Loading...
HomeMy WebLinkAboutEDB Update on Capital Projects Bid vs OPCC AGENDA ITEM: EXECUTIVE SUMMARY Update to Board of Supervisors Regarding Recent and Historical Construction Bids vs Opinions of Probable Construction Cost(Bid/OPCC ratio). Date: March 16,2023 BACKGROUND: The water utility heavy construction market has become saturated with projects in the past year. Capacity constraints on contractors are resulting in fewer bids on publicly bid projects,and higher bid prices relative to the Engineers Opinion of Probable Construction Cost(OPCC). Staff will review the most recent 3 years of bidding trends to show this recent departure in the Bid/OPCC ratio. Staff will continue to manage the CIP and associated projects accordingly. as ATTACHMENTS: c m cc Summary Table of Bids and OPCC by Project o r Bid/OPCC vs Time Chart c L m //PS(Author) ce //AA(Review) //PS(Final) CCUA Bid Information Bid Date OPCC Winning Bid Range Low Bid High Bid Project Description Number Month/Year (Millions) (Millions) (Millions) (Millions) (Millions) of Bidders Fleming Island Oct-20 New BTU,Yard Piping,Headworks Mod $7.4 $6.3 $6.3 $8.4 $6.3 $8.4 8 BTU Expansion Mid-Clay Oxidation Ditch,additional Filter, Aug-21 $6.9 $7.1 $7.1-$9.5 $7.1 $9.5 7 BTU Expansion headworks improvements Meadow Lakes Electrical upgrades,associated piping,well Oct-21 $3.0 $2.7 $2.7-$3.1 $2.7 $3.1 3 WTP Expansion pumps _ Saratoga Springs Dec-21 New WTP,RW Storage&Pump Station $14.9 $13.5 $13.5-$16 $13.5 $16 3 WTP&RWF Ridaught Water Plant Aug-22 GST Rehab& Minor Plant Modifications $0.7 N/A $1.4-$1.5 $1.4 $1.5 2 Tank Rehab Ridaught Oct-22 Plant Rehab $3.6 $3.5 $3.5-$4.4 $3.5 $4.4 4 WRFR&R _ Governor's Park Oct-22 Lift Station&Reclaimed Water $6.6 $7.7 $7.7$8.6 $7.7 $8.6 3 LS&RWPS Regional Pumping Facility Peters Creek Dec-22 Expanded WRF&Pipeline $54 $81 N/A N/A N/A 1 WRF Governor's Park Dec-22 New WTP $2.4 N/A 55.0-$6.7 $5.0 $6.7 3 WTP Lift Station 3 Jan-23 Demo Exisiting LS&construct new LS $0.9 N/A N/A N/A N/A 0 t0 Improvements Lowest Bid/OPCC 2.5 Gov Park Ridaught WTP • Project Bid WTP Tank 3 2 2 Rejected or No Bid Peters Creek 1 1.5 • Gov Park 0 Mid-Clay BTU LS&RWPS Expansion 3 N 7 1 I • • • Fleming BTU Ridaught WRF 8 Meadow Lakes Saratoga Springs 4 WTP Expansion WTP &WRF 0.5 3 3 Lift Station 3 t0 Improvements 0 NO- Opt 2� Feb-21 NO- Oe�-2� Feb- )0\- Oe Feb-73 Bid Opening Date