Change Order No. 2 Date: April 4, 2023
Project: Mid-Clay WWTF Phase II Expansion
CCUA Bid No.: 19/20-A11
CCUA Project No.: 2205-077
Vendor: Wharton-Smith, Inc. Owner: Clay County Utility Authority
750 Monroe Road 3176 Old Jennings Road
Sanford, Florida 32771 Middleburg, FL 32068
(407)321-8410 (904)272-5999
Engineer: Mittauer&Associates, Inc.
580-1 Wells Road
Orange Park, FL 32073
(904)278-0030
CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 12/8/2021
DAYS ADD 0 0
SUB. COMP 485 4/7/2023 4/7/2023
FINAL COMP 515 5/7/2023 5/7/2023
to
INCREASE OR
R
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) QTY, UNIT PRICE CONTRACT PRICE
c Contract increase
1
r Hatches at aerator deck 1 $1,620.00
c Contract Decrease
Change Order No.2:Cost deduct for material not
1 used $ (4,045.00)
•
TOTAL INCREASE $ 1,620.00
TOTAL DECREASE $ (4,045.00)
NET CHANGE RESULTING FROM THIS CHANGE ORDER $ (2,425.00)
ORIGINAL CONTRACT PRICE $ 7,097,000.00
Net Increases by Change Orders(prior to this change order) $ -
Net Decreases by Change Orders(prior to this change order) $ (1,945,008.20)
Total Net Change by Change Orders (prior to this change order) $ (1,945,008.20)
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 5,151,991.80
NET CHANGE RESULTING FROM THIS CHANGE ORDER $ (2,425.00)
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $ 5,149,566.80
This document shall become endment to the contract and all provisions of the contract will apply hereto.
Accepted by: T l mo -i ('. M ca.reW-1 . P F_ Date: L3 I L-14 Z3
Engineer of Record
Accepted by: Mike Higginbotharh g .- ^ °H .r-„_„ Date: 4/4/23
Vendor /
Accepted by: Date: Z.o2-3 -O`'f"-0(0(0- •_
er
SECTION 00660
CHANGE ORDER REQUEST FORM
Project, Mid-Clay WWTF PhaseIl Expansion Project No.: 2205-077
Clay County Utility Authority Change Order No.:Two(2)Final
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion:510 Ready for Final Payment:
Increased from previous C.O.: Substantial Completion:0 Ready for Final Payment:
Decreased from previous C.O.: Substantial Completion:0 Ready for Final Payment:
Contract time prior to this C.O.: Substantial Completion:0 Ready for Final Payment:
Increase in time on this C.O.: Substantial Completion:0 Ready for Final Payment:
Decrease in time on this C.O.: Substantial Completion: 0 Ready for Final Payment:
Contract time with all approved C.O.s: Substantial Completion: 510 Ready for Final Payment:
Change in Contract Price
Original Contract Price: $7.097,000.00
Increased from previously approved C.O.:
Decreased from previously approved C.O.: $1.945.008.20
Increase in Contract price this C.O.:
Decrease in Contract price this C.O.: $2,425.00
Contract price with all approved C.O.s: $5.149.566.90
The undersigned Contractor certifies to the best of my knowledge and belief: (1)all items and amounts shown above are correct;(2)all
Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all previous
progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract referred to
above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by prior Applications
for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered by this Application
for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and encumbrances; (5)payment
is due and has not been previously requested for these amounts; (6)no markup has been applied to reimbursable expenses.
Wharton Smith Construction,Mike Higginbotham—Project Manager
Contractor Name and Title
00660-1
CCUA Project No.2205-077
Mid-Clay VVVVTF Phase II Expansion CHANGE ORDER REQUEST FORM
M&A Project No.9204-54-1 July 2021
SECTION 00660
CHANGE ORDER REQUEST FORM
Cost Break Down Form: instructions: use a se arate form for each individual work item)
Labor N/A $
Materials - $-2,425.00
Equipment
Maintenance of Traffic
Bonding
General Conditions
Overhead and Profit
Total firm fixed cost not to exceed amount: $-2,425.00
Note:attached supporting documentation
RFI No. initiating the change: None
Description:_
1. Elevated platform in lieu of stairs to BTU#2 and revised checker plate covering of influent structure channels($4,045 deduct).
2. Substitution of 30"x 30" hatches at aerator deck($1,620 adder).
Justification for the request: Owner Request
State the firm fixed cost not to exceed amount in words: Deduct of two thousand four hundred twenty five dollars(-$2,425.00)
oeww-,ate•• ►
Mike Higginbotham" , „""Contractor Signature: Date: 4-3-23
Printed Name: Mike Higginbotham Title: Project Manager