Loading...
HomeMy WebLinkAboutFYI Fleming Island Clarifier CO1 Return to a s enda Change Order Request Form Project: Fleming Island WWTF Clarifier No. 1 Rehabilitation Change Order No.: 1 Change in Contract Times (Days) (Days) Original Contract time: Substantial Completion: 300 Ready for Final Payment: 330 Increased from previous C.O.: Substantial Completion: Ready for Final Payment: Decreased from previous C.O.: Substantial Completion: Ready for Final Payment: Contract time prior to this C.O.: Substantial Completion: Ready for Final Payment: Increase in time on this C.O.: Substantial Completion: 327 Ready for Final Payment: 357 Decrease in time on this C.O.: Substantial Completion: Ready for Final Payment: Contract time with all approved C.O.s: Substantial Completion: Ready for Final Payment: Change in Contract Price Original Contract Price: $737,474.14 Increased from previously approved C.O.: Decreased from previously approved C.O.: Increase in Contract price this C.O.: 0 Decrease in Contract price this C.O.: Contract price with all approved C.O.s: The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2) all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all previous progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by prior Applications for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered by this Application for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and encumbrances; (5) payment is due and has not been previously requested for these amounts; (6) no markup has been applied to reimbursable expenses. Steven Kelley- R2T Project Manager Contractor Name and Title CCUA Project No: 1111-028 CDM Smith Project No.259164-254937 CHANGE ORDER REQUEST FORM Meadow Lake WTP Expansion Project November 2021 Return to a'enda Change Order Request Form Cost Break Down Form: (instructions: use a separate form for each individual work item) Description Unit Quantity Unit Cost Extended Cost Labor $ Materials $ Equipment $ Maintenance of Traffic $ Bonding $ General Conditions $ Overhead and Profit $ Total firm fixed cost not to exceed amount:MEW $ Note: attached supporting documentation RFI No. initiating the change: Description: Lakeside scheduled to have the new spirovac delivered and on site by 2/2/2023 after the submittal was released . Lakeside PO was issued 5 days after NTP (5/24/22), submittal was released on 8/8/22 after FOR review. Justification for the request: R2T is requesting an additional 27 days to contract duration due to the longer than anticipated delivery schedule of equipment that was out of our control. We will need this additional time in order to install the unit and grout prior to startup services. State the firm fixed cost not to exceed amount in words: Contractor Signature: )Jiri rgev 0 Date: 3/20/23 Printed Name: Steven Kelley Title: Project Manager CCUA Project No:2203-137 Fleming Island WWRF Clarifier No. 1 CHANGE ORDER REQUEST FORM Rehabilitation November 2021 Return to agenda Steven Kelley From: Todd Shaw <Its@trippenseeshaw.com> Sent: Thursday, November 3, 2022 4:10 PM To: Steven Kelley Cc: Fred Trippensee (fwt@trippenseeshaw.com) Subject: Fleming Island - Clarifier Ship Date Steve, The clarifier is schedule to ship 2/3/2023. Todd L.Todd Shaw, PE m.407.222.0575 I LTS@TrippenseeShaw.com I www.TrippenseeShaw.com 91 TRIPPENSEE loll SHAW 1 Return to agenda +-. _ LAKES ! DE 1022 E. Devon Avenue I P.O.Box 8448 I Bartlett, IL 60103 �� T:630-837-5640 I F:630-837-5647 I E:sales@lakeside-equipment.com EQUIPMENT CORPORATION www.lakeside-equipment.com Water Purification Since 1928 January 31, 2023 R2T, Inc. 580 W. Crossville Rd. #101 Roswell, GA 30075 Attention: George Tomeh Subject: FLEMING ISLAND, FL Fleming Island Regional WRF Customer P.O.#F022000301.02 S.O. #22-142 Dear Mr. Tomeh: Our shop has indicated they have a delay in getting the material for the fabrication of the Clarifier. This delay has caused the ship date to be scheduled for the week of February 27, 2023 shipment. This date is also dependent on the galvanizing company which is utilized after the weldments are fabricated. The steel suppliers scaled back when the COVID-19 pandemic was starting due to the unknowns and used up the inventory they had on hand. Now the global recovery to the Covid-19 pandemic is underway driving a surge in demand for goods across many industries. Demand is outpacing supply and obtaining many basic materials is becoming more difficult. Especially with the increase in steel orders, the steel mill lead time for shipments has increased and or in some cases is not available. To address this situation, the Lakeside Equipment Corporation supply chain team is in continuous communications with the supply base to secure materials, provide advance forecasts, and expedite production and shipments as much as possible. This team is also looking into alternative sourcing strategies and shipping means as long as these methods meet our strict quality requirements. We will do all we can to improve the shipment of the equipment. We hope this helps explain the delay.We apologize for any inconveniences this has caused. Our shop is working overtime to help minimize the shipping delay. If we could further clarify any points,please do not hesitate to call. Regards, iiievoi\ g4),A, Jim Snyder Engineering Manager