HomeMy WebLinkAbout15.a FYI CO No. 3 Sawcross GP Reclaimed Water Pump Station GAY CO(J^,T), Clay County Utility Authority
Working together to protect
3176 Old Jennings Road public health,conserve our
Middleburg,Florida 32068-3907 natural resources,and
Telephone(904)213-5999 create long-term value for
ON' our ratepayers.
Facsimile (904)213-2498
Change Order No.: 3 Date: 10/30/2024
Project: Governor's Park Wastewater Lift Station Project and Reclaimed Water Pump Station Project
CCUA Bid No.: 2022/2023-A06
CCUA Project No.: 1127-004
Vendor: Sawcross Incorporated Owner: Clay County Utility Authority
10970 New Berlin Road 3176 Old Jennings Road
Jacksonville,Florida 32226-2270 Middleburg,Florida 32068
904-751-7500 (904)272-5999
Engineer of Record: Ardurra
100 Center Creek Road,Suite 108
St.Augustine,Florida 32084
904-562-2185
ORIGINAL CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 8/25/2023
DAYS ADD 420/353
SUB.COMP. 474 12/14/2024 4/30/2025
FINAL COMP. 534 2/12/2025� 12/31/2025
INCREASE OR
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) QTY. UNIT PRICE CONTRACT PRICE
Contract Increase
Contract Decrease
TOTAL INCREASE $0.00
TOTAL DECREASE $0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
ORIGINAL CONTRACT PRICE $7,683,000.00
Net Increases by Change Orders(prior to this change order) $0.00
Net Decreases by Change Orders(prior to this change order) ($792,106.37)
Total Net Change by Chance Orders(prior to this change order) ($792,106.37
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $6,890,893.63
NET CHANGE RESULTING FROM THIS CHANGE ORDER $0.00
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $6,890,893.63
This document shall become an amendment to the contract and all provisions of the contract will apply hereto.
Accepted by: Date:
Engineer of Record t ,
Accepted by: /l/f�/
Date: 20,,�"L
endor
Accepted by: Date: _
Owner
A
I,
SAWCROSS INCORPORATED
10970 NEW BERLIN ROAD JACKSONVILLE, FL 32226-2270
904-751-7500(VOICE)904-751-0600(FAX)WWW.SAWCROSS.COM (INTERNET)
October 31, 2024
Paul Steinbrecher, P.E.
Clay County Utility Authority (CCUA)
3176 Old Jennings Road
Middleburg, FL 32068
Subject: CCUA Governors Park RWPS — Proposed Change Order #003 (Time
Extension)
Dear Paul,
This letter is to request a laddered extension to the Substantial Completion date
from 12/14/2024 to 12/31/2025. The extension is necessary since the developers
reclaim water distribution system will not be in service by the original Substantial
Completion date (12/14/2024) and as such, the reclaim water pump station cannot
be adequately tested for final acceptance.
All equipment is installed at this time and the plant will be functional for its intended
purpose by December 31, 2024. This request is to ensure the ability to test the high
service pumps under realistic conditions, which will not occur until the developer
completes a phase or partial phase of development which is expected in 2025.
Accordingly, Sawcross requests an initial substantial completion to demonstrate the
plant is available for its intended purpose by 12/31/2024. A second partial
substantial completion date is requested on 4/30/2025 for building components,
sitework and punchlist items.
Please see this letter as a request for an additional four hundred nineteen (419)
day(s). Revised Substantial Completion date is Wednesday 4/30/2025 and Final
Completion date is Wednesday 12/31/2025. Clay County Utility Authority (CCUA)
can withhold 2.50% of retainage from this contract until final acceptance is complete.
Warranties will not be impacted by this extension and Clay County Utility Authority
(CCUA) accepts long term storage responsibilities as indicated by manufacturers.
This will allow all associated and responsible parties to return on the first phase of a
remote development and final test the high service pumps properly by mutual
agreement.
Total Costs $0.00
Total Additional Contract Time (Days) Four Hundred Nineteen (419) Day(s)
Sincerely,
CONTRACTORS&ENGINEERS
CGC 36203 CMC 56728 CUC 56787 UC 300564
Ci te'z /7,crzi-iz
Drew Hickinbotham
Project Manager
904-751-7500 Ext. 113
drewh@sawcross.com
SECTION 00660
Change Order Request Form
Project: Governor's Park Wastewater Lift Station Project and Governor's Park Reclaimed Water Pump Station Project
Bid No.: 2022/2023-A06 Project No.: 1127-004
Change Order No.: 003
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion: 474 Ready for Final Payment: 534
Increased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Decreased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time prior to this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Increase in time on this C.O.: Substantial Completion: 419 Ready for Final Payment: 353
Decrease in time on this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time with all approved
C.O.s: Substantial Completion: 893 Ready for Final Payment: 887
Change in Contract Price
Original Contract Price: $7,683,000.00
Increased from previously approved C.O.: $0.00
Decreased from previously approved C.O.: $(792,106.37)
Increase in Contract price this C.O.: $0.00
Decrease in Contract price this C.O.: $0.00
Contract price with all approved C.O.s: $6,890,893.63
The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2)
all Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all
previous progress payments received from Clay County Utility Authority (CCUA) , on account of Work done under the Contract
referred to above have been applied to discharge in full all obligations of Contractor incurred in connection with Work covered by
prior Applications for Payment; (4) title to all materials and deliverables incorporated in said Work or otherwise listed in or covered
by this Application for Payment will pass to the CCUA at the time of payment clear of all liens, claims, security interests and
encumbrances; (5) payment is due and has not been previously requested for these amounts; (6) no markup has been applied to
reimbursable expenses.
00660-1
GOVERNOR'S PARK WASTEWATER LIFT STATION PROJECT CHANGE ORDER REQUEST FORM
AND GOVERNOR'S PARK RECLAIMED WATER PUMP STATION PROJECT OCTOBER 2022
SECTION 00660
Change Order Request Form
Drew Hickinbotham (Sawcross, Inca Project Manager)
Contractor Name and Title
Cost Break Down Form: (instructions:use a separate form for each individual work item)
Description Unit Quantity Unit Cost Extended Cost
Labor
Materials
Equipment — $
Maintenance of Traffic $
-- ----- — ----- ---
Bonding $
General Conditions $
Overhead and Profit $
- ----- ------------- ------
$
Total firm fixed cost not to exceed amount: $
Note:attached supporting documentation
RFI No. initiating the change: N/A
Description: No costs associated with change order. Time extension requested due reclaim water not being available
from the developers until late 2025. Reclaim water is required for startup and testing and complete checkout of operation.
Sawcross and required vendors/manufacturers to be onsite for startup and testing services once water is available.
Justification for the request:Reclaim water is required for startup and testing services. The developer will not be complete
will the distrubution system until late 2025. Sawcross and required parties will complete startup and testing services
once reclaim water is available.
State the firm fixed cost not to exce otft in w ds:
Contractor Signature: Date: J O) 31'Z02 G'
00660-2
GOVERNOR'S PARK WASTEWATER LIFT STATION PROJECT CHANGE ORDER REQUEST FORM
AND GOVERNOR'S PARK RECLAIMED WATER PUMP STATION PROJECT OCTOBER 2022
SECTION 00660
Change Order Request Form
Printed Name: Title:
00660-3
GOVERNOR'S PARK WASTEWATER LIFT STATION PROJECT CHANGE ORDER REQUEST FORM
AND GOVERNOR'S PARK RECLAIMED WATER PUMP STATION PROJECT OCTOBER 2022