HomeMy WebLinkAbout14.b FYI FI WRF Neutralizer Building - Petticoat-Schmitt CO #2 Change Order Request Form
Project: CCUA Fleming Island WRF Neutralizer Building PO Number 2203-136
Time Extension Change Order No: 4
Change in Contract Times (Days) (Days)
Original Contract time: Substantial Completion: 365 Ready for Final Payment: 395
Increase from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Decreased from previous C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time prior to this C.O.: Substantial Completion: 365 Ready for Final Payment: 395
Increase in time on this C.O.: Substantial Completion: 157 Ready for Final Payment: 157
Decrease in time on this C.O.: Substantial Completion: 0 Ready for Final Payment: 0
Contract time with all apprved C.O.s: Substantial Completion: 522 Ready for Final Payment: 552
Change in Contract Price
Original Contract Price: $ 3,331,182.00
Increased from previously approved C.O.: $ 46,841.64
Decreased from previously approved C.O.: $ -
Increase in Contract price this C.O.:
Decresase in Contract price this C.O.: $ -
Contract price with all approved C.O.s: $ 3,378,023.64
The undersigned Contractor certifies to the best of my knowledge and belief: (1) all items and amounts shown above are correct; (2) all
Work performed and Reimbursable Expenses fully comply with the terms and conditions of the Contract Documents; (3) all previous
progress payments received from CCUA , on account of Work done under the Contract referred to above have been applied to discharge
in full all obligations of Contractor incurred in connection with Work covered by prior Applications for Payment; (4) title to all materials and
deliverables incorporated in said Work or otherwise listed in or covered by this Application for Payment will pass to CCUA at the time of
payment clear of all liens, claims, security interests and encumbrances; (5) payment is due and has not been previously requested for
these amounts; (6) no markup has been applied to reimbursable expenses.
Adithyan Parthasarathy-Assistant Project Manager
Petticoat Schmitt Civil Contractors, Inc
Cost Break Down Form: (instructions: use separate form for each individual work item)
Description Unit Quantity Unit Cost Extended Cost
Subcontractor SUM 1 $ -
Labor SUM 1 $ - $ -
Materials SUM 1 $ - $ -
Equipment SUM 1 $ $ -
Maintenance of Traffic SUM 1 $ - $ -
Bonding SUM 1 $ ------ ---- - $ -
General Conditions SUM 1 $ - $ -
Overhead and Profit SUM 1 $ - $ -
-----------------------= 4.--- -------------------
Total firm fixed cost not to exceed amount: - $ -
Note:attach supporting documentation
RFI No. Initiating the change:
Description: Change order request for time extension due to permit delays and WAS relocation and communications
Justification for the request: Refer PSCC Cover Letter
State the firm fixed cost not to exceed amount in words:
Contractor Signature: Adithyan Parthasa�atry!r;M,, � —°'"°°
Date: 4/8/2025
Printed Name: Adithyan Parthasarathy Title: Assistant Project Manager
CO Worksheet
Description Quantity Unit Price Cost
Subcontractor Cost
$
Subtotal S
Labor Cost
Subtotal $
Material Cost
S
Subtotal $
Equipment Cost
Maintenance of Traffic Cost
$
$
Subtotal $
General Conditions
Subtotal $
Overhead and Profit
Subtotal 1 $ -
Subtotal Base Cost $
Bonding
TOTAL COST I -
!� Clay County Utility Authority
Working together to protect
r _ 3176 Old Jennings Road public health,conserve our
l` ^ Middleburg,Florida 32068-3907 natural resources,and
Telephone(904)213-5999 create long-term value for
our ratepayers,
Facsimile (904)213-2498
Change Order No.: 2 Date: 4/8/2025
Project: Fleming Island WRF Neutralizer Building
CCUA Bid No.: 22/23-A 10
CCUA Project No.: 2203-136
Vendor: Petticoat-Schmitt Civil Contractors,Inc Owner: Clay County Utility Authority
6380 Phillips Hwy
Jacksonville,Fl
(904)693-2190
Engineer of Record: J.Collins Engineering Associates,LLC.
12412 San Jose Blvd.,Suite 204
Jacksonville,FL 32223
(904)262-4121
ORIGINAL CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 12/4/2023
DAYS ADD 157
SUB.COMP. 365 12/3/2024 5/9/2025
FINAL COMP 395 1/2/2025 6/8/2025
INCREASE OR
DECREASE IN
I FI M DESCRIPTION OF CHANGE(S) QTY UNIT PRICE CONTRACT PRICE
Contract Increase
Relocate WAS pump,install with piping at wetwell,and
1 reconnect underground force main 1 $46.841.64 $46,841.64
Contract Decrease
TOTAL INCREASE $46,841.64
TOTAL DECREASE $0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $46,841.64
ORIGINAL CONTRACT PRICE $3,331,182.00
Net Increases by Change Orders(prior to this change order) $0.00
Net Decreases by Change Orders(prior to this change order) $0.00
I utal Net Change by Change Orders(prior to this change order) $0.00
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $3,331,182.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $46,841.64
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $3,378,023.64
This document shall become an amendment to the contract and all provisions of the contract will apply hereto.
Accepted by: 6/31 Date: 4/8/25
Engincc Record t
Accepted by: t• ���' Date: L 14 ZS
Ve •Velp
Accepted by ��� .`�—= '1.111.11 Date 2 ' —'p `—Z I
Ow le grin
petticoat
r� sch m itt
April 08,2025
Via Email
Ms. Heather Cavanagh, PE
Project Manager
Clay County Utility Authority
3176 Old Jennings Road
Middleburg, Florida 32068
RE: Change Order Request#004—Permit Delay Time Extension—R5
Fleming Island WRF Neutralizer Building, 1770 Radar Road, Fleming Island, 32003
CCUA Project No. 2203-136
PSCC Project No. 23200
Dear Ms. Cavanagh,
Please allow this letter and supporting documentation to serve as Change Order Request#004 for the
above referenced project.
Background
COR—004—R1(7/31/2024)-PSCC had requested 84 calendar days as a part of COR#004-Time
Extension. (Refer Change Order Request#004- R1). CCUA wanted to wait till the end of the project to
determine the actual days required to complete the project before approving a time extension.
COR—004—R2(11/21/2024)—PSCC had requested 91 calendar days as a part of COR#004-Time
Extension. (Refer Change Order Request#004-R2). Additional days were requested due to the change in
scope covered in COR 005—WAS Relocation. CCUA still wanted to wait till the end of the project to
determine the actual days required to complete the project before approving a time extension
COR—004—R3(12/13/2024)-CCUA has requested for the P6 schedule actualized till end of November
to re-evaluate the number of days required for successful completion of the project. PSCC requested 85
days after making edits to the schedule removing BCR FAT A and FAT B testing.Also, PSCC had an in-
person meeting with CCUA on 1/17/25 to review the change order.CCUA has sent a response letter
asking PSCC to provide acceptable documentation for the cost incurred during the delay.
COR-004—R4(02/27/25)
Reference to the response letter from CCUA, PSCC attached a revised cost and associated breakup for the
cost incurred during the permit delay period. Note: PSCC had removed the cost incurred due to the
delays associated with WAS relocation and the WAS communication issues.
P6 schedule additions:
Since PSCC started experiencing difficulties from the county building permit department similar to the
initial permit approval phase to get FEMA B approved,we had added (4) more weeks to the "Final
Inspections and COO" activity so that we do not request more time in the future.
6380 Philips Highway P 904.751.0888
Jacksonville,Florida F 904.751.0988
32216 petticoatschmitt.com
petticoat
r� sch m itt
COR—004-R5(Present)
CCUA has covered the cost associated with the delay using SWA allowance.
PSCC requests a time extension of(157) calendar days to the project schedule and requests CCUA to
revise Substantial Completion to 05/09/2025 and Final Completion date to 06/09/2025,to successfully
complete the project.
Sincerely,
Adithyan Parthasarathy
Assistant Project Manager
PETTICOAT-SCHMITT CIVIL CONTRACTORS, INC.
Phone: (904)612-4076
Email: aparth@Jpetticoatschmitt.com
Cc: Jeff Rumer, PSCC Vice President (jrumer@petticoatschmitt.com)
Anastasia Boyd, Project Manager(abovd@petticoatschmitt.com)
Jodi Marson, PSCC Project Coordinator(JMarson@petticoatschmitt.com)
John Collins, Engineer of Record,J. Collins Engineering Associates, LLC
(john@jcollinsengineering.com)
6380 Philips Highway P 904.751.0888
Jacksonville,Florida F 904.751.0988
32216 petticoatschmitt.com
Attachment 13 — I_:xiktioLl (1I' I'rojccl Re(lucst
Change Request Form Date Submitted 4-8-25
Project Information
Project Manager Name Joe Paterniti
Project Name/Numbers 2203-136 (2101ORR)
Fleming Island Regional WRF - 2nd BCR Plant
Project Description
Change Information
Project duration was extended to to various delays including:
Issue Prompting Change Building Permit Delay—84 days
WAS Communication and Switch Delay—45 days
FEMA B,Final Inspections and obtaining COO from Building County—28 days
Requested change to Requesting an additional 157 days to complete contract. Substantial
address Issue Completion date; March 27, 2025; Final Completion Date,April 26,2025
Change Urgency Red x Yellow Green
Change Analysis
Project Impacts
Scope None
Budget None
Schedule 157 Days
Team Impacts None
Other Benefits None
ACE or MCA;t ►'
ACE or MCI AK �$
Recommendationsr e— der-
Approvals
Approver Si ture Date
Chief Engineer / - �! — 2
Chief Financial Officer 4— icJ -a f
Executive Dir = zo _
Chief Operating Officer / 7 -2
* Refer to the CCUA engin g a n project change management process for
instructions.
CIP Initiation Process February 26, 2025
Certificate of Substantial Completion
Clay County Utility Authority
Project Name Fleming Island WRF Neutralizer Building CCUA Project No. 2203-136
Project
Location 1770 Radar Road Contractor Petticoat Schmitt
Project designated for Substantial Completion shall include(list any exceptions,attach punch list of deficient
Items):
See Attached List
Date of Substantial Completion Contractor's Acceptance
The date of Substantial Completion of the Project or portion The Contractor will��lete or correct the Items on the attached list
designated above is the date of issuance established by this of Defective,incomplete,or unacceptable Work within 30 days from
Certificate,which Is also the date of commencement of applicable the date of Substantial Completion_
warranties required by the Contract Documents except warranties
identified on a separate Certificate of Warranty Commencement Name Pt L i'litki_r.a1 R41 V405—%c.&.7.a
March 27, 2025 sgAN't'' A <{i 2115
Date of issuance Signature Date
Engineer's Certification Owner's Acceptance
Work performed under this Project or portion designated above has The Owne accepts the Project or portion designated above as
been Inspected and found,to the Engineer's best knowledge, Substentiai,y Complete and will commence ocxvpancy/use.
Information,and belief,to be Substantially Complete,
Name John Collins Name Heather Cavanagh
Qtc.C.e, 3/27/25 i \5 —( 'S/t/ZJ'
Signature Date Signature Date