HomeMy WebLinkAbout08.h EDB Dewberry RFQ Amendment 1 Governors Park EXECUTIVE SUMMARY
AGENDA ITEM:
Proposed Amendment 1 to RFQ 2022/2023-A17 with Dewberry Engineers, Inc. to Provide Additional
Professional Services for Design and Services During Construction for the Governor's Park Water Treatment
Plant(GP WTP)
CCUA Project No.: 1127-002
CCUA Financial Job No.: 21026WP
Date: February 15,2024
BACKGROUND:
CCUA staff requests authorization from the Board of Supervisors to execute Amendment 1 to RFQ
2022/2023-A17 with Dewberry, Inc., to provide additional professional services for design and services
during construction(SDC) for the GP WTP.
Dewberry Engineers,Inc.is currently under contract with CCUA via competitive RFQ to provide design,bid,
and SDC services for the GP WTP,a new water plant that will independently serve a new CCUA service area,
Governor's Park. CCUA bid the construction of the plant as two separate projects — drilling two (2) new
supply wells and construction of the treatment, storage, and distribution elements.
As bid,the designed plant treatment process to reduce sulfides in the raw water includes natural tray aeration.
This is standard at every other CCUA water plant because sulfide levels are low and tray aeration is the most
cost-effective method to reduce sulfides. Following completion of the wells, and after awarding the plant
construction contract,water quality testing indicated that source water sulfide levels are elevated(>1.5 mg/L).
When sulfide levels are at this level,the Florida Department of Environmental Protection requires additional
or alternate treatment to reduce sulfides in the finished water. CCUA staff and our engineer of record,
Dewberry, determined that the most reliable, effective, and cost-efficient treatment is to use a forced draft
aerator with upstream CO2 injection. The CO2 injection lowers the pH of the water and allows the sulfides to
be removed more effectively. The design modifications include changes to the storage tank,yard piping, and
addition of CO2 storage and controls and a forced draft aerator and controls.
The proposed amendment will authorize Dewberry to perform additional design services and SDC for these
sulfur removal system changes on the GP WTP project as detailed in the attached Scope and Fee Proposal.
The cost for these services is $57,826.61 which includes necessary work by their subconsultants. The
additional services could not have reasonably been anticipated at the time of the original agreement.
BUDGET:
The current budget for the project, $9,375,000.00, includes sufficient funds to cover the cost of the proposed
amendment. The contracts in this project currently total$8,729,456.53. This change order will bring the total
contracts to $8,787,283.14.
RECOMMENDATION:
Staff respectfully requests the Board of Supervisors approve Amendment 1 to RFQ 2022/2023-A17 with
Dewberry Engineers, Inc. for$57,826.61 for additional professional services for design and SDC for the GP
WTP.
ATTACHMENTS:
Amendment 1 to RFQ 22/23-A17
Dewberry Engineers, Inc., Scope and Fee Proposal
//DD(Author)
//PS,AA(Review)
//PS(Final)
Amendment No. 1 to RFQ 2022/2023-A17 with Dewberry Engineers,Inc. for Professional Services
to Additional professional Services and Services During Construction for the Governor's Park
Water Treatment Plant
CCUA Project No. 1127-002
Engineer: Robert Beltran, PE Owner: Clay County
Dewberry Engineers, Inc. Utility Authority
3616 Harden Blvd. #110
Lakeland, FL 33803
Date: February 20, 2024
Item: Description of Services:
Provide professional engineering services as
requested and identified in the attached scope of
services and fee proposal.
Task 100 Project Management $3,538.00
Task 200 Design Services $47,380.21
Task 300 Construction Administration $6,908.40
Total Lump Sum Price Not to Exceed Without Prior Authorization $57,826.61
The Contract time shall commence on February 21, 2024. This document, along with the Scope and Fee
Proposal, shall become an amendment to the RFQ contract agreement and all provisions of the
Agreement will apply hereto.
Accepted by: Date:
Consultant:
Robert Beltran, PE
Dewberry Engineers, Inc.
Accepted by: Date:
Owner:
Jeremy D. Johnston, P.E., MBA,
Executive Director
Clay County Utility Authority
itDewberry Engineers Inc. 863.345.0838
;:% Dewberry® 1479 Town Center Drive,Suite D214 www.dewberry.com
Lakeland,FL 33803-7974
SCOPE OF SERVICES
Governor's Park Water Treatment Plant (GPWTP) Rebid
Additional Services for Change in Aeration
February 7, 2024
A. Project Background and Description
Dewberry Engineers (CONSULTANT) is under contract with the Clay County Utility Authority
(AUTHORITY) to provide engineering services to provide design and construction services for
the GPWTP.
The project was bid using natural draft aeration of the raw water, as is the standard on the
AUTHORITY's other water treatment plants. The majority of the raw water wells in the
AUTHORITY's system have low dissolved sulfide levels, suitable for natural draft aeration. This
includes the two closest water treatment plants to the GPWTP. Well drilling of the two new
water production wells at the GPWTP site was completed after the WTP was bid. Water testing
indicated that the sulfide levels exceeded the FDEP threshold that requires using forced draft
aeration in lieu of the natural draft aeration that was the basis of the Contractor's bid and the
CONSULTANT's engineering services proposal. In addition, the well testing conducted
indicated that the aquifer levels are higher than the assumed levels based on nearby wells.
Discussion with the CONSULTANT's process specialist and the AUTHORITY's staff indicated
that the pH of the raw water will need to be lowered to air strip the excess sulfide from raw
water. Two process equipment manufacturers for forced draft aeration equipment were
contacted and pricing obtained. The selected forced draft aerator manufacturer had pricing
significantly lower than the alternative. The pH adjustment of the raw water will be by injection
of liquid carbonic acid (CO2), which provides significant safety improvements over mineral acid,
and which is the typical method of making this pH adjustment. The dissolved CO2 is also
reduced in the forced draft aerator, making post-aeration pH adjustment using sodium hydroxide
unnecessary.
The scope of services for the change of aeration will include the following:
• Revise project plans to replace the natural draft aerator with a forced draft aerator.
• Design a liquid carbonic acid storage and metering facility to include a 10-ton CO2
storge tank, liquid panel to produce carbonic acid from CO2 and carrier water, injection
vault and field piping of the CO2, solution water and feed water.
• Modification of the yard piping to provide PVC piping downstream of the CO2 solution
injection to the forced draft aerator and elimination of below slab piping at the ground
storage tank.
• Structural design of the foundation slabs associated with the CO2 system, design of a
weather shed over the CO2 panel and design of a CO2 injection vault.
• Electrical and I&C changes associated with the project modifications.
Page 1 of 3
;
Dewberry-
Dewberry Engineers Inc. 863.345.0838
1479 Town Center Drive,Suite D214 www.dewberry.com
Lakeland,FL 33803-7974
• Hydraulic calculations to support trimming the impellers of the well pumps for the
changed hydraulic conditions associated with the high aquifer levels.
• Additional services during construction for review of the forced draft aerator and CO2
system shop drawings, requests for information and record drawings.
B. Deliverables
The CONSULTANT shall prepare and submit to the Authority, including electronic format when
applicable, deliverables including supplemental drawings, shop reviews, and RFI responses.
C. Schedule
The CONSULTANT will proceed with the services identified herein immediately upon receipt of
an executed copy of this Consultant Purchase Order and a formal Notice-to-Proceed (NTP)
from the AUTHORITY. The proposed additional work will be accomplished in accordance with
the current schedule for the GPWTP.
D. Compensation
This AGREEMENT establishes a lump sum cost of$57,826.61. Compensation for the services
performed under this Agreement shall include all personnel services, any reimbursable
expenses, which may include, but are not necessarily limited to, such items as reproduction,
travel, communication expenses, and postage and shipping. Attachment A-1 shows the
breakdown by task.
E. The AUTHORITY's Responsibilities
The AUTHORITY will provide the following information for the CONSULTANT and / or perform
the following services related to the Project:
• Allow CONSULTANT scheduled access to the project site.
• Provide one representative by the AUTHORITY to coordinate, schedule, and receive
comments/information related to this project.
• The AUTHORITY will furnish the CONSULTANT with readily available studies, reports,
and other data pertinent to the CONSULTANT's services.
All documents and data provided by the AUTHORITY shall be provided in digital format (e.g.,
PDF, database files, spreadsheet, etc.) to the greatest extent feasible and practical.
F. Services Not Included
Dewberry
Page 2 of 3
;:��► Dewberry Engineers Inc. 863.345.0838
Dewberry 1479 Town Center Drive,Suite D214 www.dewberry.com
Lakeland,FL 33803-7974
Service not specifically described in the tasks above are not included.
G. Assumptions
The Scope of Services and compensation arrangement outlined in this Consultant Purchase
Order are based on the following assumptions:
1. The AUTHORITY will provide review comments on project submittals in accordance with
the draft schedule.
Dewberry-
Page 3 of 3
Attachment A-1
Clay County Utility Authority
Governor's Park Water Treatment Plant Rebid Additional Services
ill',. Dewberry
Dewberry Staff Total Subs Total Direct Costs Grand Total
Project
Principal in Senior Technical
Charge Manager/Design
Manager Quality Control Senior Technical Professional II Professional
Officer Dpty PM Senior Process Analist Professional Ill (DH) Process Analist I/Inspector Des/CADD Mgr. Admin Professional Total Hours Total Dewberry Wikeva Ardurra Total Subs Dewberry&Subs
Phase/Task Task Description $ 285.04 $ 272.18 $ 223.55 $ 197.90 $ 188.48 $ 128.25 $ 120.00 $ 97.30 $ 101.48 $ 90.00 $ 80.00
Task 100 Project Management 1 2 0 6 0 • 0 0 4 13 $ 2,336.80 $ - $ 1,201.20 $ 1,201.20 $ 3,538.00 $ - $ 3,538.00
Project Management 1 2 0 6 0 0 0 0 0 0 4 13 $ 2,336.80 $ 1,201.20 $ 1,201.20 $ 3,538.00
Task 200 Additional Design Services 0 73.5 3 M 20.5 0 32- 0 186 $ 35,330.21 $ 4,550.00 $ 7,500.00 $ 12,050.00 $ 47,380.21 $ - $ 47,380.21
Process Calculations/Analysis 9 41 20.5 70.5 $ 12,171.95 $ - $ - $ - $ 12,171.95
CO Design of Forced Draft Aerator 40 1 8 16 65 $ 13,576.75 $ 4,550.00 $ 7,500.00 $ 12,050.00 $ 25,626.75
CO Design of CO2 System 18.5 1 8 16 43.5 $ 7,724.88 $ - $ - $ - $ 7,724.88
Modify Well Hydraulics 6 1 7 $ 1,856.63 $ - $ - $ - $ 1,856.63
Task 300 Construction Administration Services 0 4 0 0 0 16 0 0 $ 4,458.40 $ 1,250.00 $ 1,200.00 $ 2,450.00 $ 6,908.40 $ $ 6,908.40
Addt'l Shop Drawings,RFIs,Record Dwgs 4 8 16 8 0 $ 4,458.40 $ 1,250.00 $ 1,200.00 $ 2,450.00 $ 6,908.40
Grand Total 1 79.5 3 6 20.5 161111 4 199 $ 42,125.41 $ 5,800.00 $ 9,901.20 $ 15,701.20 $ 57,826.61 $ - $ 57,826.61
Basic Services