmitt Civil Contractors, Inc_ S8.551,000
Wharton-Smith S7.880.000
Sawcross_ Inc. S7,683,000
The Clay County Utility Authority's (CCUA's) consultant and Engineer of Record (EOR), David
Rasmussen, P.E., QEP, BCEE of Ardurra Group, Inc. along with CCUA staff evaluated the bids for
conformance with the solicitation requirements. Both the EOR and staff and determined Sawcross, Inc.
submitted the lowest, responsive bid at a total lump sum bid price of$7,683,000.
BUDGET:
Staff continues to work through the Capital Improvement Program (CIP) contingencies and project
delays to accommodate the Peters Creek and Governor's Park Projects. Staff identified$20,609,249.82
in CIP contingency and $75,249,273.06 in potential projects in the current and next fiscal year that
could be delayed to accommodate construction of these projects. Staff itemized the intended project
budgets and contracts below. Staff will present an updated CIP at an upcoming Board of Supervisors
meeting.
Capital Improvement Program(CIP) Budgets:
Peters Creek WRF Phase II: $ 43,819,540.00
Peters Creek WRF Land Acquisition: $ 3,000,000.00
Project Transfers from Delayed Projects: $ 41,524,718.08
Total CIP Project Budget: $ 88,344,258.08
Current and Proposed Contracts:
Original Design and Bidding Services with Ardurra: $ 3,564,608.00
Previous Change Orders for Interim Modifications: $ 76,960.80
Design and Bidding Amendment#3 with Ardurra: $ 690,013.00
Peters Creek Pre-purchase of Equipment: $ 15,492,603.20
Peters Creek WRF Expansion with Wharton Smith: $ 55,088,600.00
Governor's Park Site Civil with PSCC: $ 1,905,000.00
Governor's Park LS and RWPS with Sawcross, Inc.: $ 7,683,000.00
Governor's Park Pre-Purchase Equipment: $ 609,643.08
Sub-Total Design and Construction Services Contracts: $ 85,110,428.08
Total Construction Contingency: $ 3,233,830.00
Total Design and Construction Services Contracts: $ 88,344,258.08
RECOMMENDATION:
Staff respectfully requests the Board of Supervisors approve the award to Sawcross, Inc. of the
Governor's Park Wastewater Lift Station Project and Governor's Park Reclaimed Water Storage and
Pump Station Project. Additionally, Staff requests approval of the attached Bid Documents.
ATTACHMENTS:
Florida Times Union Advertisement Pre-Bid Meeting Attendance
Bid Opening Attendance
Engineer of Record Recommendation and Bid Tabulation
//DP(Author)
//DD,AB,PS (Review)
//PS (Final)
LOCALiQ
FLORIDA PO Box 631244 Cincinnati, OH 45263-1244
IPROOF OF PUBLICATION TO BID
NOTICEnTATION ISIHEREBY GIVEN THAT
Clay County Utility Authority
Angelia Wilson (AUTHORITY), Clay County,
Accounts Payable Florida, will be accepting sealed
Y Bids for ITB# 22/23-A06 Governor's
Clay County Utility Auth Park Wastewater Lift Station
3176 Old Jennings RD Project and Governor's Park
ANGELIA WILSON Reclaimed Water Pump Station
Project, which will be received until
Middleburg FL 32068-3907 2:00 P.M. (EDT), December 19,
2022,at the following location:
The complete Solicitation package
STATE OF FLORIDA,COUNTIES OF DUVAL AND CLAY can b: obtained by visiting:
https://clayuti I ity.bonfirehub.com/po
rta I/?tab=openOpportun iti es.
The Florida Times-Union,a daily newspaper published in Submissions must be posted to the
Jacksonville in Duval and Clay County, Florida;And of general Clay County Utility Authority
circulation in Duval and Clay County;and personal knowledge of at BonfirepProcurement Portal located
om.
the facts herein state and that the notice hereto annexed was (hardcopies will
not be accepted).
cre to ).
will not be accepted).
Published in said newspapers in the issues dated or by publication A Pre-Bid Meeting (herein so
on the newspaper's website, if authorized,on: called) will be held Wednesday,
November 2, 2022, at 1:00 P.M
10/24/2022 (EDT) at the following location:
Clay County Utility
Authority Boardroom
and that the fees charged are legal. 3176 Old Jannings Road
Sworn to and subscribed before on 10/24/2022 Middleburg, Florida 32068
All questions and concerns regard-
ing this Solicitation must be submit-
ted on the CCUA Bonfire Procure-
ment portal
https://clayuti lity.bonfirehub.com
prior to 12:00 P.M. (EDT) on
Monday, November 21, 2022. Late
questions may be answered at the
C°j1161—
discretion of CCUA. All responses to
questions will be uploaded to the
Portal and issued in an Addendum
on Monday, December 5, 2022.
Legal Clerk CCUA reserves the right to change
`� iL In p� Q the time and date of the Pre-Bid
V` ") Meeting, to change the Bid due date
Notary,State of WI,County of Brown and time, to waive formalities in
C1
S r any Bid, to reject any or all Bids
with or without cause, and/or to
Mycommision expires accept the Bid or any portion
P thereof that, in the CCUA'S sole and
Publication Cost: $92.04 absolute ludgment, will be in the
best interest of CCUA.
Order No: 7951023 #of Copies: 10/24/2022
Customer No: 759750 1
PO#: 23-35208
THIS IS NOT AN INVOICE!
Please do not use this form for payment remittance.
IVIARIAH VERHAGEN
Notary Public
State of Wisconsin
II Page 1 of 1
tr. PRE-BID MEETING SIGN-IN SHEET
GOVERNOR'S PARK INTERIM WTP AND GOVERNOR'S PARK PRELIMINARY CIVIL WORK
CCUA Bid No. 22/23-A07
Date: November 2, 2022, 1:00 P.M. (EDT)
Name Company E-Mail Address
Darrin G. Parker Clay County Utility Authority dgparker@clayutility.org
Angelia Wilson Clay County Utility Authority awilson@clayutility.org
Paul Steinbrecher Clay County Utility Authority psteinbrecher@clayutility.org
Joe Paterniti Clay County Utility Authority jpaterniti(c�clavutility.orq
Dave Rasmussen Ardurra Rasmussen@ardurra.com
0
Mike Pekkala Dewberry mpekkala@Dewberry.com
Damon Alexander R2T damon.alexander@R2Tinc.com
Gorger "Bubba" Cundiss William Ind
Chase Rachal Sawcross chaser@sawcross.com
Mike Higginbotham Wharton Smith mhigginbotham@whartonsmith.com
Joby Jett SGS Contracting joby@sgscsi.com
Jason Farkais PSCC jfarkas@petticoatschmitt.com
Nathan Podson PSCC npdson@petticoatschmitt.com
Darrell Damrow CCUA ddamrrow(aclayutility.org
Gary Rivello R2T Gary.Riverllo@R2Tinc.com
David Lassiter Ardurra wdlass@bellsouth.net
Lee Hilbert Godwin Pumps lee.hilbert@xylem.com
BID OPENING SIGN-IN SHEET
Governor's Park WW LS and Governor's Park Reclaimed Water Pump Station Project
CCUA Bid No. 22/23-A06
Date: December 19, 2022
Name Company E-Mail Address
Angelia Wilson Clay County Utility Authority awilsonna,clayutility.org
Paul Steinbrecher Clay County Utility Authority psteinbrecher(a�clayutility.org
Dave Rasmussen Ardurra drasmussenc ardurra.com
Mike Pekkala Dewberry mpekkala(adewberry.com
to
ARDURRA
February 20,2023
Angelia C.Wilson
Procurment Manager
Clay County Utility Authority
3176 Old Jennings Road
Middleburg,Florida 32068
RE: Clay County Utility Authority
Governor's Park Wastewater Lift Station and Reclaimed Pump
100 Center Creek Rd.
Unit 108 Station Project
St.Augustine,FL 32084 CCUA Project No.: 1127-004
CCUA Bid No.: 2022/2023-A06
0 Ardurra Project No.: 100435.07
904-562-2185 Bid Review and Evaluation of Findings
Dear Ms.Wilson,
0 This letter summarizes the construction contract bids received for the
www.ardurracom Governor's Park Wastewater Lift Station and Reclaimed Pump Station Project.
to Clay County Utility Authority (CCUA) opened the project on the Bonfire
Procurement Platform on October 20, 2022. Three bids were uploaded to the
Bonfire Procurement Platform on February 17, 2023, at 11:00 am. Based on the
interest from three contractors, Ardurra Group, Inc. believes the project was
well advertised.Three base bids ranged from$7,683,000.00 to$8,551,000.00.The
bid tabulation form is attached.
Sawcross,Inc. submitted the lowest base bid for$7,683,000.00. Ardurra Group,
Inc. has reviewed the Sawcross, Inc. bid package provided by CCUA with the
following findings:
• The Addendums were acknowledged on the Bid Form.
• The Bid Bond was provided,and the Bid Bond surety is licensed in
Florida.
• Sawcross,Inc. is not a federally debarred contractor.
• Ardurra Group, Inc. ran a Dunn & Bradstreet report on Sawcross,
Inc.which indicated no high-risk concerns for the company.
• Ardurra Group, Inc. investigated the Contractor's experience,
reputation, performance, past projects, and outstanding projects
and finds the Contractor appears capable to perform the scope of
work for this project.
While the final determination of which contractor will be awarded this project
will be made by CCUA,Ardurra Group, Inc. believes the bid to be responsive
and, based on the findings above, does not take exception to awarding the
1
February 20,2023
project to the low bidder,Sawcross, Inc. for the total contract amount of$7,683,000.00.
If you have any questions or comments, feel free to contact me at (904) 562-2185 or
drasmussen@ardurra.com.
Sincerely,
ARDURRA GROUP,INC.
avid Rasmu sen,P.E.,QEP, BCEE
Project Manager
to
2
ITB# 22/23-A06 GP WW LS PROJECT AND GP RECLAIMED WPS PROJECT BID TABULATION SHEET
Item Description Petticoat-Schmitt Sawcross Wharton-Smith
1 General and Administrative $ 961,000.00 $ 100,000.00 $ 325,000.00
2 4.0 mgd Wastewater Lift Station $ 3,339,000.00 $ 720,000.00 $ 3,150,000.00
3 Reclaimed Water Pump Station and GST $ 4,146,000.00 $ 6,758,000.00 $ 4,300,000.00
4 Clay Electric Alloowance $ 10,000.00 $ 10,000.00 $ 10,000.00
5 Geotechnical Investigation Allowance $ 20,000.00 $ 20,000.00 $ 20,000.00
6 Laboratory Testing Allowance _ $ 50,000.00 $ 50,000.00 $ 50,000.00
7 Clay County Building Department Allowance $ 25,000.00 $ 25,000.00 $ 25,000.00
Total $ 8,551,000.00 $ 7,683,000.00 $ 7,880,000.00