Change Order No.: 3 Date: 5/28/2028
Project: Potable Reuse Demonstration Facility
CCUA Bid No.: 21/22-A23
CCUA Project No.: 3019-001
Vendor: Wharton-Smith,Inc. Owner: Clay County Utility Authority
750 Monroe Road
Sanford,Fl 32771
(904)228-6998
Engineer of Record: Carollo Engineers
390 Interlocken Crescent,Suite 800
Broomfield,CO 80021
(303)324-1278
ORIGINAL CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP ADD
10/3/2022
DAYS222 60
SUB.COMP. 360� 9/28/2023 5/7/2024 7/6/2024
FINAL COMP, 390, 10/28/2023 5/11/2024 7/10/2024
INCREASE OR—
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) QTY. UNIT PRICE CONTRACT PRICK
Contract Increase
Contract Decrease
TOTAL INCREASE $0.00
TOTAL DECREASE _ $0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
ORIGINAL CONTRACT PRICE $4,540,000.00
Net Increases by Change Orders(prior to this change order) $0.00
'Net Decreases by Change Orders(prior to this change order) $0.00
Total Net Change by Change Orders(prior to this change order) $0.00
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $4,540,000.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $4,540.000.00
This document shall become an amendment to the contract and all provisions of the contract will apply hereto.
Accepted by: /G%r/l� Date: 2024-05-30
Engine of Record
ooaeir s��er nars caz�na
Travis Cassella&C=05 :L,n, ,-
o=�wna�ro��sm�in.m��,ou=o�mao-o m'
Accepted by: oam.,oz,.o Date: 2024-05-30
Vendor
Accepted by: t Date:0 24_(2)-s�'?i
net•.
Project: Potable Reuse Demonstration Facility
CCUA Bid No.: 21/22-A23 CCUA Project No.: 3019-001
Summary of Change Orders
Date Description Contract Net Increase Net Decrease Revised Contract
10/3/2022 Original Contract Price: $4,540,000.00
Change Order No. 1:
9/13/2023 Add 196 Calendar Days due to $0.00 $0.00
electrical gear delay
Change Order No. 2: Add 26
4/1/2024 Calendar Days due to electrical $0.00 $0.00
gear delay
Change Order No. 3: Add 60
5/24/2024 Calendar Days due to electrical $0.00 $0.00
gear delay
Summary of Totals: $4,540,000.00 $0.00 $0.00 $4,540,000.00
114111111101
Wharton-Smith, Inc.
CONSTRUCTION GROUP
Friday, May 24,2024
Sent via email
Mr. Paul Steinbrecher
Clay County Utility Authority
3176 Old Jennings Road
Middleburg, FL 32068
Chief Engineer
RE: CCUA Potable Reuse Demonstration Facility
Contract Time Extension Request
Mr.Steinbrecher,
The purpose of this letter is to notify Clay County Utility Authority of the schedule impact associated with the Square D.
Electrical Gear Package Delay we are facing on this project and to request additional contract time.
The Motor Control Center equipment was originally scheduled to ship in December 2023,the gear did not deliver until
May 22,2024. Installation of the electrical gear package and all associated start-up activities have been scheduled for the
last week of May and the first two weeks of June.
In response to the delays of the electrical gear,Cogburn provided a temporary panel to power equipment until the
delivery of the permanent motor control center. All process equipment with exception to the GAC Pump have been
started up,commissioned,and training has been provided. The facility is currently operating and will continue to do so
with minor outages during the final start-up work activities.
At this time based on our current projected schedule for the completion of the project,we request a contract extension
to the new Substantial Completion date of July 6,2024, and a new Final Completion Date of August 5, 2024.
If there are any questions or concerns with the above information, please feel free to contact me at 904-699-3253.
Sincerely,
WHARTON-SMITH,INC.
Travis Cassella
Project Manager
CC:
Sloan Hagerty, Project Executive(shagerty(twhartonsmith.com)
Warrick Sams, CCUA,wsams@clayutility.org
Linda Ortiz Figueroa,CCUA,lortizfigueroa@clayutility.org
750 Monroe Road • Sanford, Florida 32771 • (407)321-8410 • Fax: (407)829-4453
CG C032669 PC C048385 CU C056506
SECTION 00660
Change Order Request Form
Project:Potable Reuse Demonstration Facility Project No.: 3019-00] Change Order No.: 3
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion: 360 Ready for Final Payment:
Increased from previous C.O.: Substantial Completion: 222 Ready for Final Payment:
Decreased from previous C.O.: Substantial Completion: N/A Ready for Final Payment:
Contract time prior to this C.O.: Substantial Completion: 582 Ready for Final Payment:
Increase in time on this C.O.: Substantial Completion: 60 Ready for Final Payment:
Decrease in time on this C.O.: Substantial Completion: N/A Ready for Final Payment:
Contract time with all approved C.O.s: Substantial Completion: 642 Ready for Final Payment:
Change in Contract Price
Original Contract Price: $4,540,000.00
Increased from previously approved C.O.: N/A
Decreased from previously approved C.O.: N/A
Increase in Contract price this C.O.: N/A
Decrease in Contract price this C.O.: N/A
Contract price with all approved C.O.s: $4,540.000.00
The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2)
all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all
previous progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract
referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by
prior Applications for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered
by this Application for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and
encumbrances; (5) payment is due and has not been previously requested for these amounts; (6) no markup has been applied to
reimbursable expenses.
Travis Cassella, Project Manager—Wharton-Smith, Inc.
Contractor Name and Title
00660-1
CCUA Project No.:3019-001
FOR PROJECT No.: 11991 B 10 CHANGE ORDER REQUEST FORM
PROJECT NAME:CCUA Potable Reuse Demonstration Facility February 2020
SECTION 00660
Change Order Request Form
Cost Break Down Form: (instructions: use a se s arate form for each individual work item)
Description Unit Quantith Unit Cost Extended Cost
Labor
Materials
Equipment
Maintenance of Traffic
Bonding
General Conditions $
Overhead and Profit $
Total firm fixed cost not to exceed amount: MIL $
Note: attached supporting documentation
RFI No. initiating the change:
Description: No cost, contract time extension request.
Justification for the request: Time extension request due to Square D. electrical Bear nackace delay.
State the firm fixed cost not to exceed amount in words:
Travis Cassella�' �,;."""' „�
Contractor Signature: o„.�.o,,,,,�,oww Date: 5/24/2024
Printed Name: Travis Cassella Title: Project Manager
00660-2
CCUA Project No.:3019-001
FOR PROJECT No.: 11991 B 10 CHANGE ORDER REQUEST FORM
PROJECT NAME:CCUA Potable Reuse Demonstration Facility February 2020
Linda Ortiz Figueroa
From: Travis Cassella <tcassella@whartonsmith.com>
Sent: Friday, May 24, 2024 11:59 AM
To: Paul Steinbrecher; Linda Ortiz Figueroa;Warrick Sams;Jason Assouline; Pranjali Kumar;
Marya Redmond
Cc: Sloan Hagerty; Brent Oskin;Tucker Littlepage
Subject: RE: 22-117 CCUA Potable Reuse Demonstration -Tentative Start-Up Plan for MCC
Attachments: 22-117 Start Up Schedule_5-17-24.pdf
Follow Up Flag: Follow up
Flag Status: Flagged
This Message Is From an External Sender
This message came from outside your organization.
Team,
Following up as a reminder that the installation of the MCC will take place on Tuesday of next week. Major
upcoming activities to note:
- 5/28—5/30: Outage at facility for MCC install
- 6/3:Square D will be onsite for manufacturer proper installation inspection and VFD start-up.
- 6/4—6/5: Orthos will be onsite performing the Air Scour start-up for the BAC system
- Southern Flow will be onsite during the week of 6/3—6/7 finishing start-up and completing punch list
items.
Have a great holiday weekend.
Thanks,
Travis
From:Travis Cassella
Sent: Friday, May 17, 2024 5:18 PM
To: Paul Steinbrecher<psteinbrecher@clayutility.org>; Linda Ortiz Figueroa <lortizfigueroa@clayutility.org>; Warrick
Sams<WSams@clayutility.org>;Jason Assouline<jassouline@carollo.com>; Pranjali Kumar<pkumar@carollo.com>;
Marya Redmond <MRedmond@carollo.com>
Cc: Sloan Hagerty<shagerty@whartonsmith.com>; Brent Oskin <boskin@whartonsmith.com>
Subject: 22-117 CCUA Potable Reuse Demonstration-Tentative Start-Up Plan for MCC
Good Afternoon,
The MCC has shipped and is set to deliver next week. Please see the attached tentative start-up plan for work
associated.
Have a great weekend!
Thank you,