Change Order No.: 4 Date: February 13.2024
Project: Ridgecrest WTP Electrical Upgrades Project
CCUA Bid No.: 1102-0050
CCUA Project No.: 19/20-A 16
Vendor: Sawcross,Inc. Owner: Clay County Utility Authority
10970 New Berlin Road 3176 Old Jennings Road
Jacksonville,FL 32226 Middleburg,Florida 32068
Engineer of Record: Constantine Engineering,Inc.
100 Center Creek Road,Suite 108
St.Augustine,FL 32084
CONTRACT TIMES _ _ ORIGINAL PREVIOUS CO CURRENT CO
NTP 10/20/2021
DAYS ADD 345 70
SUB.COMP. 420 12/14/2022 11/24/2023 2/2/2024
FINAL COMP. 450 1/13/2023 12/24/2023 3/3/2024
INCREASE OR
DECREASE IN
(ITEM DESCRIPTION OF CHANGE(S) QTY, UNIT PRICE CONTRACT PRICE
Contract Increase
Contract Decrease
OTAL INCREASE $0.00
OTAL DECREASE - - - $0.00
ET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
•RIGINAL CONTRACT PRICE $1,926,000.00
et Increases by Change Orders(prior to this change order) $0.00
et Decreases by Change Orders(prior to this change order) ($831114.70)
otnl Net Change by Change Orders(prior to this change order) ($833,114.70)
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $1,092,885.30
ET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $1.092,885.30
""his document shall become an amendment to the contract and all provisions of the contract will apply hereto.
Accepted by: ' / _ Date: /s .-4V
Engineer of Rec /t/-
Accepted by: Date:4//5422"V
ender
Accepted by: Date: Zs. _4 0•Z-15-
wr
Project: Ridgecrest WTP Electrical Upgrades Project
CCUA Bid No.: 1102-0050 CCUA Project No.: 19/20-A16
Summary of Change Orders
Date Description Contract Net Increase Net Decrease j Revised Contract
9/20/2021 ,Original Contract Price
� $1,926,000.00 �
2/13/2024 $0.00 ($833,114.70) $1,092,885.30
Change Order No. 1: ODP
6/26/2023 'Change Order No. 2: Add 300 days $0.00 $0.00
due to electrical gear delays
i I
12/24/2023 Change Order No. 3: Add 45 days $0.00 $0.00
due to electrical gear delays
Change Order No.4: Add 70 days
2/13/2024 ;due to electrical gear installation $0.00 $0.00
'and programming
;Summary of Totals: $1,926,000.00 $0.00 ($833,114.70) $1,092,885.30
Conota tame
ENTITLEMENT RECOMMENDATION LETTER rnArdcurwCampany
CCUA Ridgecrest WTP Electrical Upgrades Project
FOR Entitlement Recommendations:
ENGINEER PROJECT NO.: 100435.04
CCUA PROJECT NO. 1102-0050
CHANGE ORDER NUMBER: 4
DESCRIPTION: Extended Time
PREPARED BY: Sawcross,Inc.-Drew Hickinbotham
DATE: February 15,2024
Sawcross(Contractor)is providing construction services for the Ridgecrest WTP Electrical
Upgrades Project.
Change Order No.4 is the proposed extended time required for Sawcross to finalize the project
due to subcontractor programming delays.
The Contractor submitted a change order request for a lump sum amount of$0.00 on February
14,2024 to extend the time to perform the work.The Contractor requests 70 additional days
from contract completion of December 24,2023 per change order#3.
Schedule:
Contract Completion was 01/13/2023.
Contract Completion for CO#1 was 01/13/2023
Contract Completion for CO#2 was 11/9/2023
Contract Completion for CO#3 was 12/24/2023
Contract Completion is now 03/03/2024.
Budget:
The project construction budget was$1,926,000.00
The project after Change order No.1 was$1,092,885.30
The project after Change order No.2 was$1,092,885.30
The project after Change order No.3 was$1,092,885.30
The project after Change order No.4 is$1,092,885.30
David Rasmussen,PE,BCEE
Project Manager
Ardurra
SECTION 00660
Change Order Request Form
Project: Ridgeerest WTP Electrical Upgrades Project Bid No.19/20-A16 Project No.; 1102-0050
Change Order No.: 04
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion: 420 Ready for Final Payment 450
Increased from previous CO.: Substantial Completion: 345 Ready for Final Payment: 345
Decreased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time prior to this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Increase in time on this C.O.: Substantial Completion: 70 Ready for Final Payment: 70
Decrease in time on this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time with all approved
C.O.s: Substantial Completion: 835 Ready for Final Payment: 865
Change in Contract Price
Original Contract Price: $1.926,000.00
Increased from previously approved C.O.: 30.00
Decreased from previously approved C.O.: 4833,114.70
Increase in Contract price this C.O.: $0.00
Decrease in Contract price this C.O.: $0.00
Contract price with all approved C.O.s: $1.092.885.30
The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2)
all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all
previous progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract
referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by
prior Applications for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered
by this Application for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and
encumbrances; (5) payment is due and has not been previously requested for these amounts; (6) no markup has been applied to
reimbursable expenses.
Drew Hickinbotham (Project Manager; Sawcross, Inc.)
Contractor Name and Title
00660-1
Project No.1102-0050 CHANGE ORDER REQUEST FORM
Ridgecrest WTP Electrical Upgrades Project September 2021
SECTION 00660
Change Order Request Form
Cost Break Down Form: (instructions:use a separate form for each individual work item)
Description Unit Quantity . Unit Cost Extended Cost
Labor $ __
Materials
Equipment
$
Maintenance of Traffic $
Bonding
General Conditions
Overhead and Profit
Total firm fixed cost not to exceed axnount: $
Note:attached supporting documentation
RFI No.initiating the change:
Description: No costs associated with change order. Time extension requested due to delays in programminc
:Issues preventing others from completing ounchlisUtems.
Justification for the request: Sawcross requests time to be added to contract due to delays in programmino completion.
State the firm fixed cost not to exceed amount in words:
Contractor Sig ature / Date: 21/#21W
Printed Name: Ow-v icA 045 t4t Title: P AC{"RA/Vii",:x6A.