HomeMy WebLinkAbout08.b EDB Cognizant Lean-on Change Order 1 EXECUTIVE SUMMARY
AGENDA ITEM:
Proposed Change Order No. 1 to the Statement of Work for Workday Lean-on Services Support with
Collaborative Solutions Inc. (Collaborative)an Affiliate of Cognizant Worldwide Limited(Cognizant)
Date:November 1,2024
BACKGROUND:
CCUA never used an industry standard inventory system or software program to track inventory items. We
expensed all items as incurred except for our meters and MXU's which were tracked in our legacy
Filemaker system. With the implementation of Workday,CCUA planned to fully implement the inventory
module and begin to track inventory items consistent with industry standard processes.
CCUA was without an Inventory Manager for five months during the most critical stage of our Workday
implementation. During that time,we made the decision to scale back the inventory implementation. We
set-up and tested the inventory processes for the main warehouse and the inventory items housed there.
Very shortly after go-live, we began to experience some accounting anomalies related to the inventory
transactions. We attempted to work through these with Cognizant but were unable to identify the
underlying cause or remedy the situation. We made the decision to turn off the inventory tracking at that
time so we could focus on more pressing implementation issues and revisit the inventory issues later.
The ERP transition reached a stabilization period.We have the necessary resources to implement inventory
at this time.
BUDGET:
Staff determined the fee for professional services is fair, competitive, and reasonable. Collaborative
Solutions Inc.will be paid on a time and materials basis for a total estimated cost of$62,400 which will be
transferred from contingency of this year's operating budget.
RECOMMENDATION:
Staff respectfully recommends the Board of Supervisors' approval of Change Order No. 1 to the Statement
of Work for Workday Lean-on Services Support with Cognizant.
ATTACHMENTS:
Cognizant Project Change Order
//AW(Author)
//AW, KO(Review)
//KO//JDJ(Final)
cognizant
rif-couNi‘
c c.,\- 1.1...--------- --
Oat L
C:ex(el 4 iiiiiil
IYALAW
Project Change Order
. .
.. ,
=or
Project change order
This Change Order form is used for requesting, documenting and approving changes to the
Workday deployment or other applicable service offering, including, but not limited to, changes
to the project's Scope, changes for a major configuration element, project timeline/schedule
changes, integration specifications changes, addition of resources or any other deliverable
change from the originally planned Workday deployment or applicable service offering.
Summary
Clay County Utility Clay County Utility Authority
Authority:
SOW/Project Name: Clay County Utility Authority - P1 to CVS 2023-24
PROJ_69340
Change Order#: C01 —Adding Inventory Implementation To Scope
Project Manager (Clay Karen Osborne, Clay County Utility Authority
County Utility Authority):
Project Sponsor (Clay Jeremy Johnston, Executive Director
County Utility Authority):
Engagement Manager: Mike Thomas, Cognizant
Acceptance Due Date: 11/8/2024
Change Type: Change In Scope (Additional Hours Added)
Impact Assessed by: Mike Thomas (EM Cognizant)
Stephanie Pacienza (Fins Lead Cognizant— Provided Scope
and Timing)
Karen Osborne (Project Lead CCUA)
Priority: High
Billing: Bill Separately under new project
Contract Line Type: Time and Materials
Is new PO# required? No
Request Description
Clay County Utility Authority has requested that Cognizant re-engage in the deployment of the
Inventory Module. This was originally in scope but due to changes in resources from both Cognizant
and CCUA—we will need to go back through the normal deployment process including a brief Plan
Stage, Architect Workshops, Customer Confirmation Session, Testing, Deployment, & Post production
Support. These will inevitably be abbreviated stages but all the same will be required for an adequate
implementation.
Business Purpose / Reason for Change
2
Adding Inventory implementation to the scope of the CVS document and CO1 will provide the
hours rather than take hours from the Lean On Agreement.
Impact Assessment
Project This will be considered a new implementation of the Inventory module and
Activities functionality. This will not affect the current Lean On activities. A review of the
Affected: work done during the initial implementation has been assessed by Cognizant
and provided to CCUA.
It has been concluded that this project will need to follow the normal Workday
Methodology Stages; Plan Stage, Architect & Configure Stage, Test Stage,
Deployment Stage, and finally Postproduction Stage.
Deliverable The Project in this Change Order will follow the normal deployment
s Affected: Methodology with and abbreviated planning stage, Architect Stage, Config &
Prototype stage, as well as Test Stage, Deployment Stage, and Post Prod
Support Stage.
In Addition— In accordance with the original Scope From The Statement Of
Work executed on 2/23/2023 and culminated on 5/3/24:
Functional Scope:
• Locations
o Up to one hundred fifty(150) Business Asset and Ship-To
Locations
o Up to three hundred (300) inventory locations organized in a
hierarchy structure with up to four(4) levels of hierarchy
• Inventory:
o Inventory Sites - Up to three (3) Inventory Sites
o Inventory Stocking/Bin Locations - Up to one thousand (1,000)
Inventory Stocking/Bin Locations
o Convert Item Master— up to one thousand (1,000) from two (2)
source systems (Cartegraph, Filemaker)
o Inventory Fulfillment
o Inventory Replenishment
o They will need an Inventory Dashboard in Workday created for
Inventory reporting and tasks. One Dashboard for Managers
and One for Inventory technicians.
o Client went live with Workday 4/1/24. Inventory was in scope but
not fully supported internally as the client's Inventory Manager
resigned. Then shortly after go live the resource from Cognizant
who implemented their Inventory Functionality resigned.
o Client does not have a good understanding of Inventory
Accounting principles in Workday, Inventory Account Posting
rules or why Inventory Accounting was so skewed on the
Inventory Cost Adjustment ledger account that they stopped all
inventory functionality in Workday Mid-May 2024 and did two
3
huge manual journal entries to balance their spend/inventory
cost adjustment ledger accounts and are handling inventory
activities outside of Workday for now.
o They have 1 Main storeroom and several sub storerooms. The
Main storeroom will issue inventory directly to technicians and
replenish inventory to sub storerooms. Sub storerooms will fill
department inventory stock requests as will the main storeroom.
Data Conversion:
• Inventory Beginning Balances
Project Project Schedule:
Schedule Stage Start Date End Date #of Weeks Notes
Impact: Plan Stage 11/4/2024 11/22/2024 3
Design&Requirements 11/25/2024 12/27/2024 5 Thanksgiving Holiday Included In This Time
Config&Unit Testing 12/30/2024 2/14/2025 7 Includes Christmas&New Years
Client Testing 2/17/2025 3/14/2025 4
Sandbox Migration&Testing 3/17/2025 3/28/2025 2
Prod Migration 3/31/2025 4/4/2025 1
Post Prod Support&KT 4/7/2025 4/18/2025 2
Total Weeks 24
Note:
*Design & Requirements will likely take 4 weeks but have accounted for the
Thanksgiving Holiday
*Config & Unit Testing will likely take 6 weeks but have account for the
Christmas & New Year's Holiday
Pricing The following is the Pricing Matrix:
Matrix Role Rate Hours Cost
Engagement Manager $240 48 $11,520
CVS Consultant $212 240 $50,880
Total 288 $62,400
Payment Terms
Time & Materials SOW: This Change Order will be billed monthly on a Time and Materials
("T&M") Basis based on actual usage at the rates set forth in the SOW and as identified
in the Pricing Matrix above.
Assumptions
All assumptions from the SOW dated May 1, 2024 and ending on September 30, 2025
apply to this change order.
Additional Assumptions:
o Cognizant Consultants will:
4
• Configure inventory settings and functionality based on client design
decisions
• Put together documentation of functionality to be used for training
purposes
• Provide testing scenarios and support client testing efforts
• Move final approved configuration to Production after client sign off.
• Knowledge Transfer Sessions On Best Practice on Inventory
Accounting
o CCUA will:
• Attend weekly design and working sessions with consultant
• Conduct all end user training internally
• Conduct all testing for inventory functionality
• Validate data and configuration after testing to include account posting
for inventory transactions
• Validate all data conversion in Production.
Authorization
Clay County Utility Authority Authorization Collaborative Solutions LLC Authorization
Signature Signature
Name Name
Job Title Job Title
Date Date
5