HomeMy WebLinkAbout09.d EDB Carollo Pilot Study Grant Funding Support EXECUTIVE SUMMARY
AGENDA ITEM:
Proposed Supplemental Agreement No. 1 with Carollo Engineers, Inc (Carollo) to the Civil and
Environmental Engineering Professional Services Agreement RFQ 23-24-A01, to provide Pilot
Operation and Testing Support Services for the Potable Reuse Demonstration Project.
Project Number: 3019-001
Finance Number: 20022WL
Date: November 15, 2024
BACKGROUND:
Staff requests the Board of Supervisors approve Supplemental Agreement No. 1 with Carollo to
the Civil and Environmental Engineering Professional Services Agreement RFQ 23-24-A01, to
provide Pilot Operation and Testing Support Services for the Potable Reuse Demonstration
Project.
The State of Florida has been directing utilities to seek infrastructure cost share through State Grant
Programs. Clay County Utility Authority(CCUA)and our Engineer of Record for Project Quench,
Carollo, submitted a Request for Inclusion (RFI) to the Florida Department of Environmental
Protection(FDEP) for the Clean Water State Revolving Fund(CW SRF)Emerging Contaminants
program in July 2024 for Project Quench. While this program operates under the SRF umbrella, if
approved. The FDEP administers these applications as a grant with 100% principal loan
forgiveness.
On August 22, 2024, CCUA was informed that their project was approved at FDEP's quarterly
priority meeting for a planning loan application of up to $1,000,000 (all in the form of, principal
forgiveness, so in practical terms, a grant). The grant would support generation of data relevant to
potential future full-scale design, including collecting water quality data for a 12-month duration.
To obtain funding,a planning loan application must be completed and submitted prior to December
12, 2024. Disbursement requests will be made for the period between being approved on the
priority list (August 22, 2024) to the end of operating the pilot for 12 months, which is expected
to be through October 2025.
BUDGET:
Staff budgeted $300,000.00 for miscellaneous expenses in the 2024/2025 operating budget. The
fee for Carollo to complete this funding request is $15,497.00 as detailed in Exhibits A and B of
their proposal. There is sufficient remaining project budget to cover this expenditure.
CCNA:
CCNA, F.S. s. 287.055 does apply to the use of a consultant under a continuing contract. The
estimated construction cost for each project is expected not to exceed$7.5 million. Staff negotiated
this Supplemental Agreement in compliance with F.S. s. 287.055. Based on established contract
rates, staff and the consultant negotiated the scope and fee for the professional services at
compensation that CCUA determines is fair, competitive, and reasonable.
RECOMMENDATION:
Staff respectfully recommends that the Board of Supervisors approve the attached Supplemental
Agreement No. 1 with Carollo for Pilot Operation and Testing Support Services for the Potable
Reuse Demonstration Project not-to-exceed amount of$15,497.00.
ATTACHMENTS:
Supplemental Agreement No. 1
Supplemental Agreement No. 1 Scope and Fee Proposal
//JP (Author)
//AA(Review)
//PS (Final)
Supplemental Agreement No. 1 to Professional Engineering Services Agreement RFQ 23-24-A01,
with Carollo Engineers,Inc. to provide Pilot Operation and Testing Support Services for the
Potable Reuse Demonstration Project.
CCUA Project No. 3019-001
Engineer: Jason Assouline Owner: Clay County
Carollo Engineers, Inc Utility
200 East Robinson Street, Suite 1400 Authority
Orlando, FL, 32801
Date: November 19, 2024
Item: Description of Services:
Provide professional engineering services as requested
and identified in the attached scope of services and fee
proposal.
Task 1 Project Management/Meetings $5,027.00
Task 2 FDEP SRF Application $3,748.00
Task 3 Disbursement Request Support $6,722.00
Amended Total Lump Sum Price Not to Exceed Without Prior $15,497.00
Authorization
The Contract time shall commence on November 19, 2024. This document, along with the Scope and
Fee Proposal, shall become an amendment to the Professional Engineering Services Agreement, and all
provisions will apply hereto.
Accepted by: Date:
Engineer:
Jason Assouline
Carollo Engineers, Inc
Accepted by: Date:
Owner:
Jeremy D. Johnston, P.E., MBA,
Executive Director
Clay County Utility Authority
Exhibit A
CCUA Project Quench
FDEP SRF Grant Funding Support
Basis of Fee Estimate
Clay County Utilities Authority(CCUA) submitted a Request for Inclusion (RFI) to the Florida
Department of Environmental Protection (FDEP)for the Clean Water State Revolving Fund (CW
SRF) Emerging Contaminants program in July 2024 for Project Quench. While this program
operates under the SRF umbrella, if approved, it is administered as a grant with 100% principal
loan forgiveness.
Building upon the success of other projects similar to Project Quench in successfully obtaining
funding from this grant opportunity, Carollo Engineers, Inc. (Carollo) submitted a Request for
Inclusion application to the FDEP on behalf of CCUA. On August 22, 2024, CCUA was informed
that their project was approved at FDEP's quarterly priority meeting for a planning loan
application of up to$1,000,000 (in which $1,000,000 is principal forgiveness).The grant would
support generation of data relevant to full-scale design, including collecting water quality data
for a 12-month duration.To obtain funding, a planning loan application must be completed and
submitted prior to December 12, 2024. Disbursement requests will be made for the period
between being approved on the priority list (August 22, 2024)to the end of operating the pilot
for 12 months,which is expected to be through October 2025.
This scope of work and associated fee provides details of professional services to be provided by
Carollo Engineers, Inc. (Carollo)to support CCUA in submitting the program application to FDEP,
coordinating with FDEP on loan/grant requirements, and managing funding requirements over
the course of the pilot system operation.
I. SERVICES TO BE PERFORMED
Task 1 - Meetings
Funding Application Kickoff Meeting with FDEP& CCUA
Carollo will coordinate directly with FDEP and CCUA to schedule a preliminary funding kickoff
meeting.This meeting will be held virtually via Microsoft Teams.The purpose of this meeting will
be to review the project scope, schedule, and discuss lines of communication. Carollo will
develop and distribute the meeting agenda prior to the meeting. A summary of the kickoff
meeting will be sent after the meeting to the participants.
Progress Meetings
1
Carollo will schedule and attend up to 4 progress meetings throughout the course of the project.
These meetings may include FDEP, if determined to be appropriate by CCUA and the project
team. Carollo will summarize these meetings in meeting minutes and distribute them to the
participants.These project meetings will be held virtually via Microsoft Teams.
Task 2— FDEP CW SRF EC Application
Carollo staff will provide services to coordinate with CCUA to complete FDEP's CW SRF loan
application.This task will include the formulation of a data request to be sent to CCUA containing
a list of documentation required to complete the application. Once information is received,
Carollo will use the provided documentation to complete the remaining portions of the loan
application to fund the regulatorily required duration of 12-months of piloting Project Quench.
Carollo will provide the completed draft loan application to CCUA for review and incorporate
comments before routing the final package for CCUA signatures prior to FDEP submittal. CCUA
will submit the application to FDEP and will be responsible for paying any submission fees.
Task 3— Disbursement Request Support
Carollo staff will compile invoicing information from the previous month's services to complete
FDEP's disbursement request form and associated summary disbursement request spreadsheet.
Requests must be reviewed and signed by CCUA prior to submittal to FDEP. Carollo will submit
the disbursement requests to FDEP. Disbursement requests are expected to end by October
2025.
II. PROJECT SCHEDULE
Task Duration (Months) Estimated Completion
Task 1—Meetings 12 November, 2025
Task 2—FDEP SRF Application 1.5 December 12, 2024
Task 3—Disbursement 12 November 23, 2025
Request Support
III. PROJECT ASSUMPTIONS
• CCUA will provide a response to all requests in a timely manner that allow SRF deadlines
to be met.
• CCUA will pay all costs associated with FDEP fees.
• Owner-Provided Information and Services.The Owner shall furnish the Consultant
available studies, reports and other data pertinent to the Consultant's services; obtain or
authorize the Consultant to obtain or provide additional reports and data as required;
furnish to the Consultant services of others required for the performance of the
Consultant's services hereunder, and the Consultant shall be entitled to use and
reasonably rely upon all such information and services provided by the Owner or others
in performing the Consultant's services under this Agreement.
2
• Estimates and Projections. In providing opinions of cost,financial analyses, economic
feasibility projections, schedules, and quantity and/or quality estimates for potential
projects,the Consultant has no control over cost or price of labor and material; unknown
or latent conditions of existing equipment or structures that may affect operation and
maintenance costs; competitive bidding procedures and market conditions;time or
quality of performance of third parties; quality,type, management, or direction of
operating personnel; the incoming water quality and/or quantity;the way the Owner's
plant(s) and/or associated processes are operated and/or maintained; and other
economic and operational factors that may materially affect the ultimate project
elements, including, but not limited to, cost or schedule. Therefore,the Consultant
makes no warranty that the Owner's actual project costs,financial aspects, economic
feasibility,schedules, and/or quantities or quality realized will not vary from the
Consultant's opinions, analyses, projections, or estimates.
• Third Parties.The services to be performed by the Consultant are intended solely for the
benefit of the Owner. No person or entity not a signatory to the Agreement shall be
entitled to rely on the Consultant's performance of its services hereunder, and no right
to assert a claim against the Consultant by assignment of indemnity rights or otherwise
shall accrue to a third party as a result of the Agreement or the performance of the
Consultant's services hereunder.
IV. PAYMENT FOR SERVICES
Compensation for the scope of services described above shall be delivered on a lump sum basis
for a fixed fee of$15,497 detailed in Exhibit B.The total compensation for this service agreement
are based on billing rates provided in the continuing services agreement between Carollo and
CCUA under Civil and Environmental Engineering Professional Services RFQ 18/19 No. 3. Invoices
for Carollo's services will be submitted to CCUA on a monthly basis; submittals will include
progress reports associated with the billing period.
3
Exhibit B
Fee Schedule
CLAY COUNTY UTILITY AUTHORITY
PROJECT QUENCH-FDEP SRF GRANT FUNDING SUPPORT «cro%%o
FEE SCHEDULE
Labor Hours and Costs Other Direct Project Costs Total
Task Hours Carollo Travel Other Total
No. Labor Related ODCs ODCs
Ta Tcs �a a = ODCs
o o 0 0 0
N
O_ t 'a :a; t , -a N
5 O R N O O O O O O O
Staff Classification vn a` _1 a` a` o. o.` a` a`
$259.87 $231.52 $182.69 $146.47 $108.67 Hours Cost
1 Meetings
1 4 8 12 2 27 $4,622 $0 $405 $405 $5,027
Task 1 Totals= 1 4 8 12 2 27 $4,622 $0 $405 $405 $5,027
2 FDEP SRF Application
1 1 2 16 2 22 $3,418 $0 $330 $330 $3,748
Task 2 Totals= 1 1 2 16 2 22 $3,418 $0 $330 $330 $3,748
3 Disbursement Request Support
2 3 6 24 3 38 $6,152 $0 $570 $570 $6,722
Task 3 Totals= 2 3 6 24 3 38 $6,152 $0 $570 $570 $6,722
Project Totals 4 8 16 52 7 87 $14,192 $0 $1,305 $1,305 $15,497