Clay County Utility Authority
3176 Old Jennings Road
Middleburg,Florida 32068-3907
ANABELLE ISLAND SUBDIVISION,PHASES 3,4&5
CONSISTING OF 513 SINGLE FAMILY LOTS
Parcel No. 23-05-25-010097-000-00 (Mid-Clay System)
Clay County Name of Project
DEVELOPER AGREEMENT
THIS AGREEMENT GRANTS TO THE"UTILITY"(AS HEREINAFTER DEFINED)AN ENFORCEABLE LIEN
ATTACHING TO THE LANDS DESCRIBED IN EXHIBIT"A"HEREIN(THE"PROPERTY")FOR CERTAIN
DEFERRED CAPACITY AND CONNECTION CHARGES TO BE PAID UPON APPLICATION FOR SERVICE.
THIS DEVELOPER AGREEMENT("Agreement"), made and entered into this I)- day of/Vev&i 4Cr ,
2024, by and between DFC ANABELLE, LLC, a Florida limited liability company, hereinafter referred to as
"Developer",and CLAY COUNTY UTILITY AUTHORITY,an independent special district established under
Chapter 94-491, Laws of Florida, Special Acts of 1994, hereinafter referred to as "Utility".
WHEREAS,Developer owns or controls lands located in Clay County,Florida,and described in Exhibit
"A," attached hereto and incorporated herein by reference (hereinafter "Property");
WHEREAS, Developer desires that the Utility provide central potable water, pumping, treatment and
distribution service; central wastewater collection, treatment and disposal service; and central reclaimed water
service for the Property;
WHEREAS, the Utility is willing to provide, in accordance with the provisions of this Agreement central
potable water,wastewater,and reclaimed water service to the Property and thereafter operate applicable facilities so
that the occupants of the improvements on the Property will receive adequate potable water, wastewater; and
reclaimed water service from the Utility; and
WHEREAS, the parties wish to enter into this Agreement setting forth their mutual understandings and
undertakings regarding the furnishing of potable water,wastewater,and/or reclaimed water service by the Utility to
the Property.
NOW, THEREFORE, for and in consideration of the premises, the mutual undertakings and agreements
herein contained and assumed, Developer and Utility hereby covenant and agree as follows:
1. The foregoing statements are true and correct.
2. The following definitions and references are given for the purpose of interpreting the terms as used in
this Agreement and apply unless the context indicates a different meaning:
(a) "Consumer Installation" - All facilities ordinarily on the consumer's side of the point of
delivery.
(b) "Contribution-in-Aid-of-Construction (CIAC)" - The sum of money and/or the value of
property represented by the cost of the wastewater collection system, potable water distribution system, and
reclaimed water distribution system constructed or to be constructed which Developer or owner transfers,or agrees
to transfer,to Utility, if so designated by the Utility, at no cost to Utility to provide utility service to the Property.
(c) "Equivalent Residential Connection (ERC)" -A factor expressed in gallons per day(GPD)
which is used to convert a given average daily flow(ADF)to the equivalent number of residential connections. For
this purpose the average daily flow of one potable water ERC is(450)GPD,one wastewater ERC is(311)GPD,and
one reclaimed water ERC is(275) GPD.
-2-
(d) "Point of Delivery" - The point where the pipes or meter of Utility are connected with the
pipes of the consumer. Point of delivery for potable water service and reclaimed water service shall be at the
consumer's side of the meter and for wastewater service at the lot or property line. Utility shall, according to the
terms and conditions hereof,own all pipes and appurtenances to the point of delivery unless otherwise agreed. The
pipes and appurtenances inside the point of delivery shall belong to others.
(e) "Service" - The readiness and d ability on the part of Utility to furnish and maintain potable
water, reclaimed water, and wastewater service to the point of delivery for each lot or tract pursuant to rules and
regulations of applicable regulatory agencies.
3. Assurance of Title-Developer represents and warrants that Developer is the owner of the Property
and has the legal right to grant the exclusive rights of service contained in this Agreement. Upon request,Developer
agrees to deliver to Utility evidence of such ownership including any outstanding mortgages, taxes, liens and
covenants.
4. Connection Charges-In addition to the contribution of any wastewater collection systems,potable
water distribution systems, and reclaimed water systems where applicable,and further to induce Utility to provide
potable water,reclaimed water,and wastewater service,Developer hereby agrees to pay to Utility the following fees
and charges, as defined in the Rate Resolution (including Service Availability Policy), upon execution of this
Agreement in order to reserve capacity in the System:
(a) Water Capacity Charge:
($450.00 x 513 ERCs) $ 230,850.00 *
Alternative Water Supply Surcharge:.
($388.01 x 513 ERCs) $ 199,049.13 *
SJWMD Black Creek Water Resource Charge:
($105.19 x 513 ERCs) $ 53,962.47 *
Wastewater Capacity Charge:
($4,100.00 x 513 ERCs) $2,103,300.00 *
Reclaimed Water Capacity Charge:
($300.00 x 513 ERCs) $ 153,900.00 *
Total Capacity Charges to be Deferred $ 2,741,061.60
(b) Debt Service Charge:
($191.00 x 513 ERCs) $ 97,983.00
(c) Main Extension Charge—Water $ 73,359.00.
Main Extension Charge—Wastewater $ 155,700.63
Main Extension Charge—Reclaimed Water $ 69,408.90
(d) Meter Installation Charge $ N/A **
Effluent Reclaimed Meter Installation $ N/A **
(e) Plan Review Fee $ 1,732.50
(f) Inspection Fee $ 20,809.96
(g) Recording Fee $ 162.59
Subtotal $ 3,160,218.18
Less Total Capacity Charges to be Deferred $2,741,061.60
Total due at execution of Developer Agreement $ 419,156.58✓
* - Includes 513 ERCs, based on 513 single-family lots, which are deferred and to be paid at the time of
application for service via meter install, in accordance with Utility's Rate Resolution.
** - See Paragraph 44 for the explanation of charges.
*** - The potable water meters and reclaimed water meters will be paid by each builder or customer upon
application for building water for each lot. This Agreement does not include a provision for any other
separate landscape irrigation meters for the Property or park areas.
Note: Items (e) and (f) are estimates and subject to adjustment based on actual costs incurred.
-3-
Method of Payment/Security Interest- Utility agrees to defer payment and collection of certain capacity
charges as set forth above on an individual per lot basis,until such time as water service is applied for as to such lot
within the Property. In consideration for such delay Developer does hereby grant,convey,hypothecate,and pledge
to Utility a security interest in the lands described in Exhibit"A"herein. Such security interest shall constitute an
enforceable lien on the individual lots as depicted on the plat of said lands recorded(or to be recorded)in the public
records of Clay County, Florida. The lien hereby created will be released by Utility on a lot by lot basis upon
payment to Utility of the capacity charges assigned to the lot(s)to be released. The party requesting the release shall
be responsible for recording the release in the public records.
The priority of the lien granted herein is governed by Chapter 94-491,Laws of Florida,Special Acts of 1994
(the "Act"), which is recorded in OR BK 1524, PG 1798-1836, public records of Clay County, Florida. Specific
reference is made to Section 11 and Section 19.(6)and(9)of the Act,respectively,which provide in pertinent part
that the priority of such lien "... shall be superior and paramount to the interest on such parcel or property of any
owner, lessee, tenant, mortgagee, or other person except the lien of county taxes and shall be on a parity with the
lien of any such county taxes." Utility shall not be obligated to provide the services herein for any particular lot or
parcel until such time as the capacity charges and related costs have been paid in full for that lot or parcel.
Payment of the charges in Paragraph 4 does not and will not result in Utility waiving any of its rates or rules
and regulations and their enforcement shall not be affected in any manner whatsoever by Developer making
payment of same.Except as specifically stated,Utility shall not be obligated to refund to Developer any portion of
the value of the above charges for any reason whatsoever nor shall Utility pay any interest upon the above charges
paid.
Except as otherwise stated in this Agreement,neither Developer nor any person or other entity holding any
of the Property by,through or under Developer, or otherwise, shall have any present or future right,title, claim or
interest in and to the charges paid or to any of the potable water, reclaimed water, or wastewater facilities and
properties of Utility, and all prohibitions applicable to Developer with respect to no refund of such charges, no
interest payment on said charges and otherwise, are applicable to all persons or entities.
Paid capacity or connection charges may not be applied to offset any service bill or other claims of Utility.
5. On-Site Installations-On-site facilities are those located within the Property for which Developer is
requesting service. Developer shall convey to Utility, if so designated by Utility,all on-site water and wastewater
lines, laterals,mains, lift stations,pump stations and appurtenant facilities(collectively referred to as"Components"
or"On-Site System")on the Property with all contractual guarantees relating thereto. Conveyance shall take place
within a reasonable time after installation of the On-Site System but prior to Utility's obligation to provide service.
Until such time as the On-Site System is conveyed,the same shall be operated and maintained by Developer. In its
sole discretion,Utility may decline to accept the On-Site System,may lease the On-Site System from Developer,or
agree to such other arrangement as it deems appropriate.
Utility shall have the right and obligation, at the Developer's expense, to construct and/or approve the
construction of the on-site installations which shall be owned and maintained by Utility,if so designated by Utility.
The Utility shall also have the right to review all plans and specifications, connections to its system and the
Developer shall pay a fee equal to the Utility's actual cost to review such plans and specifications. The Utility shall
have the right to inspect all phases of construction undertaken by outside contractors for facilities which are to be
owned by the Utility, if so designated by Utility. The Developer will reimburse the Utility for its costs for such
inspection, including all overhead associated with same. Where on-site temporary pump stations or backflow
prevention devices are required, they shall be paid for one hundred percent(100%) by the Developer without any
provision for refund. Utility reserves the right to require backflow prevention devices on all potable water service
connections.
-4-
The On-Site System shall be constructed in compliance with all regulatory requirements and the
specifications and requirements of Utility. No construction shall commence until Utility has reviewed and approved
Developer's contractor and the plans and specifications for construction of the potable water,reclaimed water, and
wastewater systems for the project. The proposed electrical transformer layout of the electric utility providing
service must be provided to the Utility prior to commencement of construction.
Developer shall guarantee Utility against defects in material and workmanship for the portion of the On-Site
System to be owned by the Utility or County,if so designated by Utility. Developer shall secure from its contractor
a written and fully assignable warranty that the system installed will be and remain free from all defects, latent or
otherwise,with respect to workmanship, materials and installation in accordance with Utility-approved plans and
specifications,for a period of two(2)years from the date of the system acceptance by the Utility,and immediately
assign the same and the right to enforce the same to the Utility on or before such date.
The Developer shall also provide to the Utility, at Developer's sole expense, such maintenance bond and
other form of security acceptable to Utility in such amounts approved by Utility,which by its or their express terms
protect and indemnify Utility against any loss,damage,costs,claims,debts or demands by reason of defects, latent
or otherwise, in the system to be and remain in effect for two (2)years from the date of the system acceptance by
Utility.
In addition to any other promises, guarantees or warranties to be provided by Developer to the Utility
hereunder, Developer agrees to protect and indemnify Utility against any loss, damage, costs, claims, debts or
demands by reason of defects, latent or otherwise, in the system which could not have been reasonably discovered
upon normal engineering inspection, to be and remain in effect for a period of two (2) years from the date of the
system's acceptance by Utility.
Developer agrees to transfer to Utility, if so designated by Utility, title to all water distribution and
wastewater collection systems installed by Developer or Developer's contractor,which the Utility has agreed shall
be owned and maintained by it pursuant to the provisions of this Agreement and shall:
(a) Deliver a Bill of Sale and No Lien Affidavit in a form acceptable to Utility for such potable water
distribution, reclaimed water distribution, and wastewater collection systems.
(b) Provide copies of invoices and Release of Liens from contractor for installation of the utility systems
as well as for any repairs to the Systems which may have been caused by other subcontractors during construction.
(c) Assign any and all warranties and/or maintenance bonds as set forth herein.
(d) Provide all operations, maintenance and parts manuals, as-built plans complying with Utility's
specifications, and other documents required for operation of the utility system.
(e) Convey to Utility, if so designated by Utility, easements and/or rights-of-way covering all areas in
which potable water,reclaimed water,and wastewater systems are installed,with adequate legal access to same,by
recordable document satisfactory to Utility.
(f) Convey to Utility,if so designated by Utility,by recordable document in form satisfactory to Utility,
fee simple title to lift station and pump station sites, along with recordable ingress/egress easement documents.
(g) Provide a copy of the Project Engineer's final certification of completion to the Florida Department of
Environmental Protection certifying installation of all potable water and wastewater facilities in accordance with
approved plans.
-5-
6. Off-Site Installations-Developer shall further construct all transmission mains, pump stations and.
appurtenant facilities necessary to connect the On-Site System to the nearest appropriate point in Utility's
transmission system, as determined by Utility. Utility may require Developer to oversize off-site transmission
mains and appurtenant facilities in a manner consistent with Utility's Wastewater System Master Plan. The costs
associated with construction of over-sized facilities which provide Utility with excess capacity for the benefit of
other properties may be subject to refundable advance treatment pursuant to Utility's Service Availability Policy,as
then in effect. The same construction standards,warranty requirements,maintenance bond requirements,transfer of
title by Bill of Sale,and indemnification requirements,as provided under paragraph 5 of this Agreement,shall also
apply to the Off-Site installations.
7. Agreement to Serve-Upon the completion of construction of the On-Site and Off-Site Facilities by
Developer, or an appropriate phase thereof,and compliance with the terms and conditions of this Agreement and
Utility's Service Availability Policy, Utility will allow connection or oversee the connection of the wastewater
collection facility, potable water distribution facility,and/or reclaimed water facility installed by Developer to the
central facilities of Utility in accordance with all rules, regulations and orders of the applicable governmental
authorities. Utility agrees that once it provides potable water, reclaimed water, and/or wastewater service to the
customers within the Property that it will continuously provide such service, at its cost and expense, but in
accordance with the other provisions of this Agreement,the then current Rate Resolution in effect for Utility, and
the requirements of the governmental authorities having jurisdiction over the operations of Utility. Utility shall not
be liable for any temporary interruptions in service as a result of equipment failure, emergencies or Act of God.
The covenants and agreements of Developer contained in Paragraphs 5; 6, and 7, hereof shall survive
Utility's acceptance of any On-site and Off-site Facilities and Utility's commencement of service to the Property.
Should any such covenant or agreement of Developer in fact be outstanding following either or both of such dates,
then, notwithstanding any contrary provision contained herein,Utility may,upon thirty(30)days advance written
notice and demand for cure mailed to Developer,temporarily interrupt service to the Property until such outstanding
covenant or agreement of Developer is satisfied in full. Utility shall not be liable for any temporary interruptions in
service as a result of any action authorized or permitted by this paragraph.
8. Application for Service-Developer,or any owner of any parcel of the Property,or any occupant of
any residence, building or unit located thereon shall not have the right to and shall not connect any consumer
installation to the facilities of Utility until formal written application has been made to Utility by the prospective
user of service,or either of them,in accordance with the then effective rules and regulations of Utility and approval
for such connection has been granted.
9. Easements-Developer hereby grants and gives to Utility, its successors and assigns,but subject to
the terms of this Agreement, the exclusive right or privilege to construct, own, maintain and operate the potable
water,reclaimed water,and wastewater facilities to serve the Property in,under,upon,over and across the present
and future streets, roads, alleys, utility easements, reserved utility strips and utility sites. Mortgagees, if any,
holding prior liens on the Property shall be required to release such liens, subordinate their position or join in the
grant or dedication of the easements or rights-of-way, or give to Utility assurance by way of a "non-disturbance
agreement",that in the event of foreclosure,mortgagee would continue to recognize the easement rights of Utility.
All potable water, reclaimed water, and wastewater collection facilities, save and except installations owned by
Developer,or its successors or assigns,shall be covered by easements or rights-of-way if not located within platted
or dedicated roads or rights-of-way for utility purposes and there shall be adequate legal access to same.
The use of easements granted by Developer to Utility shall not preclude the use by other utilities of these
easements,such as for cable television,telephone,electric,or gas utilities. However,the use of such non-exclusive
easements by third parties shall not interfere with Utility's utilization of same. Utility hereby agrees that all
easement grants will be utilized in accordance with the established and generally accepted practices of the potable
water, reclaimed water, and wastewater industry with respect to the installation of all its facilities in any of the
easement areas.
-6-
10. Utility's Exclusive Right'to Utility Facilities-Developer agrees with Utility that all potable water,
reclaimed water,and wastewater facilities accepted by Utility in connection with providing potable water,reclaimed
water and wastewater services to the Property, shall at all times remain in the sole, complete and exclusive
ownership of Utility, and any person or entity owning any part of the Property or any residence, building or unit
constructed or located thereon,shall not have any right,title,claim or interest in and to such facilities or any part of
them,for any purpose,including the furnishing of potable water,reclaimed water,and wastewater services to other
persons or entities located within or beyond the limits of the Property.
11. Exclusive Right to Provide Service-Developer shall not engage in the business of providing potable
water services or sanitary wastewater services to the Property during the period of time Utility provides potable
water and wastewater services to the Property. Utility shall have the sole and exclusive right and privilege to
provide potable water and wastewater services to the Property and to the occupants of such residence, building or
unit constructed thereon.
12. Rates-Utilityagrees that the rates to be charged to Developer and individual consumers of potable
g g p
water and wastewater services shall be those set forth in the then current Rate Resolution most recently adopted by
the Board of Supervisors of Utility as may be amended from time to time. However,notwithstanding any provision
in this Agreement, Utility, its successors and assigns, may establish, amend or revise, from time to time in the
future, and enforce in a reasonable manner, rates or rate schedules so established.
Notwithstanding any provision in this Agreement,Utility may establish,amend or revise,from time to time,
in the future, and enforce rules and regulations covering potable water and wastewater services to the Property.
However,all such rules and regulations so established by Utility shall at all times be reasonable and subject to such
regulations as may be provided by law or contract.
13. Quality of Wastewater-No substance other than domestic wastewater will be placed into the sewage
system and delivered to the lines of the Utility directly by Developer. The Developer shall,be required to install
grease traps for all non-residential kitchen facilities and sand traps if floor drains are connected to the Utility's
sanitary wastewater transmission system. Such installation shall be in accordance with the requirements of the
Utility. Should any non-domestic wastes,grease,or oils,including,but not limited to,floor wax,paint,chlorides,or
salt water or any substances an`d materials which contain any hazardous, flammable, toxic and/or industrial
constituents, be directly delivered by Developer to the lines, of the Utility, Developer will be responsible for
payment of the cost and expense required in correcting or repairing any resulting damage to the system or property
of third parties.
14. Binding Effect of Agreement-This Agreement shall be binding upon and shall inure to the benefit of
Developer,Utility and their respective assigns and successors by merger,consolidation,conveyance or otherwise.
Any assignment or transfer by Developer shall be subject to Utility approval which shall not be unreasonably
withheld provided the assignee or transferee shall acknowledge in writing that it assumes the duties and
responsibilities of Developer as set forth in this Agreement.
15. Notice-Until further written notice by either party to the other,all notices`provided for herein shall
be in writing and transmitted by messenger,by mail,or by e-mail,and if to Developer,shall be mailed or delivered
to Developer at:
DFC Anabelle, LLC
Attn:Kyle Hudson
13000 Sawgrass Village Circle,
Bldg. 5, Ste. 24
Ponte Vedra Beach, Florida 32082
-l-
and if to the Utility at:
Clay County Utility Authority
3176 Old Jennings Road
Middleburg, Florida 32068-3907
or at such other address as specified in writing by either party to the other.
16. Laws of Florida-This Agreement shall be governed by the laws of the State of Florida and it shall be
and become effective immediately upon execution by both parties hereto, subject to any approvals which must be
obtained from governmental authority, if applicable.
17. Costs and Attorney's Fees - In the event the Utility or Developer is required to enforce this
Agreement by court proceedings,by instituting suit or otherwise,then venue shall lie in Clay County,Florida,and
the prevailing party shall be entitled to recover from the other party all cost incurred,including reasonable attorney's
fees.
18. Force Majeure'-In the event that the performance of this Agreement by either party is prevented or
interrupted in consequence of any cause beyond the control of either party,including,but not limited to Act of God
or of the public enemy,war, national emergency, allocation or of other governmental restrictions upon the use or
availability of labor or materials, civil disorder, strike, embargo, natural disaster or catastrophe, unforeseeable
failure or breakdown of transmission, treatment or other facilities, governmental rule, act, order, restriction,
regulation, statute, ordinance, or order, decree,judgment, restraining order or injunction of any court, said party
shall not be liable for such non-performance.
19. Indemnification-Developer agrees to indemnify and hold the Utility harmless from and against any ,
and all liabilities, claims, damages, costs and expenses (including reasonable attorney's fees) to which it may
become subject by reason of or arising out of Developer's performance of this Agreement. This indemnification
provision shall survive the actual connection to Utility's potable water, reclaimed water and wastewater systems.
MISCELLANEOUS PROVISIONS
20. The rights, privileges, obligations and covenants of Developer and Utility shall survive the
completion of the work of Developer with respect to completing the facilities and services to any development phase
and to the Property as a whole.
21. This Agreement supersedes all previous agreements or representations, either verbal or written,
heretofore in effect between Developer and Utility, made with respect to the matters herein contained, and when
duly executed,constitutes the agreement between Developer and Utility. No additions,alterations or variations of
the terms of this Agreement shall be valid,nor can provisions of this Agreement be waived by either party,unless
such additions, alterations,variations or waivers are expressed in writing and duly signed.
22. Whenever the singular number is used in this Agreement and when required by the context,the same
shall include the plural, and the masculine, feminine and neuter genders shall each include the others.
23. Whenever approvals of any nature are required by either party to this Agreement, it is agreed that
same shall not be unreasonably withheld or delayed.
24. The submission of this Developer Agreement for examination by Developer does not constitute an
offer but becomes effective only upon execution thereof by Utility.
-8-
•
25. Failure to insist upon strict compliance of any of the terms,covenants,or conditions herein shall not
be deemed a waiver of such terms,covenants, or conditions,nor shall any waiver or relinquishment of any right or
power hereunder at any one time or times he deemed a waiver or relinquishment of such right or power at any other
time or times.
26. It is because of inducements offered by Developer to Utility that Utility has agreed to provide potable
water, reclaimed water, and wastewater services to Developer's project. Capacity reserved hereunder cannot and
shall not be assigned by Developer to Third Parties without the written consent of Utility, except in the case of a
bona-fide sale of Developer's Property.
27. Utility shall, as aforesaid, at all reasonable times and hours, have the right of inspection of
Developer's internal lines and facilities. This provision shall be binding on the successors and assigns of the
Developer.
28. The parties hereto recognize that prior to the time Utility may actually commence upon a program to
carry out the terms and conditions of this Agreement,Utility may be required to obtain approval from various state
and local governmental authorities having jurisdiction and regulatory power over the construction,maintenance,and
operation of Utility. The Utility agrees that it will diligently and earnestly make the necessary proper applications to
all governmental authorities and will pursue the same to the end that it will use its best efforts to obtain such
approval. Developer agrees to provide necessary assistance to Utility in obtaining the approvals provided for herein.
Upon execution of this Agreement, Utility may require the payment of a reasonable fee to defray Utility's legal,
engineering, accounting and administrative and contingent expense.
29. It shall be Developer's responsibility to provide acceptable as-built drawings of the potable water,
wastewater and reclaimed water systems installed by Developer,in accordance with Utility's standard specifications,
details and notes,which are to be accepted by Utility for ownership and maintenance,as set forth in paragraph 5(d)
herein;and Utility's charges associated with the review and quality assurance of the CAD as-built survey drawings
will be paid directly by Developer's licensed underground utility contractor and shall be provided in accordance with
CCUA's "As-built Specifications Standards Manual", which can be obtained from the Utility's website
(www.clayutility.org).It shall be Developer's responsibility to properly instruct his contractor to contact Utility for
an estimate of such charges and clarification of the required as-built drawing procedures.
30. It shall be Developer's responsibility or Developer's customers'responsibility,utilizing the project's
potable water, reclaimed water, and wastewater service within Developer's project, to apply to Utility for service
after the installation of the potable water, reclaimed water, and wastewater utilities have been completed and
accepted by Utility. Upon completion of application for potable water,reclaimed water,and wastewater service and
payment of the appropriate charges set forth in Utility's then current applicable Rate Resolution, including any
security deposits required, service will be initiated to customers within Developer's Property.
31. Developer shall not place any conservation easements over any of the easement lands that contain
Utility's existing or proposed water and/or wastewater facilities for the project covered by this Agreement.
32. Developer shall grant or otherwise secure the easements to Utility covering the potable water,
reclaimed water; and wastewater facilities that Utility agrees to own and maintain and shall be responsible for
providing the legal descriptions and maps for such easements to Utility, as shown on the plans prepared by North
Florida Engineering Services,Inc.,Job Number 23-030,as described in Exhibit"C",prior to commencement of this
project. This shall include (1) all casements necessary to accommodate water, wastewater, and reclaimed water
stubs to adjacent properties; (2) an easement ten (10) feet in width lying parallel and adjacent to all right of way
lines within the Developer's Property; (3) any easements within storm drainage retention pond areas or along lot
lines that may be necessary to accommodate any storm water harvesting systems that Utility may choose to install
within Developer's Property.
-9-
33. The landscaping (new or existing)for this project shall not include the planting of any trees within
seven and one half feet(7 ft. 6 in.)of any of the water,wastewater and/or reclaimed water mains. In the alternative,
Developer shall provide a root barrier,satisfactory to Utility,around the roots of all landscaping,trees,shrubs,etc.,
that are planted within the road right-of-ways that will potentially impact any of the utilities covered by this
Agreement.
It shall be Developer's responsibility to contractually require builders within the Property to establish a
workable procedure to assure Utility that the planting of"street trees"within the project provide at least seven and
one-half feet(7 ft. 6 in.) of separation from the center of the trees to Utility's mains and services. Otherwise, root
barriers are to be installed where the seven and one-half feet(7 ft. 6 in.)criteria is not met. A service charge,subject
to Utility's Board of Supervisors approval,may be assessed in order for Utility to inspect and approve the proposed
tree locations.
34. The road cross-section,utility placement,and sidewalk placement used within the subdivision streets
and right-of-ways shall be consistent with those layouts established by Utility in cooperation with other utilities and
the Clay County Engineering Department. Any variance from these standard layouts shall be communicated by
Developer to all utilities requiring facilities in the right-of-way and the Clay County Engineering Department and
shall be approved by all such utilities and agencies prior to commencement of construction.
35. It shall be Developer's responsibility where the engineering plans are reviewed and approved for an
entire project(Anabelle Island, Phases 3, 4 & 5), but the Developer constructs the project in phases to valve each
water stub in such a fashion that connection and extension of service to subsequent phases does not disrupt service
to prior phases,and such additional valving shall be approved by Utility prior to installation. Each such phase shall
be bacteriologically cleared and final certified by the design engineer as complete,including as-built drawings,final
close out documents,and final acceptance byUtility,prior to water,wastewater,and reclaimed water servi
ce s ce being
initialized.
36. Utility shall have access to all of the water and reclaimed water meters during normal business hours
for meter reading purposes.
37. Utility shall own and maintain all facilities upstream of the downstream side of the reclaimed water
meters and potable water meters, and the construction of the water and reclaimed services from the proposed
connection point to the meter locations shall be installed by Developer's State of Florida Licensed Underground
Utility Contractor and shall meet all of the requirements of Utility prior to Utility's acceptance for ownership and
maintenance. All facilities downstream of the downstream side of the reclaimed water meters and potable water
meters shall be owned and maintained by Developer. All of the water and reclaimed water installations shall be in
accordance with the plans prepared by North Florida Engineering Services,Inc.,Job Number 23-030,as described
in Exhibit"C," or as modified in a manner acceptable to Utility.
38. All wastewater mains 8-inches and larger in size terminating by a manhole,and all wastewater mains
8-inches and larger in size that are stubbed for future extensions,as shown on the plans prepared by North Florida
Engineering Services, Inc., Job Number 23-030, as described in Exhibit"C", shall be owned and maintained by
Utility.This includes all wastewater laterals from the 8-inch wastewater mains to Developer's Property line/right-of-
way line for each lot. All wastewater installations upstream of Developer's point of connection shall be owned and
maintained by Developer, and all installations downstream of this point of connection shall be owned and
maintained by Utility. The wastewater pumping station and all ancillary items related to the wastewater pump
station shall also be owned and maintained by Utility. All such facilities shall be installed by Developer's State of
Florida Licensed Underground Utility Contractor and shall meet all of the requirements of Utility prior to Utility's
acceptance for ownership and maintenance.
39. Developer shall,by perpetual covenants and restrictions,require each developed lot or parcel within
the Property to install an on-site irrigation system in full compliance with Utility's Reclaimed Water Policy (i.e.,
"Reuse Policy"), a true copy of which, in its current form, is attached hereto as Exhibit "B," and shall require that
those systems be operated and maintained in accordance with the rules and regulations of Utility, as well as all
governmental agencies having jurisdiction over such reclaimed water systems, and all lots or parcels lying within
the Property are hereby so restricted.
-10-
40. All irrigation contractors employed by Developer to install reclaimed water irrigation systems within
the Property shall be registered with Utility. The criteria for registration is included in Utility's Cross-Connection
Control Policy. Once registered,such irrigation contractor shall comply completely with Utility's Cross-Connection
Control Policy and Reuse Policy. Cross-connection control inspections will not be conducted for irrigation
contractors that are not registered with Utility.
41. All elements of the Florida Department of Environmental Protection rules and regulations regarding
the use of reclaimed water within the project will be adhered to at all times,and the Homeowners'Association will
continue to be responsible after the Developer is no longer in charge of the Anabelle Island Subdivision Phases 3,4
& 5. This specifically pertains to the Public Notice (posting of signs) provisions of the Florida Department of
Environmental Protection rules and regulations, as well as all specific requirements pertaining to the use of
reclaimed water in public areas and on roadways.
42. No wells shall be permitted within or upon the Property for any purpose.
43. Service for Anabelle Island Subdivision,Phase 3,4&5 is contingent upon the completion and final
acceptance by Utility of the infrastructure currently being installed with the Anabelle Island Subdivision,Phase 1 B
&2 and the Russell Retreat Subdivision.
44. The charges shown in paragraph 4(c), "Main Extension Charge—Water","Main Extension Charge—
Wastewater," and "Main Extension Charge—Reclaimed Water" in the amount of$298,468.53,of this Agreement,
are refundable to Utility who previously paid for upsizing the water; wastewater, and reclaimed water main
extensions along Sandridge Road that benefit this development.
45. This Agreement does not include any other phases or developments planned for this Property.Water,
wastewater, and/or reclaimed water service to any future/proposed amenity center, swimming pool, and/or
recreation areas are also not included in this Agreement. A separate agreement will be entered into when these
developments are initiated.
46. This Agreement will need to be executed by Developer, the charges paid (shown on page.2 of
Agreement),prior to October 1,2024,and the construction of the utilities for this total project shall be commenced
by October 1, 2024, or this Agreement will be subject to any Service Availability charge increases currently
approved,which may be applicable or which may be approved by Utility's Board of Supervisors for the next fiscal
year beginning October 1, 2024; and this Agreement is subject to any material cost increases which Utility may
experience after October 1, 2024.
[Signatures Begin Next Page]
•
-11-
IN WITNESS WHEREOF, Developer and Utility have executed or have caused this Agreement,with the
named Exhibits attached,to be duly executed in several counterparts,each of which counterpart shall be considered
an original executed copy of this Agreement.
WITNESSES: • DEVELOPER:
DFC ANABELLE, LLC,
a Florida limited liability company,
Witness: By: (Seal)
Print Name: 11-1064tiotsz,t' Scirviber'y f Kyle Hudson,Vice President
Witness:
Print Name: (ivy
STATE OF PI o r't oLQ
COUNTY OF S-`-. .\oh rl 5 "
The foregoing instrument was acknowledged before me by means of I] physical presence or ❑ online
notarization this 12. day of NOV€4'YI , 2024, by KYLE HUDSON, as VICE PRESIDENT of DFC
ANABELLE,LLC,a Florida limited liability company,on behalf of the company, ho is personally known to me)
or has produced , as identification. •
4
l Notary Public State of Florida I Print Name: JI t)colrld r2 r L ?m be.1ye f-
Alexander on tits gar NotaryPublic in and for the !!JJ
1 � '• My Commission HN 606807 i
Expires 10/27/2028 I County and State Aforesaid
My Commission Expires: 0 f'l 1/202$
-12-
WITNESSES: UTILITY:
CLAY COUNTY UTILIT - • ORITY
Witne By: \ -'
Print e��,SM�� 's ;,� �. , ' E.,M.B.A.
„,,4
•erflYton
•cu ytor
(Corporate Seal)
Witness: ,(5/mningiL
Pc1.-
Print Name: Summer P. Berndt
STATE OF FLORIDA
COUNTY OF CLAY
The foregoing instrument was acknowledged before me by means of x❑ physical presence or ❑ online
notarization this I3#h day of NiNef 1k c , 2024 by JEREMY D. JOHNSTON, as
EXECUTIVE DIRECTOR of the CLAY COUNTY UTILITY AUTHORITY,who is personally known to me.
04% SUMMER P BERNDT `
��ui z,-sNotary Public-State of Florida Print Name: Summer P. Berndt
*E Commission#HH 450194
:;•rilrPe;. Notary Public in and for the
' ��. My Commission Expires
January 26, 2028 County and State Aforesaid
My Commission Expires: 01 P10/0
ANABELLE ISLAND SUBDIVISION,
PHASES 3, 4 & 5
513 SINGLE FAMILY LOTS
Parcel No. 23-05-25-010097-000-00
Clay County
EXHIBIT "A" •
1of2
A PORTION OF BLOCKS 1,2, 16 AND 17, FLORIDA FARMERS LAND COMPANY'S SUBDIVISION, AS
RECORDED IN PLAT BOOK 1, PAGE 49, OF THE PUBLIC RECORDS OF CLAY COUNTY, FLORIDA,
TOGETHER WITH THAT PORTION OF ALL PLATTED ROADS LYING BETWEEN OR ADJACENT TO
THE AFORESAID BLOCKS (SAID PORTION OF PLATTED ROADS VACATED AND ABANDONED
ACCORDING TO OFFICIAL RECORDS BOOK 1633, PAGE 1483, OF SAID PUBLIC RECORDS), AND A
PORTION OF THE MOSES E.LEVY GRANT,SECTION 39,TOWNSHIP 5 SOUTH,RANGE 25 EAST,CLAY
COUNTY, FLORIDA, BEING MORE PARTICULARLY DESCRIBED AS FOLLOWS:
COMMENCE AT AN INTERSECTION WITH THE NORTHEASTERLY LINE OF LOT 9, SAID BLOCK 19,
FLORIDA FARMERS LAND COMPANY'S SUBDIVISION,AND THE NORTHWESTERLY RIGHT-OF-WAY
LINE OF COUNTY ROAD NO.C-739-B,ALSO KNOWN AS SANDRIDGE ROAD(AN 80F.00T RIGHT-OF-
WAY PER S.R.D. RIGHT-OF-WAY MAP SECTION NO. 71530-2603); THENCE NORTH 42°24'25" WEST,
ALONG SAID NORTHEASTERLY LINE OF LOT 9, AND ALONG THE NORTHWESTERLY
PROLONGATION THEREOF,A DISTANCE OF 3529.87 FEET TO THE POINT OF BEGINNING;THENCE
SOUTH 47°38'29"WEST, 1819.57 FEET TO THE NORTHEASTERLY LINE OF THOSE LANDS DESCRIBED
AND RECORDED IN OFFICIAL RECORDS BOOK 2310,PAGE 1689 OF THE PUBLIC RECORDS OF SAID
COUNTY,SAID LINE ESTABLISHED PER AGREEMENT RECORDED IN OFFICIAL RECORDS BOOK 312,
PAGE 334 OF THE PUBLIC RECORDS OF SAID COUNTY; THENCE NORTH 39°52'31" WEST, ALONG
LAST SAID LINE,4600.39 FEET TO A POINT HEREINAFTER REFERRED TO AS REFERENCE POINT A;
THENCE RETURN TO THE POINT OF BEGINNING; THENCE NORTH 47°38'29" EAST, 48.95 FEET TO
THE POINT OF CURVATURE OF A CURVE LEADING NORTHERLY;THENCE NORTHERLY, ALONG
AND AROUND THE ARC OF SAID CURVE,CONCAVE WESTERLY,HAVING A RADIUS OF 345.00 FEET,
AN ARC DISTANCE OF 474.54 FEET, SAID ARC BEING SUBTENDED BY A CHORD BEARING AND
DISTANCE OF NORTH 08°14'12" EAST,438.01 FEET TO THE POINT OF REVERSE CURVATURE.OF A
CURVE LEADING NORTHWESTERLY;THENCE NORTHWESTERLY,ALONG AND AROUND THE ARC
-OF SAID CURVE, CONCAVE NORTHEASTERLY; HAVING A RADIUS OF 555.00 FEET, AN ARC
DISTANCE OF 13.96 FEET,'SAID ARC BEING SUBTENDED BY A CHORD BEARING AND DISTANCE OF
NORTH 30°26'52" WEST, 13.95 FEET; THENCE SOUTH 63°43'27" WEST; 169.60 FEET;THENCE SOUTH
80°28'16"WEST, 129.28 FEET;THENCE SOUTH 65°52'43"WEST, 177.12 FEET;THENCE NORTH 83°06'37"
WEST,200.11 FEET; THENCE NORTH 61°12'10"WEST,299.88 FEET; THENCE NORTH 49°51'34"WEST,
211.28 FEET TO THE ARC OF A CURVE LEADING SOUTHWESTERLY; THENCE SOUTHWESTERLY,
ALONG AND AROUND THE ARC OF SAID CURVE,CONCAVE NORTHWESTERLY,HAVING A RADIUS
OF 545.00 FEET, AN ARC DISTANCE OF 4.18 FEET, SAID ARC BEING SUBTENDED BY A CHORD
BEARING AND DISTANCE OF SOUTH 61°02'45" WEST, 4.18 FEET TO THE POINT OF COMPOUND
CURVATURE OF A CURVE LEADING WESTERLY;THENCE WESTERLY,ALONG AND AROUND THE
ARC OF SAID CURVE, CONCAVE NORTHERLY, HAVING A RADIUS OF 40.00 FEET, AN ARC
DISTANCE OF 37.37 FEET,SAID ARC BEING SUBTENDED BY A CHORD BEARING AND DISTANCE OF
SOUTH 88°01'54"WEST,36.03 FEET TO THE POINT OF TANGENCY OF SAID CURVE;THENCE NORTH
65°12'08" WEST, 62.20 FEET TO THE POINT OF CURVATURE OF A CURVE LEADING NORTHERLY;
THENCE NORTHERLY, ALONG AND AROUND THE ARC OF SAID CURVE, CONCAVE EASTERLY,
HAVING A RADIUS OF 30.00 FEET,AN ARC DISTANCE OF 70.73 FEET,SAID ARC BEING SUBTENDED
BY A CHORD BEARING AND DISTANCE OF NORTH 02°20'24" EAST, 55.45 FEET TO THE POINT OF
REVERSE CURVATURE OF A CURVE LEADING NORTHEASTERLY; THENCE NORTHEASTERLY,
ALONG AND AROUND THE ARC OF SAID CURVE,CONCAVE NORTHWESTERLY,HAVING A RADIUS
OF 348.87 FEET, AN ARC DISTANCE OF 130.61 FEET, SAID ARC BEING SUBTENDED BY A CHORD
EXHIBIT "A"
2 of 2
BEARING AND DISTANCE OF NORTH 59°09'37" EAST, 129.85 FEET TO THE POINT OF REVERSE
CURVATURE OF A CURVE LEADING EASTERLY; THENCE EASTERLY,ALONG AND AROUND THE
ARC OF SAID CURVE, CONCAVE SOUTHERLY, HAVING A RADIUS OF 30.00 FEET, AN ARC
DISTANCE OF 41.14 FEET,SAID ARC BEING SUBTENDED BY A CHORD BEARING AND DISTANCE OF
NORTH 87°43'32" EAST, 38.00 FEET; THENCE NORTH 38°14'29" EAST, 74.40 FEET; THENCE NORTH
58°26'04"EAST,95.24 FEET;THENCE NORTH 36°01'07"WEST, 138.50 FEET;THENCE NORTH 16°36'35"
WEST, 64.78 FEET; THENCE NORTH 42°12'24" WEST, 122.40 FEET; THENCE NORTH 49°53'12" EAST,
60.04 FEET; THENCE NORTH 42°12'24" WEST, :130.00 FEET; THENCE NORTH 47°47'36" EAST, 80.00
FEET;THENCE NORTH 09°08'00"EAST,96.05 FEET;THENCE NORTH 42°12'24"WEST, 120.06 FEET TO
THE SOUTHEAS 1'ERLY LINE OF THOSE LANDS DESCRIBED AND RECORDED IN OFFICIAL RECORDS
BOOK 2171, PAGE 1730 OF THE PUBLIC RECORDS OF SAID COUNTY; THENCE SOUTHWESTERLY,
NORTHWESTERLY AND NORTHEASTERLY ALONG THE SOUTHEASTERLY AND SOUTHWESTERLY
LINE OF LAST SAID LANDS,RUN THE FOLLOWING SEVEN(7)COURSES AND DISTANCES;COURSE
NO 1: SOUTH 47°47'36" WEST, 503.43 FEET; COURSE NO. 2: NORTH 47°31'44" WEST, 1311.00 FEET;
COURSE NO.3:NORTH 45°40'12" WEST, 1849.79 FEET; COURSE NO.4:NORTH 61°27'47"EAST,217.50
FEET; COURSE NO. 5:;NORTH 50°29'18" WEST 9.92 FEET; COURSE NO. 6: NORTH 79°03'53" WEST, -
223.98 FEET;COURSE NO.7:NORTH 36°29'23"WEST,905 FEET,MORE OR LESS,TO THE CENTERLINE
OF BRADLEY CREEK; THENCE SOUTHWESTERLY, ALONG THE MEANDERINGS OF SAID
CENTERLINE, 1395 FEET, MORE OR LESS, TO AN INTERSECTION WITH THE AFORESAID
NORTHEASTERLY LINE OF THOSE LANDS DESCRIBED AND RECORDED IN OFFICIAL RECORDS
BOOK 2310,PAGE 1689,SAID LINE BEARING NORTH 39°54'03"WEST,FROM AFORESAID REFERENCE
POINT A; THENCE SOUTH 39°54"03 EAST, ALONG LAST SAID LINE, 1695 FEET,MORE OR LESS TO
SAID REFERENCE POINT A, AND TO CLOSE.
CONTAINING: 200 ACRES, MORE OR LESS.
EXHIBIT "B"
REUSE POLICY
PAGE 1 OF 2
Effective Date- Thirty (30) days after Board's approval of the policy, for all developments that have not met the
filing requirements of the County's Zoning Department,which requires each new development to be reviewed by the
Development Review Committee(DRC),or for those developments not requiring DRC approval,which have been
quoted charges to connect to the Clay County Utility Authority's(CCUA)water and/or wastewater systems within
twelve months prior to the effective date of the reuse policy. A filing for a DRC meeting,which is incomplete as of
the effective date of this policy, shall not be considered as filed timely for the prior policy to apply.
If the developer has not commenced substantial construction on his project,which was filed with DRC prior
to the effective date of this policy,within fifteen months after the effective date of the policy,then said development
shall come under the provisions of this policy.
Applicability-This policy will be applicable to all developments that file for a Development Review Committee
review after the effective date of this policy. This shall include:
A. Developments occurring under Development of Regional Impact(DRI)agreements which may not
be technically required to install residential reuse, but who choose to do so in settlement of minor and/or major
modifications to the structure and composition of developments within the DRI. These shall be regulated and
charged under this proposed policy and effective date criteria the same as all other developments.
B. Exceptions to the applicability of this policy and/or effective date are as follows:
1. Developments occurring under DRI agreements or Florida Quality Development (FQD)
agreements,which are notre
quired by said agreement to install residential reuse and who do
not volunteer to provide residential reuse piping systems.
2. Developments which,as of the date of enactment of this policy,own and maintain their own
reuse pumping plant and purchase bulk service from the CCUA.
3. Developments which have prepaid connection fees prior to January 1, 1998, at a prior
approved rate and still have an inventory of prepaid connections,shall be exempt until such
prepaid connections are used up.
4. Developments and/or communities that own, operate and maintain their own reuse
infrastructure as of January 1, 1998.
Developments Required to Install Wastewater Effluent Reuse Piping Systems and Take Reuse Water When it
is Available-All developments occurring after the effective date of this policy will be reviewed by the CCUA staff
for feasibility of the installation of a reuse piping system for irrigation purposes. These shall include commercial,
public facilities, industrial, as well as residential developments.
Summary of Criteria to be Utilized by Staff to Evaluate and Determine if Reuse Piping Systems will be
Required -
(1) Financial feasibility of extending a trunk main to an area at that time,or some planned future date,to
provide reuse water to the proposed reuse system. This item shall consider the size of the development,distance to
nearest master planned reuse trunk main or planned reuse plant, remaining developable property in the area,
complexity of existing development of area which trunk mains must pass through,natural geographical barriers(or
obstacles), environmental damage, etc.
EXHIBIT 'B"
REUSE POLICY
PAGE 2 OF 2
(2) Remaining developable land in the area(new area with very little existing development and much
growth potential will be considered more feasible than an already built-out area).
(3) Availability of adequate reuse water within a reasonable time to service the reuse system.
(4) CCUA's budgetary restraints.
(5) Length of time before a reuse plant or pump station is expected to be built in the area.
Surcharge for Developments not required to Install Reuse Piping Systems -Due to the built-out condition of
certain geographical areas and the other evaluation of feasibility considerations noted above, it will not be practical
to require all areas to install reuse piping systems. All developments that are not required to install the reuse system
shall pay a surcharge per ERC as its share of the burden of the reuse system installations at a rate set forth in the
"proposed charges for service availability".
Requirement for Installation of an Automatic Sprinkler System-All developments where reuse piping systems
are required shall install or require the installation of an automatic sprinkler irrigation system acceptable to CCUA
for the development of each separate parcel(lot)within the development. Such on-site systems shall utilize color-
coded pipe for reuse water, functional rain sensors, and automatic controllers and timers.
Approval of Sprinkler Irrigation Contractors -It is deemed by CCUA to be important that sprinkler irrigation
contractors,who connect to the reuse system, be thoroughly educated with regard to reuse systems in an effort to
eliminate any potential cross connection with the potable water system. In this regard, all irrigation contractors
installing irrigation systems in conjunction with this reuse program must prequalify with CCUA by providing their
credentials and passing a qualification interview with CCUA's staff for the purpose of demonstrating knowledge of
the key issues regarding use of reuse water. A current certificate of insurance, acceptable to CCUA, naming the
CCUA as an additional insured shall be on file at all times with the CCUA.
Requirement for Payment of Reuse Base Facility Charge-All customer classes that have reuse piping systems
available shall be required to pay the Base Facility Charge for reuse water whether they use the reuse water or not.
Requirement for Reuse Meter- All customer classes that have reuse piping systems available shall pay for the
installation of a reuse meter at the same time the domestic meter is requested.
Wells - All developments where reuse piping systems are installed shall prohibit the installation of wells for
irrigation purposes.
Responsibility for Design and Installation of Reuse Piping Systems-Where reuse piping systems are required,
the design engineer for the project shall design,at Developer's expense,the reuse piping system for the development
and any reasonable trunk mains necessary to connect to the nearest source of reuse water,and developer shall install
said system at its expense. The CCUA's existing policy regarding cost sharing for oversized mains, refundable
agreements, plan review and approval, and adherence to CCUA's specifications and details, shall apply to these
reuse piping systems, the same as the potable water distribution systems and wastewater collection systems.
EXHIBIT "C"
DESCRIPTION OF APPROVED CONSTRUCTION PLANS
(Less and except plans to be replaced due to minor changes required)
Project: Anabelle Island, Phases 3,4 & 5
Engineer: Michael Light, P.E.
North Florida Engineering Service, Inc.
3530 Agricultural Center Drive, Ste. 209
St. Augustine, Florida 32092
Job Number: 23-030
Date: May 6, 2024
Engineer Description Approved Plan
Drawing Date
Number
1 Cover Sheet • 09/09/2024
2-3 Pre-Development Drainage Plan 09/09/2024
4 Development Plan 09/09/2024
5-15 Horizontal Control Plan 09/09/2024
16-19 Overall Post Drainage Plan A,B, C&D 09/09/2024
21-31 Lot Grading Plan 09/09/2024
32 Master Drainage Plan 09/09/2024
33-47 Paving and Drainage Plan&Details 09/09/2024
48-50 Erosion Control Plan 09/09/2024
51 Master Water Plan 09/09/2024
52-62 Water Plan 09/09/2024
63 Master Sewer Plan 09/09/2024
64-74 Sewer Plan 09/09/2024
75 Sewer Structure Tables 09/09/2024
76 Sewer Pipe Details 09/09/2024
S-SPA Standard Water and Sewer System Specifications 09/09/2024
WAT 01 Standard SCH80 PVC and Polyethylene Water Service Details 09/09/2024
WAT 02 Standard Water Casing, Crossing Type, and Pipe Restraint Details 09/09/2024
WAT 02 Standard Water Casing,Crossing Type, and Pipe Restraint Details 09/09/2024
LW-STD Standard Locator Wiring Installations 09/09/2024
S-SEW Standard Sewer System Details 09/09/2024
S-RE I Reclaim Water Distribution System Details and Specifications 09/09/2024
S-RE2 Reclaim Water Distribution System Details and Specifications 2 09/09/2024
S-UTC2 Water, Sewer, and Reclaimed Water Utility Placement in R/W 27' Pavement Width 09/09/2024
S-UTC 1 Water, Sewer, and Reclaimed Water Utility Placement in R/W 27' Pavement Width 09/09/2024
L.S.3 Permanent Submersible Pump Station with Concrete Wet Well 09/09/2024
L.S. 3 480 Volt for 40 HP &Larger Submersible Pump Station Electrical Schematic and Details 09/09/2024
L.S.4 Permanent Submersible Pump Station with Concrete Wet Well 09/09/2024
L.S.4 480 Volt for less than 40 HP Submersible Pump Station Electrical Schematic and Details 09/09/2024
L.S.5 Permanent Submersible Pump Station with Concrete Wet Well 09/09/2024
X:E gmccring\COMMERCIAL I'I.AN Rf VIE\'Inns In Rvinsv\AnabnIN Island Subdivision,phase 3+\C Dn+doper AgrcmcnMGR.Anubclln Island.I'basc 3..J&i-i13 I.ou JMS.don -
EXHIBIT "C"
L.S.5 480 Volt for 40 HP &Larger Submersible Pump Station Electrical Schematic and Details 09/09/2024
90 F.D.O.T Details 09/09/2024
91-99 Profiles 09/09/2024
100-102 Wetlands Flag Map 09/09/2024
103 Master Reclaim Water Plan 09/09/2024
104-114 Water Reclaim Plan 09/09/2024
115-119 Off-Site Utility Plan 09/09/2024
120-121 Sleeving Plan 09/09/2024
Standard Water and Sewer System'Outline Technical Specifications for Developer -09/09/2024
122 Initiated Projects
•
•
X:\Engineuine\COMMERCIAL PLAN RLVII.WII'lans In Rv.vinnv\Anahclle Inland Subdivision,Phnnn i+\C Developer Agruemcnt AGR.Anabclic ininnd,l'hasc 3.4&5-51:Lou JMS.dot.
CI N
CC
W 10, 4),
W-'02S
" Nj‘IPth
r1
11
S,(vE �o��
REEKp�sz,P., ` .t�
NIPPY.r • 9$,
cx.
.• 440
•
((4)6 44
...-- 4:i.;•,'Noliik .....!4.4:,)
04/ fl
.
I
\\\\\°---) 16 le
, ,;,. ..„ ____,
c, ,. .
a"
J*y cR.
N Anabelle Island Subdivision �� �L�1 � PS
Q Phases 3,4&5 �•' 'T' C� T O/V ROEI
oil TER_
a `��/8f111 -
t% h
..
•( /
Disclaimer:The information displayed on this drawing or sheet is for a general visual representation purposes only.The drawing is based upon numerous sources of public '1.
information which include but are not limited to Clay County Property Appraisers, FDOT, SJRWMD, and the Clay County Utility Authority's (CCUA)own records.All
information included in the drawing is general in nature and not site specific.Any cimensions or other information is approximate and needs to be field verified.CCUA does k
not offer any guarantees,certifications,or warranties,either expressed or implied,in regards to the accuracy of the information represented on these drawings.The drawing
is not a survey and should not be construed in any manner as such.By receiving this drawing,the recipient is agreeing to hold CCUA harmless for any errors or omissions
which may be present in this&awing.All interested parties are strongly encouraged to engage a Professional Surveyor and Mapper licensed in the State of Florida to field
verify all site,property,infrastructure,and utility information prior to any decisions or actions.
I I __ T Z- CCUA
1, CO(�NT Title:
C.........
__ Clay County Utility Authority CCUA Web Map
i- 3176 Old Jennings Road Info:
� Middlebur Florida 32068 3907 Water Features
g+ Prepared by CCUAGIS Portal'a Phone 904 272 5999MI Gravity Sewer Features
t11/13/2024,4:36:05 PM
�� Conservation.Commitment.Community l= Forced Sewer Features
�TYAUTN� 1 inch = 1,000 feet — Reclaimed Features