Change Order No 2.: 100 day time extension Date: 2/26/2025
Project: Lift Station#2
CCUA Bid No.: 22/23-A 16
CCUA Project No.: 2021.I47(2I0I 6RR)
Vendor: Petticoat-Schmitt Civil Contractors,Inc. Owner: Clay County Utility Authority
6380 Phillips Hwy 3176 Old Jennings Rd.
Jacksonville,Fl Middleburg,Florida 32068
904-751-0888 904-272-5999
Engineer of Record: Four Waters Engineering, Inc.
324 6th Avenue N.
Jacksonville Beach,FL 32250
904-993-3724
ORIGINAL CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 1/16/2024 9/12/2024
DAYS ADD 100
SUB COMP 365 1/15/2025 4/25/2025
FINAL COMP 395 2/14/2025 5/26/2025
INCREASE OR
DECREASE IN
[TEM DESCRIPTION OF CHANGE(S) OTY UNIT PRICE CONTRACT PRICE
Contract Increase
$000
Contract Decrease
TOTAL INCREASE $0 00
TOTAL DECREASE $0 00
NET CHANGE RESULTING FROM THIS CHANGE ORDER _ $0 00
ORIGINAL CONTRACT PRICE S4,496,301 00
Net Increases by Change Orders(prior to this change order) $0 00
Net Decreases by Change Orders(prior to this change order) (S52.423.21 I
I nial Nett hangs by Change Orders(pour to this ihan4e oiled ($52,423.211,
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER S4,443.877 79
NET CHANGE RESULTING FROM THIS CHANGE ORDER S0 00
CONTRACT PRICE INCLUDING ftItS CHANGI ORDER S4,443.877 79
Ibis document shall become an nendrnent tot contract and all provisions of the contract will apply hereto
/ Date-
Ai �w
Acce ted by' A�� ,�
Engines W ecrtt_Four or Engineering,In I l
Accepted by �I:�j�/�� Dale _2/ 2.1j9/2S
Vendor ; C I . l�
Accepted by: sew Date: ��2J _�2- 5-
ch..it ire
Project: Lift Station #2  L�py Co
rio
v'�Ty
CCUA Bid No.: 22/23-A16 CCUA Project No.: 2021.147 (21016RR)
I
Summary of Change Orders /Ih}' u r kph\
Date Description Contract Net Increase Net Decrease Revised Contract
Original Contract Price: $4,496,301.00
Change Order No. 1: Deductive CO
9/12/2024 for elimination of proposed gravity ($52,423.21)
piping, manhole modification.
2/26/2025 100 Day time extension
Summary of Totals: $4,496,301.00 $0.00 ($52,423.21) $4,443,877.79