Change OrderNo.: 2 Date: 10/30/2024
Project: Governor's Park Wastewater Lift Station Project and Reclaimed Water Pump Station Project
CCUA Bid No.: 2022/2023-A06
CCUA Project No.: 1127-004
Vendor: Sawcross Incorporated Owner: Clay County Utility Authority
10970 New Berlin Road 3176 Old Jennings Road
Jacksonville,Florida 32226-2270. Middleburg,Florida 32068
904-751-7500 (904)272-5999
Engineer of Record: Ardurra
100 Center Creek Road,Suite 108
St.Augustine,Florida 32084
904-562-2185
ORIGINAL CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 8/25/2023
DAYS ADD 70
SUB.COMP. 413 10/14/2024 12/23/2024
FINAL COMP. 534 2/12/2025 6/13/2025
INCREASE OR
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) QTY. UNIT PRICE CONTRACT PRICE
Contract Increase
Contract Decrease
TOTAL INCREASE $0.00
TOTAL DECREASE $0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
ORIGINAL CONTRACT PRICE $7,683,000.00
Net Increases by Change Orders(prior to this change order) $0.00
Net Decreases by Change Orders(prior to this change order) ($792,106.37)
Total Net Change by Change Orders(prior to this change order) ($792,106.37)
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $6,890,893.63
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $6,890,893.63
This document shall become an amendment to the contract and all provisions of the contract will apply hereto.
Accepted by: Date:
En . r of Record
1
Accepted by: ` � Date: 1 03 1 ji!202-4�,J
1
endor
Accepted by: Date:
Owner
LA
I,
SAWCROSS INCORPORATED
10970 NEW BERLIN ROAD JACKSONVILLE,FL 32226-2270
904-751-7500(VOICE)904-751-0600(FAX)WWW.SAWCROSS.COM(INTERNET)
October 22, 2024
Paul Steinbrecher, P.E.
Clay County Utility Authority (CCUA)
3176 Old Jennings Road
Middleburg, FL 32068
Subject: CCUA Governors Park WWLS — Proposed Change Order#002 (Time
Extension)
Dear Paul,
This letter is to request an extension of the contractual Substantial Completion date
from 10/14/2024 to 12/23/2024. The request for additional time is a result of the
delays with the developer providing easement access to Clay Electric to provide
permanent power onsite and the impacts from Hurricane Helene (9/25/2024 —
9/27/2024) and Hurricane Milton (10/8/2024 — 10/10/2024).
Please see this letter as a request for an additional seventy (70) day(s). Revised
Substantial Completion date is Wednesday 12/23/2024.
Total Costs $0.00
Total Additional Contract Time (Calendar Days) Seventy (70) Day(s)
Sincerely,
its m,
Drew Hickinbotham
Project Manager
904-751-7500 Ext. 113
drewh@sawcross.com
CONTRACTORS&ENGINEERS
CGC 36203 CMC 56728 CUC 56787 UC 300564
SECTION 00660
Change Order Request Form
Project: Governor's Park Wastewater Lift Station Project and Governor's Park Reclaimed Water Pump Station Project
Bid No.: 2022/2023-A06 Project No.: 1127-004
Change Order No.: 002
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion: 413 Ready for Final Payment: 534
Increased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Decreased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time prior to this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Increase in time on this C.O.: Substantial Completion: 70 Ready for Final Payment: 353
Decrease in time on this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time with all approved
C.O.s: Substantial Completion: 483 Ready for Final Payment: 887
Change in Contract Price
Original Contract Price: $7,683,000.00
Increased from previously approved C.O.: $0.00
Decreased from previously approved C.O.: $(792,106.37)
Increase in Contract price this C.O.: $0.00
Decrease in Contract price this C.O.: $0.00
Contract price with all approved C.O.s: $6.890,893.63
The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2)
all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all
previous progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract
referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by
prior Applications for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered _
by this Application for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and
encumbrances; (5) payment is due and has not been previously requested for these amounts; (6) no markup has been applied to
reimbursable expenses.
00660-1
GOVERNOR'S PARK WASTEWATER LIFT STATION PROJECT CHANGE ORDER REQUEST FORM
AND GOVERNOR'S PARK RECLAIMED WATER PUMP STATION PROJECT OCTOBER 2022
SECTION 00660
Change Order Request Form
Drew Hickinbotham (Sawcross, Inc.; Project Manager)
Contractor Name and Title
Cost Break Down Form: (instructions:use a separate form for each individual work item)
Description Unit Quantity Unit Cost Extended Cost
Labor $
Materials
Equipment __ $
Maintenance of Traffic _ $
Bonding $
General Conditions $
-----------
Overhead and Profit $
----- -- ----------
Total firm fixed cost not to exceed amcnill111111111111111111111111.11 $
Note:attached supporting documentation
RFI No. initiating the change:
Description: No costs associated with change order. Time extension requested due to delays in easement provided
by developer. Also, Hurricane Helene and Hurricane Milton delays.
Justification for the request: Sawcross requests for time to be added to contract due to delays in the easement
provided by the developer to Clay Electric to obtain permanent power onsite.
State the firm fixed cost not to exceed amount in words:
Contractor Signature: — Date:
00660-2
GOVERNOR'S PARK WASTEWATER LIFT STATION PROJECT CHANGE ORDER REQUEST FORM
AND GOVERNOR'S PARK RECLAIMED WATER PUMP STATION PROJECT OCTOBER 2022
SECTION 00660
Change Order Request Form
Printed Name: Title:
00660-3
GOVERNOR'S PARK WASTEWATER LIFT STATION PROJECT CHANGE ORDER REQUEST FORM
AND GOVERNOR'S PARK RECLAIMED WATER PUMP STATION PROJECT OCTOBER 2022