HomeMy WebLinkAboutFYI CO-2 R2T FIWWTF Clarifier 1 EXECUTIVE SUMMARY
AGENDA ITEM:
Proposed Change Order No. 2 for additional time on the Fleming Island Wastewater Treatment
Facility(WWTF) Clarifier No. 1 Rehabilitation Contract with R2T, Inc.
CCUA Job File No. 2203-137
CCUA Bid No. 20/21/A03
Date: May 30, 2023
BACKGROUND:
R2T, Inc. has provided construction services for the Fleming Island WWTF Clarifier No. 1
Rehabilitation project.
cts The Contractor is requesting a time change order due to vendor's lack of availability to be on site
cfor startup service. The clarifier mechanism manufacturer, Lakeside Equipment Corp., could not
ca be on site before May 23, 2023, which is past the current final completion date of May 15, 2023.
0
L Change Order No. 2 consists of an additional 52 days for final completion and closeout. The new
substantial and final completion dates will be 6/6/23 and 7/6/23 respectively. There is no additional
ce
cost to the contract value.
BUDGET:
The project construction budget was $737,474.14. The construction budget after the Change
Order No. 2 remains 737,474.14.
ATTACHMENTS:
Change Order No. 2 form from R2T, Inc., with backup documentation
FOR Entitlement Analysis
CCUA Change Order Form
I
I
,'II t>.r Clay County Utility Authority
3176 Old Jennings Road Working together to protect
public health,conserve our
Middleburg,Florida 32068-3907 natural resources,and
Telephone(904)213-5999 create long-term value,for
:,
i l i \t.t\,
Change Order No.: 2
Project:
our ralepoyerr,
Facsimile (904)213-2498
Date: May 12,2023
Fleming Island WWTF Clarifier No. 1 Rehabilitation
CCUA Bid No.: 20/21-A03
CCUA Project No.: 2203-137
Vendor: R2T,Inc. Owner: Clay County Utility Authority
500 Village Square Gardens,Ste 202 3176 Old Jenings Road
Palm Beach Gardens,Fl 33410 Middleburg,Fl 32068
(786)451-6584 (904)272-5999
' Engineer of Record: Constatine Engineering
100 Center Creek Rd,Suite 102
St,Augustine,FL 32084
(904)562-2185
CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 5/23/2022
DAYS ADD 27 52
SUB.COMP. 300, 3/19/2023 4/15/2023 6/6/2023
FINAL COMP. 330 4/18/2023 5/15/2023 7/6/2023
tt) INCREASE OR
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) OTY, UNIT PRICE CONTRACT PRICE
Contract Increase
Contract Decrease
TOTAL INCREASE $0.00
TOTAL DECREASE $0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
ORIGINAL CONTRACT PRICE $737.474.14
Net Increases by Change Orders(prior to this change order) $0.00
Net Decreases by Change Orders(prior to this change order) $0.00
Total Net Change by Change Orders(prior to this change order) $0.00
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $737.474.14
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $737.474.14
This document shall become an ante tdrncnt to the contract and all provisions of the contract will apply hereto.
(,....„_
f o
A ted b : - r/ Date: 5/16/2023
P Y . `
gmecr of ec
Dye,,Wre1 b,Wo,p.W
Accepted by: G e o r•e A• ws tws.e•e.«v NY
W 1R.T,ON•Geapt An 5 16 2023
o<.w�.'.ommaro bnEonmM Date:
endor
Acce P Y ted b : iiirdellNirsi, :
Date:ec.-L3 'ems-I )
:�
G. Testing
1. All facilities and systems shall be tested as a condition precedent to
substantial completion. See equipment specifications for additional
requirements. Start-up plans for each facility and equipment shall be
2.
submitted,reviewed and approved by the Engineer.
All new facilities and systems shall continue to operate for a two(2)week
period prior to substantial completion.
1.07 PERMITS
A. The Contractor shall arrange for all required inspections and shall close out the
permits at the end of the Contract.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
END OF SECTION
0
01014-4
PROJECT NO.2203-136 CONSTRUCTION SEQUENCE
FLEMING ISLAND WWTF CLARIFIER NO.1 REHABILITATION PROJECT MAY 2022
ENTITLEMENT RECOMMENDATION LETTER an,ri,rraCompany
CCUA Fleming Island WWTF Clarifier No. 1 RehConstaabtrine
Project
FOR Entitlement Recommendations:
ENGINEER PROJECT NO.: 100435.10
CONTRACTOR PROJECT NO. 2203-137
CHANGE ORDER NUMBER: 2
DESCRIPTION: Extended Time
PREPARED BY: River 2 Tap,Inc.-Steven Kelley
DATE: May 16,2023
R2T(Contractor) is providing contruction services for the Fleming Island WWTF Clarfiier No. 1
Rehabiltation Project.
Change Order No.2 is the proposed extention time required for R2T to finalize the project due
to vendor scheduling delays.Substantial completion walk through will require the vendor to be
on site during testing per specification 01014. Lakeside has coordinated with the contractor and
they are three weeks out before avaiblilty to arrive on site. Communication between the
contractor and vendor is attahed to this letter.
The Contractor submitted a change order request for a lump sum amount of$0.00 on May 11,
2023 to extend the time to perform the work.The Contractor requests 52 additional days from
contract completion of CO#1 May 15,2023.
Schedule:
Contract Completion was 04/18/2023.
Change Order#1 Contract Completion was 05/15/2023.
Change Order#2 Contract Completion is now 07/06/2023.
Budget:
The project construction budget was$737,474.14.
The project after Change order No. 1 was$737,474.14.
The project after Change order No. 2 is$737,474.14.
David Rasmussen,PE,BCEE
Project Manager
Ardurra
0
Change Order Request Form Project: Fleming Island WWTF
Clarifier No. 1 Rehabilitation Change Order No.: 2
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion: 300 Ready for Final Paylnt
Increased from previous C.O.: Substantial Completion: 327 Ready for Final Payment: 357
Decreased from previous C.O.: Substantial Completion: Ready for Final Payment:
Contract time prior to this C.O.: Substantial Completion: Ready for Final Payment:
Increase in time on this C.O.: Substantial Completion: 379 Ready for Final Payment: 409
Decrease in time on this C.O.: Substantial Completion: Ready for Final Payment:
Contract time with all approved C.O.s: Substantial Completion: _ Ready for Final Payment:
Change in Contract Price
Original Contract Price: $737,474.14
Increased from previously approved C.O.:
Decreased from previously approved C.O.:
Increase in Contract price this C.O.: 0
Decrease in Contract price this C.O.:
Contract price with all approved C.O.s:
The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2)
all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all
previous progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract
referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by
prior Applications for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered
by this Application for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and
encumbrances; (5) payment is due and has not been previously requested for these amounts; (6) no markup has been applied to
reimbursable expenses.
Steen Kelley-R2T Project Manager
Contractor Name and Title
CCUA Project No: 111 I-028
CDM Smith Project No:259164-254937 CHANGE ORDER REQUEST FORM
Meadow Lakc WTP Expansion Project November 2021
Change Order Request Form
Cost Break Down Form: (instructions: use a separate form for each individual work item)
Labor
Materials
Equipment __ w
Maintenance of Traffic
_Bonding.._ — -- $
General Conditions
Overhead and Profit $
Total firm fixed cost not to exceed amount: 1111111111.1111111111111111
Note: attached supporting documentation
RFI No. initiating the change:
Description- Contractor(R2T)requested start up service with Lakeside(manufacturer)3 weeks in advance to have scheduled for week of 5/15/23
Lakeside Rep is not available until 5/23/23 which is past current final completion.Customer has also requested additional coating work to be performed from owner's
allowance.This additional no cost change order is for additional time to complete the extra work,also time for startup and any punch out repairs.
Justification for the request: Lakeside Rep schedule is out of contractor's control,it was also not known if there would be enough budget to have the
extra work performed until the spirovac was installed and elevations could be taken so the appropriate amount of grout could be accounted for.
This additional time extension request would add52days for final completion and close out.
State the firm fixed cost not to exceed amount in words:
y tu�[rt 5/2/23
Contractor Signature: Date:
Printed Name: Steven Kelley Title- Project Manager
CCUA Project No:2203.137 Fleming
Island WWRF ClaritierNo.I CHANGE ORDER REQUEST FORM
Rehabilitation November 2021
O
Heather Cavanagh
From: Steven Kelley <steven.kelley@r2tinc.com>
Sent: Tuesday, May 2, 2023 9:29 AM
To: Heather Cavanagh
Subject: FW: CCUA Fleming Island Clarifier Startup 22-142
This Message Is From an External Sender
This message came from outside your organization.
Heather,see below
From: Mark Resendez<mr@lakeside-equipment.com>
Sent: Monday,April 24, 2023 3:48 PM
To:Steven Kelley<steven.kelley@r2tinc.com>;Jim Snyder<js@lakeside-equipment.com>; Fred Trippensee(fwt@trippenseeshaw.com)
<fwt@trippenseeshaw.com>
Cc:Gary Rivello<gary.rivello@r2tinc.com>; George Ajy<george.ajy@r2tinc.com>
Subject:RE:CCUA Fleming Island Clarifier Startup 22-142
Steven,
Currently I can do the following week 5/23. Please confirm.
Regards,
MARK RESENDEZ
Service Manager
Lakeside Equipment Corporation
Phone:630.837.5640 X 242 I FAX:630.837.5647
From:Steven Kelley<steven.kelley@r2tinc.com>
Sent: Monday,April 24, 2023 2:00 PM
To: Mark Resendez<mr@lakeside-equipment.com>;Jim Snyder<js@lakeside-equipment.com>; Fred Trippensee (fwt@trippenseeshaw.com)
<fwt@trippenseeshaw.com>
1
5-
Cc:Gary Rivello<garv.rivello@r2tinc.com>;George Ajy<george.aly@r2tinc.com>
Subject:RE:CCUA Fleming Island Clarifier Startup 22-142
Good Afternoon Mark,
We would like to schedule the final walk through and startup service for 5/16/23. Can you please confirm your schedule that this works so that we can
coordinate with the Engineer and Customer?
Steven Kelley
* Project Manager
c. 321-693-2190
580 W Crossville Rd.Suite 101,Roswell,GA 30075
RIVERTOTAP
RIVER TO TAP I A RESERVOIR OF EXPERTISE
Woman-Owned Small Business
CD 0
From: Mark Resendez<mr@lakeside-eauipment.com>
Sent: Monday, March 27,2023 4:28 PM
To:Steven Kelley<steven.kelley@r2tinc.com>;Jim Snyder<Is@lakeside-equipment.com>; Fred Trippensee(fwt@trippenseeshaw.com)
<fwt@trippenseeshaw.com>
Cc:Gary Rivello<garv.rivello@r2tinc.com>;George Ajy<george.aiv@r2tinc.com>
Subject: RE:CCUA Fleming Island Clarifier Startup 22-142
Steven,
I can do 4/10 week.
Regards,
MARK RESENDEZ
Service Manager
Lakeside Equipment Corporation
Phone:630.837.5640 X 242 I FAX:630.837.5647
2
0
From:Steven Kelley<steven.kellev@r2tinc.com>
Sent: Monday, March 27,2023 3:23 PM
To: Mark Resendez<mr@lakeside-equipment.com>;Jim Snyder<is@lakeside-equipment.com>; Fred Trippensee (fwt@trippenseeshaw.com)
<fwt@trippenseeshaw.com>
Cc:Gary Rivello<gary.rivello@r2tinc.com>;George Ajy<george.aiv@r2tinc.com>
Subject:RE:CCUA Fleming Island Clarifier Startup 22-142
Good Afternoon Mark,
I wanted to follow up with you, please let us know when you can schedule the first startup for this lakeside equipment.
Steven Kelley
Project Manager
Cl*
River 2 Tap,Inc.
580 W Crossville Road, Suite 101
Roswell,GA 30075
Office: (770)629-8295 ext 113
Cell: (321) 693-2190
Fax: (770)993-5082
steven.kellev@r2tinc.com
www.r2tinc.com
From:Steven Kelley
Sent:Thursday, March 23,2023 8:35 AM
To: Mark Resendez<mr@lakeside-equipment.com>;Jim Snyder<js@lakeside-equipment.com>; Fred Trippensee(fwt@trippenseeshaw.com)
<fwtt trippenseeshaw.com>
3
0
Cc:Gary Rivello<garv.rivello@r2tinc.com>;George Ajy<george.aly@r2tinc.com>
Subject: RE:CCUA Fleming Island Clarifier Startup 22-142
Good Morning Mark,
We would like to schedule the first of the two startup visits no later than 4/20/23 prior to the grout installation. Please let us know if this works or if there is an
earlier date that your field technician is available.
Steven Kelley
Project Manager
River 2 Tap, Inc.
580 W Crossville Road, Suite 101
Roswell,GA 30075
Office:(770)629-8295 ext 113
Cell: (321)693-2190
Fax: (770)993-5082
steven.kellev@r2tinc.com
www.r2tinc.com
From: Mark Resendez<mr@lakeside-equipment.com>
Sent:Wednesday, March 22, 2023 6:08 PM
To:Jim Snyder<js@lakeside-equipment.com>;Steven Kelley<steven.kellev@r2tinc.com>; Fred Trippensee (fwt@trippenseeshaw.com)
<fwt@trippenseeshaw.com>
Cc:Gary Rivello<gary.rivello@r2tinc.com>
Subject: RE:CCUA Fleming Island Clarifier Startup 22-142
Steven,
4
0
Please let me know when you have a firm date.
Regards,
MARK RESENDEZ
Service Manager
Lakeside Equipment Corporation
Phone:630.837.5640 X 242 I FAX:630.837.5647
From:Jim Snyder<js@lakeside-equipment.com>
Sent:Wednesday, March 22, 2023 8:14 AM
To:Steven Kelley<steven.kellev@r2tinc.com>; Fred Trippensee (fwt@trippenseeshaw.com)<fwt@trippenseeshaw.com>
Cc:Gary Rivello <garv.rivello@r2tinc.com>; Mark Resendez<mr@lakeside-equipment.com>
Subject:RE:CCUA Fleming Island Clarifier Startup 22-142
Steven
Our startup schedule is currently approx.3 weeks out on the schedule.
Please contact our service manager, Mark Resendez,to schedule startup. Mark is copied on this email.
Regards,
Jim Snyder
Voice 1-630-837-5640 x245 FAX 1-630-837-5647
From:Steven Kelley<steven.kellev@r2tinc.com>
Sent:Wednesday, March 22, 2023 8:10 AM
To: Fred Trippensee(fwt@trippenseeshaw.com)<fwt@trippenseeshaw.com>
Cc:Jim Snyder<js@lakeside-equipment.com>;Gary Rivello<garv.rivello@r2tinc.com>
Subject:CCUA Fleming Island Clarifier Startup 22-142
Good Morning Fred,
We have received the Lakeside equipment and are in process of installing the unit. Could you let us know how long ahead of time we need to schedule with
Lakeside for startup services of the new unit?Our substantial completion date with the customer will hopefully be extended to April 19tn
Steven Kelley
Project Manager
5