HomeMy WebLinkAboutFYI CO No. 2 to 19_20-A16 with Sawcross for Ridgecrest WTP EXECUTIVE SUMMARY
AGENDA ITEM:
Change Order No. 2 to Ridgecrest WTP Electrical Upgrades Project Agreement with Sawcross,
Inc.
CCUA Bid No. 19/20-A16
CCUA Project No.: 1102-0050
CCUA Financial Job No.: 20021RR
Date: June 14, 2023
BACKGROUND:
Sawcross, Inc. has provided construction services for the Ridgecrest WTP Electrical Upgrades
project.
co The Contractor's electrical gear supplier begin to experience supply change issues from its material
a supply vendors during the peak of the COVID-19 era. From April 7, 2022, through May 1,
co 2023, the electrical gear supplier provided written updates explaining to the contractor their
° difficulties in supplying the electrical gear equipment and materials.The written correspondences
cited supply chain(electronics, metals, resins, etc.), logistics, and continued supplier labor
disruptions. CCUA Staff has several existing projects experiencing the same delay concerns
cc
herein.
The electrical gear supplier completed the electrical gear equipment and materials delivery on June
12, 2023.
Change Order No. 2 consists of extending the project substantial and final completion durations
by 300 calendar days. The new substantial and final completion dates will be October 10, 2023,
and November 9, 2023, respectively. There is no additional cost to the contract value.
BUDGET:
The project contract construction budget was $1,926,000. The project construction budget with
Change Order No.2 remains $1,926,000.
ATTACHMENTS:
Change Order No. 2
Change Order No. 2 request from Sawcross, Inc., with backup documentation
•
i\.',1 t''t,t7,1 Clay County Utility Authority Workinglorr„I«•I
3176 Old Jennings Road public health,c•ansenr our
Middleburg.Florida 32068-3907 natural resources,and
Telephone(904)213-5999 creole long-lent rnlue for
///rl N1 '(I our raleparers
Facsimile (904)213-2498
Change Order No.: 2 Date: June 26.2023
Project: Ridgecrest WTP Electrical Upgrades Project
CCUA Bid No.: 1102-0050
CCUA Project No.: 19/20-A 16
Vendor: Sawcross,Inc. Owner: Clay County Utility Authority
10970 New Berlin Road 3176 Old Jennings Road
Jacksonville,FL 32226 Middleburg,Florida 32068
Engineer of Record: Constantine Engineering,Inc.
100 Center Creek Road,Suite 108
St.Augustine,FL 32084
CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 10/20/2021
DAYS ADD 0 300
SUB.COMP. 420 12/14/2022 10/10/2023
FINAL COMP. 450 1/13/2023 11/9/2023
INCREASE OR
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) QTY. UNIT PRICE CONTRACT PRICE
Contract Increase
Contract Decrease
TOTAL INCREASE $0.00
TOTAL DECREASE $0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0-00
ORIGINAL CONTRACT PRICE $1,926,000.00
Net Increases by Change Orders(prior to this change order) $0.00
Net Decreases by Change Orders(prior to this change order) ($833,1 14.70)
Total Net Change by Change Orders(prior to this change order) ($833.1 14.70)
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $1,092.885.30
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $1.092,88530
This document shall become rt latent to the contract and all provisions of the contract will apply hereto.
/14 Accepted by: •-/ Date: 6/29/2023
ingineer of Re
Accepted by: , Date: 7/27/23
V.ndor
Accepted by: Date: Z �D — e--.
lei
A
I,
SAWCROSS INCORPORATED
10970 NEW BERLIN ROAD JACKSONVILLE, FL 32226-2270
904-751-7500(VOICE)904-751-0600(FAX)WWW.SAWCROSS.COM (INTERNET)
June 19, 2023
Warrick L. Sams, MBA, CPPO
Clay County Utility Authority
3176 Old Jennings Road
Middleburg, FL 32068-3907
Subject: CCUA Ridgecrest WTP Electrical Upgrades (Schedule Impact —
Equipment/Material Lead Times & Delays)
Dear David,
In regards to the CCUA Ridgecrest WTP Electrical Upgrades Project, the current
and ongoing issue of supply chain has significantly impacted the construction
schedule and contractual completion dates (Substantial Completion December
14, 2022). Please see below for anticipated delivery dates of major equipment:
ANTICIPATED
to EQUIPMENT VENDOR DELIVERY DATE
(CURRENT)
Motor Control Center/ Electrical Gear Eaton 6/13/2023
***These current projected lead times/expected delivery dates are only
estimates and are subject to change***
Revised Substantial Completion Date: October 10, 2023
Revised Final Completion Date: November 9, 2023
Total Costs: $0.00
Total Additional Contract Time: Three Hundred (300) Day(s)
Sincerely,
Drew Hickinbotham
Project Manager
904-751-7500 Ext. 113
CONTRACTORS&ENGINEERS
CGC 36203 CMC 56728 CUC 56787 UC 300564
SECTION 00660
Change Order Request Form
Project: Ridgecrest WTP Electrical Upgrades Project Bid No. 19/20-A16 Project No.: 1102-0050
Change Order No.: 02
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion: 420 Ready for Final Payment: 450
Increased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Decreased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time prior to this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Increase in time on this C.O.: Substantial Completion: 300 Ready for Final Payment: 330
Decrease in time on this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time with all approved
C.O.s: Substantial Completion: 720 Ready for Final Payment: 780
Change in Contract Price
Original Contract Price: $1,926,000.00
Increased from previously approved C.O.: $0.00
Decreased from previously approved C.O.: -$833,114.70
Increase in Contract price this C.O.: $0.00
Decrease in Contract price this C.O.: $0.00
Contract price with all approved C.O.s: $1 ,092,885.30
The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2)
all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all
previous progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract
referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by
prior Applications for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered
by this Application for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and
encumbrances; (5) payment is due and has not been previously requested for these amounts; (6) no markup has been applied to
reimbursable expenses.
Drew Hickinbotham (Project Manager; Sawcross, Inc.)
Contractor Name and Title
00660-1
Project No.1102-0050 CHANGE ORDER REQUEST FORM
Ridgecrest WTP Electrical Upgrades Project September 2021
SECTION 00660
Change Order Request Form
Cost Break Down Form: (instructions:use a separate form for each individual work item)
Description Unit Quantity Unit Cost Extended Cost
Labor $
Materials -_ - - - - -- -- -- $
E ui ment
Maintenance of Traffic $
BondMg
General Conditions
Overhead and Profit $
- - -------------------- -
------------------------------- ---------------------------------------------------
Total firm fixed cost not to exceed amount: — $
Note:attached supporting documentation
RFI No.initiating the change:
Description: No costs associated with change oder. Time extension requested due to electrical supply chain issues.
Justification for the request:Sawcross requests time to be added to contract due to unforeseen supply chain issues in
obtaining electrical gear.
State the firm fixed cost not to exceed amount in words:
Contractor Signature: �Lry - Date: 6,k,l/zco3
Printed Name: NE anficf,im Bo1Novi Title: PRO3E0rAMMq%R
00660-2
Project No. 1102-0050 CHANGE ORDER REQUEST FORM
Ridgecrest WTP Electrical Upgrades Project September 2021
i
E . , i
IRO & p
April 05, 2022
To: Drew Hickinbotham-Sawcross Inc.
Re: Ridgecrest WTP Electrical Upgrades- Eaton Gear Delayment
Drew,
Currently, the Eaton MCCs for the Ridgecrest WTP Electrical Upgrades have an ESTIMATED
ship date of 11/11/2022. These dates are ESTIMATED and subject to change without notice.
It is a very tough time we are facing when it comes to acquiring electrical equipment and
materials. This is due to all of the supply chain issues felt across the United States. The factors
causing these long lead times are a multitude of things such as material shortages, man power
shortage, the high demand of a booming economy and now we add in the factor of the Ukraine
War currently happening. Please know that these delays are out of the hands of us here at
to Cogburn.All we can tell you is what we are being told on a weekly basis as updates come in. We
are doing everything in our power to expedite this equipment but we cannot make any
guarantees.
Thanks,
Bryan Sullivan, Project Manager
3300 Faye Road, Jacksonville, FL 32226
Phone 904-358-7344 Fax 904-358-2805
EC-0000426
Eaton Corporation
E N 7000 Highlands Pkwy
Suite#101
Powering Business Worldwide Smyrna,GA 30075
April 7, 2022
Bryan Sullivan
COGBURN BROS. INC.
3300 Faye Road
Jacksonville, FL 32226
Dear Bryan,
As we head into the next quarter of 2022, I'd like to provide you with an update on Eaton's current
operational status and what our customers and channel partners can expect from us in the coming
months. Supply chain (electronics, metals, resins, allocations in such areas), logistics, and
supplier labor disruptions continue to provide challenges for manufacturers across the electrical
industry. We expect this to continue for a large part of 2022, which is why we have made
significant investments to increase capacity, improve throughput and grow our supply chain
elasticity. Eaton continues to qualify new suppliers, utilize "spot buys"for critical material, and
employ premium freight and expedited shipping lanes to maximize available product for our
partners and customers. These investments and actions are helping, but due to the continuation of
challenging conditions, lead times continue to be extended across many Eaton product groups.
Our current efforts are focused on delivering product as efficiently as we can under the current
circumstances. Because of this, please be aware that we do not have the flexibility to support
expedite requests. While Eaton will continue to provide as-accurate-as-possible updates on lead
times, unexpected changes are anticipated. We remain committed to providing our sales teams,
customers and channel partners with the most up-to-date and available information as we can
to while managing expectations that lead times may continue to be extended or changed as the
market evolves.
Due to the current challenges, there will be revisions of our shipping schedule for your below listed
items that were purchased from World Electric Supply:
World Electric Supply PO# SO46181230 (Eaton GO# LJV0028012)
• MCCs— Items 001-004
We apologize for the delay. Eaton's recovery plan is focused in the areas above to improve
supply across all shorted and allocated material.
Please feel free to reach out to me if you have any questions or would like to discuss.
Sincerely,
Rod Spottsville
Vice President, Sales—Southeast Region
RodneyLSpottsville@eaton.com
E T•N Eaton Corporation
529 South Park Circle
Bldg. 100,Suite#180
Powering Business Worldwide Orlando,FL 32819
February 14, 2023
Bryan Sullivan
Cogburn Bros., Inc.
3300 Faye Road
Jacksonville, Florida 32226
Bryan,
As we head into the first quarter of 2023, I'd like to provide you with an update on Eaton's current
operational status and what our customers and channel partners can expect from us in the coming
months. Supply chain (electronics, metals, resins, allocations in such areas), logistics, and
supplier labor disruptions continue to provide challenges for manufacturers across the electrical
industry. We expect this to continue for a large part of 2023, which is why we have made
significant investments to increase capacity, improve throughput and grow our supply chain
elasticity. Eaton continues to qualify new suppliers, utilize "spot buys"for critical material, and
employ premium freight and expedited shipping lanes to maximize available product for our
partners and customers. These investments and actions are helping, but due to the continuation of
challenging conditions, lead times continue to be extended across many Eaton product groups.
Our current efforts are focused on delivering product as efficiently as we can under the current
circumstances. Because of this, please be aware that we do not have the flexibility to support
expedite requests. While Eaton will continue to provide as-accurate-as-possible updates on lead
times, unexpected changes are anticipated. We remain committed to providing our sales teams,
customers and channel partners with the most up-to-date and available information as we can
to while managing expectations that lead times may continue to be extended or changed as the
market evolves.
Due to the current challenges, there will be revisions of our shipping schedule for your below listed
items that were purchased from:
World Electric Supply PO#SO46181230 (Eaton GO# LJ0028012)
• MCC (MCC-MAIN & MCC-DISTRIBUTION): Items 001 & 002
o Material Delaying Shipment:
• Power Xpert Meters, VFDs, Starters, Relays, Miniature Circuit Breakers
(FAZ, QCR), Circuit Breakers, Fuses & Fuse Blocks & Indicating Lights
o Current ship date: April 6th, 2023
• MCC (MCC-2 & MCC-1): Items 003 &004
o Material Delaying Shipment:
• Power Xpert Meters, VFDs, Starters, Relays, Miniature Circuit Breakers
(FAZ, QCR), Circuit Breakers, Fuses & Fuse Blocks & Indicating Lights
o Current ship date: April 14th, 2023
Page 2 of 2 November 18,2022
We apologize for the delay. Eaton's recovery plan is focused in the areas above to improve
supply across all shorted and allocated material.
Please feel free to reach out to me if you have any questions or would like to discuss.
Sincerely,
Ervin Beckman
District Manager—GSS
ErvinWBeckman(a�eaton.com
to
Eaton Corporation
E ,TON 529 South Park Circle
Bldg.100,Suite#180
Powering Business Worldwide Orlando,FL 32819
June 5, 2023
Bryan Sullivan
Cogburn Bros., Inc.
3300 Faye Road
Jacksonville, Florida 32226
Bryan,
As we head into the third quarter of 2023, I'd like to provide you with an update on Eaton's current
operational status and what our customers and channel partners can expect from us in the coming
months. Supply chain (electronics, metals, resins, allocations in such areas), logistics, and
supplier labor disruptions continue to provide challenges for manufacturers across the electrical
industry. We expect this to continue for a large part of 2023, which is why we have made
significant investments to increase capacity, improve throughput and grow our supply chain
elasticity. Eaton continues to qualify new suppliers, utilize "spot buys"for critical material, and
employ premium freight and expedited shipping lanes to maximize available product for our
partners and customers. These investments and actions are helping, but due to the continuation of
challenging conditions, lead times continue to be extended across many Eaton product groups.
Our current efforts are focused on delivering product as efficiently as we can under the current
circumstances. Because of this, please be aware that we do not have the flexibility to support
expedite requests. While Eaton will continue to provide as-accurate-as-possible updates on lead
times, unexpected changes are anticipated. We remain committed to providing our sales teams,
customers and channel partners with the most up-to-date and available information as we can
to while managing expectations that lead times may continue to be extended or changed as the
market evolves.
Due to the current challenges, there will be revisions of our shipping schedule for your below listed
items that were purchased from:
World Electric Supply PO# SO46181230 (Eaton GO# LJ0028012)
• MCC (MCC-DISTRIBUTION): Item 002
o Material Delaying Shipment:
■ Power Xpert Meters, VFDs, Starters, Relays, Miniature Circuit Breakers
(FAZ, QCR), Circuit Breakers, Fuses & Fuse Blocks & Indicating Lights
o Current ship date: June 9th, 2023.
We apologize for the delay. Eaton's recovery plan is focused in the areas above to improve
supply across all shorted and allocated material.
Please feel free to reach out to me if you have any questions or would like to discuss.
Sincerely,
Ervin Beckman
District Manager—GSS
ErvinWBeckman@eaton.com
Ef[ N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4;
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-E
P.O. Num: SO46181230
Report Run Date: 05/02/2022
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
f/) cn
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro# Invoice#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 03/23/22 11/11/22
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 03/23/22 11/11/22
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 03/23/22 11/11/22
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 03/23/22 11/11/22
005 Q11 B 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 04/12/22 05/13/22
006 EED 0 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22
007 EED H 1 FINAL STUDY 11/30/22
008 EED 0 1 HARMONIC ANALYSIS 11/18/21 11/30/22
009 EED H 1 AAP ITEMS 11/30/22
t0 010 EED H 1 EQUIPMENT START UP 11/30/22
E:t•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4;
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-E
P.O. Num: SO46181230
Report Run Date: 05/09/2022
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
rn cn
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro# Invoice#
c
k N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 05/04/22 12/09/22
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 05/04/22 12/09/22
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 05/04/22 12/16/22
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 05/04/22 12/16/22
005 011 B 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 04/12/22 05/13/22
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22 59463162
007 EED H 1 FINAL STUDY 11/30/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22 59463162
009 EED H 1 AAP ITEMS 11/30/22
t0 010 EED H 1 EQUIPMENT START UP 11/30/22
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
30 Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
:ust: WORLD ELECTRIC SUPPLY(JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
'.O. Num: SO46181230
Report Run Date: 06/13/2022
EGEND
itatus: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
— Manufacturing and Shipping Information
N cn
:em E, °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro# Invoice#
c
K N
01 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 05/04/22 12/09/22
02 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 05/04/22 12/09/22
03 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 05/04/22 12/16/22 _ _
04 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 05/04/22 12/16/22 _
05 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 59517912
06 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22 59463162
07 EED H 1 FINAL STUDY 11/30/22
08 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22 59463162
09 EED H 1 AAP ITEMS 11/30/22
to 10 EED H 1 EQUIPMENT START UP 11/30/22
E:t•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 07/18/2022
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-N N
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
k N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 07/11/22 12/16/22
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 07/11/22 12/16/22
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 07/11/22 12/30/22
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 07/11/22 12/30/22
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED H 1 AAP ITEMS 11/30/22
tO 010 EED H 1 EQUIPMENT STARTUP 11/30/22
E:t•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 09/12/2022
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-N N
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
k N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 08/31/22 01/20/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 08/31/22 01/20/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 08/31/22 01/27/23
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 08/31/22 01/27/23
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED H 1 AAP ITEMS 11/30/22 09/01/22 05/31/23
tO 010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:t•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 09/26/2022
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-N N
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
k N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 08/31/22 01/20/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 08/31/22 01/20/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 08/31/22 01/27/23
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 08/31/22 01/27/23
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED H 1 AAP ITEMS 11/30/22 09/01/22 05/31/23
tO 010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:t•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 10/10/2022
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-N N
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
k N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 10/07/22 03/10/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 10/07/22 03/10/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 10/07/22 03/17/23
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 10/07/22 03/17/23
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED H 1 AAP ITEMS 11/30/22 09/01/22 05/31/23
tO 010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:t•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 11/28/2022
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-N N
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
k N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 10/07/22 03/10/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 10/07/22 03/10/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 10/07/22 03/17/23
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 10/07/22 03/17/23
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED H 1 AAP ITEMS 11/30/22 09/01/22 05/31/23
tO 010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 01/02/2023
'LEGEND
[Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
cn cn
Item F. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 10/07/22 03/10/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 10/07/22 03/10/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 10/07/22 03/17/23 _
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 10/07/22 03/17/23 _
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 01/16/2023
'LEGEND
'Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
cn cn
Item F. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 10/07/22 03/10/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 10/07/22 03/10/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 10/07/22 03/17/23 _
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 10/07/22 03/17/23 _
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 05/16/22 06/13/22 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 05/31/22 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 02/13/2023
'LEGEND
'Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
cn cn
Item F. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 02/07/23 04/06/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 02/07/23 04/06/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 02/07/23 04/14/23 _
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 02/07/23 04/14/23 _
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 02/27/2023
'LEGEND
'Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
cn cn
Item F. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 02/07/23 04/06/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 02/07/23 04/06/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 02/07/23 04/14/23 _
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 02/07/23 04/14/23 _
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 03/13/2023
'LEGEND
'Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
cn cn
Item F. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 02/07/23 04/06/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 02/07/23 04/06/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 02/07/23 04/14/23 _
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 02/07/23 04/14/23 _
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 09/01/22 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 03/27/2023
'LEGEND
'Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
cn cn
Item F. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 02/07/23 04/06/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 02/07/23 04/06/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 02/07/23 04/14/23 _
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 02/07/23 04/14/23 _
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 03/21/23 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 04/03/2023
'LEGEND
'Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
cn cn
Item F. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
K N
001 FVC 0 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 02/07/23 04/06/23
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 03/31/23 05/12/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 02/07/23 04/14/23 _
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 02/07/23 04/14/23 _
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 03/21/23 08/31/23
E.T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 04/24/2023
LEGEND
Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
iC N
001 FVC I 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 04/05/23 04/13/23 04/13/23 SOUTHEASTERN FREIGHT 272499421
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 03/31/23 05/12/23
003 FVC 0 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 04/17/23 04/28/23
004 FVC 0 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 04/20/23 04/28/23
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
t0 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 03/21/23 08/31/23
E.T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 05/01/2023
LEGEND
Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
iC N
001 FVC I 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 04/05/23 04/13/23 04/13/23 SOUTHEASTERN FREIGHT 272499421
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 04/27/23 06/09/23
003 FVC I 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 04/17/23 04/28/23 04/29/23 AVERITT EXPRESS 0590153417
004 FVC I 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 04/20/23 04/28/23 04/26/23 SOUTHEASTERN FREIGHT 272499501
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
t0 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 03/21/23 08/31/23
E.T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 05/15/2023
LEGEND
Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
Item °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
iC N
001 FVC I 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 04/05/23 04/13/23 04/13/23 SOUTHEASTERN FREIGHT 272499421
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 04/27/23 06/09/23
003 FVC I 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 04/17/23 04/28/23 04/29/23 AVERITT EXPRESS 0590153417
004 FVC I 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 04/20/23 04/28/23 04/26/23 SOUTHEASTERN FREIGHT 272499501
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
t0 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 03/21/23 08/31/23
E.T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 06/05/2023
LEGEND
Status: H = Hold, I = Invoiced, X = Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
Item c °. Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
iC N
001 FVC I 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 04/05/23 04/13/23 04/13/23 SOUTHEASTERN FREIGHT 272499421
002 FVC 0 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 04/27/23 06/09/23
003 FVC I 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 04/17/23 04/28/23 04/29/23 AVERITT EXPRESS 0590153417
004 FVC I 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 04/20/23 04/28/23 04/26/23 SOUTHEASTERN FREIGHT 272499501
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
t0 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 03/21/23 08/31/23
E:T•N Standard Status Report
Job Name: CCUA RIDGECREST WTP
GO Num: LJV0028012 Proj Engineer: Patrick Kelleher (678-309-4230)
Cust: WORLD ELECTRIC SUPPLY (JAX) Proj Coordinator: Theresa Blankenship (828-651-0683)
P.O. Num: SO46181230
Report Run Date: 06/12/2023
LEGEND
Status: H = Hold, I = Invoiced, X= Canceled, 0 = Open (release for mfg.), S = Shipped, B= Backorder/Built to Order
Manufacturing and Shipping Information
-
to M
Item it Qty Description Designation Released for Mfg Date Schd Date Changed Date ReSched Date Shipped Carrier Pro#
c
R co
001 FVC I 1 FREEDOM MCC MCC-MAIN 03/22/22 11/04/22 04/05/23 04/13/23 04/13/23 SOUTHEASTERN FREIGHT 272499421 -1
002 FVC I 1 FREEDOM MCC MCC-DISTRIBUTION 03/22/22 11/04/22 04/27/23 06/09/23 06/09/23 SOUTHEASTERN FREIGHT 290649854-1
003 FVC I 1 FREEDOM MCC MCC-2 03/22/22 11/04/22 04/17/23 04/28/23 04/29/23 AVERITT EXPRESS 0590153417-1
004 FVC I 1 FREEDOM MCC MCC-1 03/22/22 11/04/22 04/20/23 04/28/23 04/26/23 SOUTHEASTERN FREIGHT 272499501 -1
005 Q11 I 3 DH364UWK316 200A/600V/3P/NF/NEMA 02/21/22 03/21/22 02/07/23 06/30/23 05/16/22 S/SOUTHEASTERN FREIG 748031791 -3
006 EED I 1 PRELIM SHORT CIRCUIT STUDY 11/18/21 11/30/22 02/07/23 06/30/23 05/06/22
007 EED I 1 FINAL STUDY 06/25/22 11/30/22 06/27/22
008 EED I 1 HARMONIC ANALYSIS 11/18/21 11/30/22 05/06/22
009 EED I 1 90%PARTIAL BILL FOR AAP ITEMS 12/13/22 11/30/22 12/01/22 11/30/23 12/13/22
to 009A EED 0 1 FINAL BILLING FOR AAP 12/13/22 12/31/23
010 EED H 1 EQUIPMENT START UP 11/30/22 03/21/23 08/31/23