Loading...
HomeMy WebLinkAbout08.a EDB TetraTech SA No. 1 PES Reclaimed Main Ext EXECUTIVE SUMMARY AGENDA ITEM: Supplemental Agreement No. 1 with Tetra Tech for Civil and Environmental Engineering Professional Services Agreement RFQ 2023/2024-A01 to provide Professional Engineering Services for the construction of new Reclaimed Main Extensions in the Northern Clay County area. CCUA Project No.: 2025-094 CCUA Financial Job No.: 25022WL Date:November 26,2025 BACKGROUND: CCUA staff requests approval from the Board of Supervisors to execute Supplemental Agreement No. 1 (SA1)with Tetra Tech to provide professional services for the design,bid,and construction administration services for the"North Clay Reclaimed Transmission Mains"project. Efficient operation of the reclaimed water system is central to CCUA's strategy to eliminate surface water discharges by 2032 to achieve compliance with Florida Senate Bill 64(2021). Senate Bill 64 mandated the elimination of"non-beneficial"surface water discharges from domestic wastewater utilities.In April 2022, CCUA's Board of Supervisors authorized the execution of Supplemental Agreement No. 8 with Jacobs Engineering (JE) to evaluate the operation and performance of the Utility's reclaimed water transmission and distribution systems, as well as the Supervisory Control and Data Acquisition(SCADA) system. With five (5) interconnected and one (1) independent reclaimed water facilities, CCUA can distribute sixty to seventy percent of the reclaimed water produced through its extensive public-access reuse system. By implementing the projects identified in JE's final report,CCUA will optimize its water resource system and achieve 100% beneficial reuse. Under SA1, Tetra Tech and their subconsultants will provide design services for three (3) reclaimed main extensions critical to meeting that goal. The design, survey, geotechnical, and environmental services are described in detail in the attached Scope and Fee Proposal. In March of this year, Florida Governor Ron DeSantis announced over $389 million in grants to improve water quality and quantity across Florida. The list of projects receiving grant funding included$6,000,000 for CCUA's reclaimed water optimization program. The board approved the grant agreement at the November 18,2025,board meeting.The services to be provided by Tetra Tech under SA1 are reimbursable under the grant funding. BUDGET: Staff budgeted $8.3M for this project within CCUA's Capital Improvements Program. The professional services fee of$698,844.00 proposed here is within this budget. Staff believe these fees are reasonable given the scope of services under this supplemental agreement. CCNA: CCNA, F.S. 287.055, does apply to the use of a consultant under a continuing contract. The anticipated construction cost of the project,including contingency,is$7,461,300.00.This does not exceed the statutory limit, $7,702,500.00, which includes the 2025 CPI adjustment. Staff negotiated the Supplemental Agreement in compliance with F.S. s.287.055. Staff and the consultant negotiated the scope and fee for the professional services at a compensation that CCUA determines is fair,competitive, and reasonable. RECOMMENDATION: Staff respectfully recommend that the Board of Supervisors approve the attached Supplemental Agreement No. 1 with Tetra Tech to provide Professional Engineering Services in the amount of$698,844.00 ATTACHMENTS: Supplemental Agreement No. 1 Scope&Fee Proposal Supplemental Agreement No. 1 to Professional Engineering Services Agreement 23/24-A01 with Tetra Tech to provide Professional Services for the design, bid, and construction administration services for the installation of the "North Clay Reclaimed Transmission Mains" Project CCUA Project No. 2025-094 Engineer: James J. Wallace, P.E. Owner: Clay County Tetra Tech. Utility Authority 8880 Freedom Crossing Trail, Suite#101, Jacksonville, FL 32256 Date: December 2, 2025 Item: Description of Services: Provide professional engineering services as identified in the attached scope of services and fee proposal. Task 001 Project Coordination $30,173.00 Task 002 Field Services $192,138.00 Task 003 Preliminary Engineering $74,213.00 Task 004 Final Design $219,740.00 Task 007 Permitting $26,549.00 Task 007 Bidding Support $17,341.00 Task 008 Construction Administration $49,039.00 Task 009 Allowance for Shop Drawings, RFIs, and COs $26,120.00 Total Price $635,313.00 Project Contingency (10%) $63,531.00 Total Price with Contingency $698,844.00 Total Price without Contingency Not to Exceed Without Prior Authorization The Contract time shall commence on December 3, 2025, and the scope of services is estimated to be completed in twenty-seven(27) months according to the schedule in the Scope and Fee Proposal. This document, along with the Scope and Fee Proposal, shall become an amendment to the Professional Engineering Services Agreement, and all provisions of the Agreement will apply hereto. Accepted by: Date: Engineer: James J. Wallace, P.E. Vice President Tetra Tech. Accepted by: Date: Owner: Jeremy D. Johnston, P.E., MBA, Executive Director Clay County Utility Authority lit TETRA TECH November 21, 2025 Mr.Joe Paterniti, PE Assistant Chief Engineer Clay County Utility Authority 3176 Old Jennings Road Middleburg, FL 32068 Subject: Professional Engineering Services for the North Clay Reclaimed Water Transmission Pipelines Tt# 200BP CCUA Dear Mr. Paterniti: Tetra Tech is pleased to furnish this proposal for professional engineering services to assist the Clay County Utility Authority(CCUA) with the North Clay Reclaimed Water Transmission Pipelines Project. A detailed scope of services and compensation summary are attached hereto. We look forward to providing these services to the CCUA. If you should have any questions, please do not hesitate to contact me at 904-451-2013. Very truly yours, Tetra Tech 1(.44(._ James J. Wallace, P.E. Vice President Attachments JJW/North Clay Reclaimed/11-21-25 Tetra Tech, Inc. 8880 Freedom Crossing Trail,Suite 101,Jacksonville,FL 32256 Tel 904.636.6125 Fax 904.636.6165 www.tetratech.com ATTACHMENT A CLAY COUNTY UTILITY AUTHORITY NORTH CLAY RECLAIMED WATER TRANSMISSION PIPELINES SCOPE OF SERVICES I. PROJECT DESCRIPTION Clay County Utility Authority (CCUA) intends to make reclaimed water transmission pipeline improvements as part of the North Clay Reclaimed Transmission Pipelines Project. To meet the growing demand for reclaimed water in the southern service area, CCUA must transfer an excess of reclaimed water from the northern service area. To do so, three pipeline segments are planned to parallel the existing transmission pipeline system where it is interconnected into the distribution system. This will create an uninterrupted transmission system that can maintain the pressures and needs of the system. • Segment 1 consists of 6,500 LF 20" reclaimed water main from the Spencer's Crossing Water Reclamation Facility (WRF)to a connection along Oakleaf Village Parkway. • Segment 2 consists of 2,800 LF 12" reclaimed water main paralleling Challenger Drive from Kindlewood Drive to the First Coast Expressway(SR 23)to connect to the Oakleaf system. • Segment 3 consists of 4,300 LF 12" reclaimed water main from White Bark Plantation Drive and Brannon Mill Blvd.,traversing the unimproved right of way(R/W)of Brannon Mill Blvd to Whisper Creek Blvd, continuing West to a CCUA held property East of Challenger Drive. This scope of services is for the design of all three segments, a combined length of approximately 13,600 linear feet (Project Limits). A figure of the three segments is included as Attachment B. The proposed pipeline routes are planned within existing R/W,CCUA property,and easements.No additional easements are anticipated for the project and therefore no land acquisition assistance has been included. In order to provide logical, orderly completion of this assignment,the project has been broken down into eight (8) tasks. Tasks to be completed are further described herein. This proposal is for professional engineering services associated with project coordination, field services, preliminary engineering, final design, permitting, bid support, construction administration, construction engineering inspection, and public relations services. II. SCOPE OF SERVICES 001. Project Coordination Services: Tetra Tech will provide project coordination and administration activities such as staffing, budget management, schedule management, and coordination with CCUA as required. This is based upon an assumed project schedule as identified in Section V. JJW/North Clay Reclaimed Transmission Pipelines Fit TETRATECH Tt#200BP CCUA -1- 11/21/2025 �"� Tetra Tech will provide the following Project Coordination services: A. Kickoff Meeting and Site Visit: • Tetra Tech will attend an in-person kickoff meeting with CCUA to discuss the proposed improvements and various design considerations, identify key team members, review the project scope and schedule, and determine available information. Tetra Tech will prepare a meeting agenda and meeting minutes for distribution to meeting attendees. The agenda will include applicable site figures to aid in the discussions. • Tetra Tech will perform a site visit to observe surficial conditions of the project corridor. This site visit will be conducted following the kick-off meeting. B. Tetra Tech will prepare a data request to gather existing available data from CCUA and other stakeholders, including any record drawings of existing utilities, including reclaimed water, potable water, gravity sewer, and sewer force mains, any planned improvements along the project limits, existing easement information, GIS maps and other information to help facilitate this project. C. Tetra Tech assumes up to three (3) additional field visits during the preliminary engineering and design phases to observe specific field conditions. D. Tetra Tech will provide the following additional project coordination services: • Tetra Tech will develop a project schedule to identify key project milestones for project tasks. The project schedule will include a work breakdown structure that provides an organized approach to project delivery, defined milestones, progress/workshop meetings, deliverables, and deliverable reviews. The schedule will be prepared using MS Project and updated at major project milestones. • Tetra Tech will prepare a project status report on a monthly basis throughout the design and bidding phase. Each monthly report will include a summary of the ongoing project activities as well as status updates for the schedule and budget. Specific topics to be addressed in each monthly report consist of the following: description of work-to-date, description of 30-day look-ahead, updated project schedule, pending action items, and budget summary. • Coordinate and document Quality Assurance and Quality Control (QA/QC)coordination reviews for the project. • General project coordination between CCUA,Tetra Tech, and subconsultants necessary to help facilitate this project. Deliverables: • Meeting Agendas and Meeting Minutes • Project Schedules • Project Status Reports � JJW/North Clay Reclaimed Transmission Pipelines Fit TETRATECH Tt#200BP CCUA -2- 11/21/2025 "� 002. Field Services: All field services will be coordinated with CCUA, and will consist of the following: A. Topographic Surveying Services: Topographic surveying services are proposed to be performed by Degrove Surveying, LLC, and will consist of the following: • Topographic surveying will consist of(1) foot topography, surface utilities, stormwater culverts, R/W and easement boundaries, and above ground features within the route limits, with cross sections every 100'. In addition, topographic survey will include 10 feet outside, but contiguous to, the R/W on each side of the R/W. Will include picking up existing fence locations and fence types (field fence, barbed wire, etc.). • Subsurface Utility Engineering(SUE)in accordance with ASCE 38-02 Quality level B along the three project routes. • Once the proposed routing is confirmed by CCUA,SUE will be performed in accordance with ASCE 38-02 Quality level A. Up to 35 test holes will be included. • A tree survey will be included where applicable. Trees larger than 6-inch diameter at breast height(DBH) will be collected,with species identified. • Coordinate with the Ecological and Geotechnical Engineering services as identified in Tasks 002.E and 002.0 to collect the wetland flags, endangered species flags, and geotechnical boring locations. • Vertical control data shall be based on the North American Vertical Datum 1988. Benchmarks will be provided in the project site as needed for the various areas provided above. • Horizontal control data shall be relative to the Florida State Plane Coordinate System, North American Datum of 1983/1990 adjustment. • All work will be completed under the direct supervision of a professional surveyor and mapper licensed to practice in the State of Florida and work will be in accordance with the Standards of Practice set forth by the Florida Administrative Code 5J-17.051 for Surveyors & Mappers, pursuant to Section 472.027 Florida Statutes. B. Ecological Services: Ecological services will consist of the following: • Tetra Tech will delineate the extent of Florida Department of Environmental Protection (FDEP) state wetlands and USACE federal wetlands, including Waters of the U.S. (WOTUS), and other surface waters according to the current ( regulations, JJW/North Clay Reclaimed Transmission Pipelines ICI TETRATECH Tt#200BP CCUA -3- 11/21/2025 "� interpretations, and guidelines where the project limits encroach upon said waters/wetlands. • During the wetland delineation, Tetra Tech will conduct a preliminary assessment of protected species and their habitats within the project limits and bordering areas. • Tetra Tech will prepare a Wetlands and Listed Wildlife and Habitat Assessment Report with shapefiles to support the engineering drawings for planning, design, and local, state, and federal permitting purposes. C. Geotechnical Engineering Services: Geotechnical engineering services are proposed to be performed by Ardaman &Associates, Inc., and will consist of the following: • Perform thirty-seven (37) auger borings to a maximum depth of 10-feet, for the proposed open cut pipeline, at an approximate spacing of 400-ft.Three (3) SPT borings to a maximum depth of 40-feet are also included as an allowance to accommodate the potential trenchless installation in pipeline segment 3. Otherwise, all other pipelines are assumed to utilize open-cut installation. • Evaluate general subsurface conditions and develop engineering recommendations to guide earthwork, site preparation and foundation support for the cut and cover of proposed pipeline and unpaved access roadway. • Estimate the normal seasonal high groundwater level (SHGWL) at the boring locations. • Prepare a Geotechnical Evaluation Report summarizing the data compiled during the exploration. Deliverables: • Topographic Survey and SUE • Wetlands and Listed Wildlife and Habitat Assessment Report • Geotechnical Evaluation Report 003. Preliminary Engineering Services: A. The conceptual design phase will confirm the pipeline routing prior to development of construction documents. Tetra Tech will finalize the detailed reclaimed water main installation technique during this phase.Tetra Tech shall review all aerial,topographic, GIS, property and utility maps within the reclaimed water main corridor as well as conduct surface reconnaissance field trips as needed to determine a preliminary alignment that conforms to the scope.A proposed reclaimed water main route shall be developed by Tetra Tech in AutoCAD format. The proposed route will be based on record drawings and information provided by CCUA.The route shall show the following information: • Locations of major underground infrastructure. (� JJW/North Clay Reclaimed Transmission Pipelines ICI TETRATECH Tt#200BP CCUA -4- 11/21/2025 �"� • Locations of above ground infrastructure. • Identify areas of concern for subsurface exploration. • Route evaluation and method of construction (open-cut or trenchless). • Site access (ingress/egress) and construction easements, if required. • Preliminary Maintenance of Traffic (MOT) considerations. • Include a 30% level EOPCC(A.A.C.E. Class 3) B. Tetra Tech will prepare 30% concept drawings for the proposed pipeline route and access roadway.This is anticipated to include a cover sheet,general notes, key map and reclaimed water plan views of the pipeline at a 1"=20' scale. This is anticipated to be approximately 30 plan sheet figures on aerial imagery. These concept drawings will include topographic survey and wetlands delineated in Task 002. C. Tetra Tech will attend one (1) in-person review meeting to discuss CCUA's comments. 004. Final Design Services: Tetra Tech will prepare and submit construction documents, including engineering drawings, technical specifications, and an engineer's opinion of probable construction cost(EOPCC) at the 75% and 100% design completion levels for CCUA review. The final design services will consist of the following: A. Engineering Drawings will be provided at the 75% and 100% design completion levels and prepared utilizing AutoCAD Civil 3D and provided to CCUA as a PDF document.A preliminary list of engineering drawings is presented below: General—5 sheets Cover Sheet (1 sheet) Signature sheet(1 sheet) Index of Drawings (1 sheet) General Notes (1 sheet) Legend and Abbreviations (1 sheet) Civil—42 sheets Reclaimed Water Main Plan and Profile Sheets (Scale: 1" = 20' H, 1" = 5' V) (30-sheets) Civil Details (1 sheet) CCUA Standard Details (4 sheets) Sedimentation and Erosion Control Notes and Details (2 sheets) Maintenance of Traffic Standard Plans (5 sheets) B. Technical Specifications: Technical Specifications will be submitted at the 75% and 100% design completion levels, will be prepared utilizing Microsoft Word, and provided to CCUA as a PDF document.Tetra Tech will prepare the project Bid Form and Technical Specifications. C. Engineer's Opinion of Probable Construction Cost (EOPCC): JJW/North Clay Reclaimed Transmission Pipelines ICI TETRATECH Tt#200BP CCUA -5- 11/21/2025 �"� The EOPCC will be provided at the 75% (A.A.C.E. Class 2) and 100%(A.A.C.E. Class 1) design completion levels and provided to CCUA as a PDF document. Tetra Tech will prepare an EOPCC based on previous bid tabulations, vendor quotes, and estimates provided by Contractors. D. Quality Assurance/Quality Control: Tetra Tech will implement a quality assurance and quality control (QA/QC) program as an integral part of the delivery of the project at the 75% and 100% design completion levels. Quality reviews are an internal QA/QC procedure that will be done by senior level technical peers who were not involved in the development of the documents. The senior level technical peers will review draft documents for proper application of the approved assumptions, calculation methods, design methods and technologies. E. Review Meetings: Tetra Tech will attend an in-person design review meeting with CCUA at the 75%and 100% design completion levels. Tetra Tech will maintain a comment tracking log and provide responses to all comments received from each design completion level. Deliverables: • Engineering Drawings at the 75%and 100% Design Completion Levels • Technical Specifications at the 75%and 100% Design Completion Levels • EOPCC at the 75%and 100% Design Completion Levels • Comment Tracking Log and Responses at the 75%and 100% Design Completion Levels 005. Permitting Services: Tetra Tech will prepare and submit required project-related permit applications and supporting documentation necessary to obtain the required permits for the construction and operation of the project. Tetra Tech will respond to requests for additional information (RAI's) from permitting agencies.All permit application fees shall be paid directly by CCUA. Tetra Tech will hold pre-application meetings with applicable agencies, dependent on the meetings previously held during Task 001.C. The following permit applications and support are anticipated: A. Coordination with the Florida Department of Environmental Protection (FDEP) and CCUA regarding incorporation of the three (3) pipeline segments under the existing FDEP wastewater facility reuse design/operation plan (through FDEP 62-610). The pipelines are assumed to be covered under the existing facility reuse permit. B. FDEP Environmental Resource Permit (ERP) Exemption. C. United States Army Corps of Engineers (USACE) Nationwide Permit. JJW/North Clay Reclaimed Transmission Pipelines Fit TETRATECH Tt#200BP CCUA -6- 11/21/2025 �"� D. Clay County Right of Way Permit. E. Florida Department of Transportation (FDOT) Utility Permit. Deliverables: • Permits Obtained During this Task. 006. Bid Support Services: Bidding and award activities will be performed by CCUA's Procurement Department.Tetra Tech will assist these bid support services, supporting the singular bidding of the three pipeline segments,which will consist of the following: A. Tetra Tech will provide CCUA with a master copy of the Bidding Documents in electronic format (PDF). CCUA will be responsible for advertisement and distribution of bid packages to potential bidders. B. Tetra Tech will provide CCUA with written responses to any questions from bidders and prepare addenda as required to interpret, clarify, or expand the Bidding Documents for distribution to potential bidders by CCUA. C. Tetra Tech will attend and support one (1) pre-bid meeting. D. Tetra Tech will review and evaluate up to the three (3) lowest bidder's qualifications, including the review of up to three (3) provided references for undertaking the work and make recommendation of the award of the contract to CCUA. E. Prepare conformed Contract Documents for CCUA and a signed and sealed set and a PDF copy for the awarded Contractor. Deliverables: • Bidding Documents • Bidding Addenda • Recommendation of Award • Conformed Documents 007. Construction Administration Services: During the construction phase, Tetra Tech will provide limited construction administration services as detailed below.The construction administration services will consist of the following based on a construction duration of 16 months (480 calendar days), which includes 2 months for startup, 10 months for construction, 2 months to substantial completion, 1 month to final completion, and 1 month for final closeout: JJW/North Clay Reclaimed Transmission Pipelines Fit TETRATECH Tt#200BP CCUA -7- 11/21/2025 �"� A. Prepare for and support one (1) pre-construction meeting. Tetra Tech will be responsible for preparing the meeting agenda and recording/distributing meeting minutes. B. Attend fourteen (14) monthly site visits to the construction site to observe construction of the project and attend fourteen (14) monthly progress meetings. The site visits will be performed by Tetra Tech's Engineer of Record (EOR) or their representative, ensuring the representative is a licensed Professional Engineer(PE) in the State of Florida,to observe the progress and quality of the construction and to document general conformance with the Contract Documents. The site visits will be conducted following each progress meeting. Tetra Tech will provide input to CCUA for meeting agendas and meeting minutes for each progress meeting. C. Review of up to fourteen (14) applications for payment. Based on Engineer's observations and review of accompanying supporting documentation, determine the recommended payment amounts that Engineer recommends Contractor be paid in writing on application form. D. Upon written request by the Contractor, Tetra Tech and CCUA will conduct a substantial completion inspection of the project with preparation and distribution of a punch list of observed deficiencies to be completed by the Contractor prior to the final completion date. The project will be certified substantially complete only if the work is sufficiently complete in accordance with the contract documents, so that the work can be utilized for the purposes for which it is intended. E. Once substantial completion punch list items have been appropriately addressed, Tetra Tech and CCUA will conduct a final completion inspection of the project. F. Prepare record drawings for CCUA use, incorporating changes made during construction based on record information furnished by the Contractor in electronic format (AutoCAD). Provide CCUA with one (1)flash drive with an electronic file of record drawings in AutoCAD (using the release currently in use by Tetra Tech), one (1)full size (22"x34") set,and two (2) scalable half size (11"x17") sets of the record drawings. G. Prepare and submit certifications and required supporting documentation to regulatory agencies having jurisdiction. Deliverables: • Support Meeting Agendas and Meeting Minutes • Review of Shop Drawings, RFIs, Change Order, Work Change Directives • Application for Payment Recommendations • Substantial Completion Punch List • Record Drawings and Certifications • Regulatory Certifications JJW/North Clay Reclaimed Transmission Pipelines ICI TETRATECH Tt#200BP CCUA -8- 11/21/2025 �"� 008. Construction Services(Time& Materials Items): During the construction phase, Tetra Tech will provide limited construction administration services as detailed below.The construction administration services will consist of the following based on a construction duration of 16 months (480 calendar days), which includes 2 months for startup, 10 months for construction, 2 months to substantial completion, 1 month to final completion, and 1 month for final closeout: A. Review up to fifteen (15) shop drawings,for up to two (2) reviews per submittal, and other submittals to determine general conformance with the design concepts of the project and compliance with the requirements provided in the contract documents. B. Review up to ten(10) requests for information(RFIs),provide interpretation of construction documents, and issue written clarifications or interpretations. C. Review up to five (5) requests for change orders and work change directives and prepare subsequent documentation. III. ASSUMPTIONS 1. Hydraulic modeling services to verify the pipe size and capacity have previously been completed by others, and therefore, are not included as part of this scope of services. 2. CCUA will provide all record drawings, as-builts, pertinent easement/property information, and GIS files related to the prospective routes(s). 3. Easement drawings and real estate acquisition assistance are not included in this scope of services. 4. CCUA will provide timely reviews and comments on all submittals so as to support the project schedule; a two-week review period for each deliverable has been included in the schedule. 5. Groundwater sampling and analyses to comply with the FDEP Generic Permit for the Discharge of Produced Groundwater from Any Non-Contaminated Site Activity is not included in the cost proposal, as no contamination was found within 500 feet of the project per review of the FDEP contaminant locator map. 6. A dewatering plan is not included in this scope of work. If a dewatering plan is required for agency approval, it will be under a separate scope of work. Based on recent FDOT permitting experience in the past year, FDOT does not require a dewatering plan to be submitted with a utility permit application;the contractor is responsible to submit a dewatering plan to FDOT as part of the utility permit conditions. 7. If hazardous materials or contaminated soils or groundwater are found during the geotechnical investigation,subsurface utility investigation, or construction, additional testing, investigation,or remediation are not included in this scope of services. JJW/North Clay Reclaimed Transmission Pipelines ICI TETRATECH Tt#200BP CCUA -9- 11/21/2025 "� 8. Pavement design or redesign is not included in this scope of services, other than removing and replacing existing pavement for reclaimed water main construction, in accordance with FDOT and Clay County standard details. 9. Test holes and soil borings to be performed within FDOT R/W require a FDOT General Use Permit. To minimize schedule impacts, test holes and soil borings in FDOT R/W will be identified as early as possible and prioritized. We will keep CCUA apprised of any schedule impacts resulting from the FDOT General Use Permit approval process. 10. CCUA will be responsible for the Bidding and Contract Requirements (i.e., Divisions 0 and 1); however,Tetra Tech will support as needed. 11. Electronic submission of the Permitting applications with all application fees paid for by CCUA. 12. Permit applications are assumed to include one (1) meeting with each agency to discuss project and one (1) request for additional information (RAI) response prepared by Tetra Tech. 13. It is anticipated that permanent wetland impacts will be less than 0.1 acres. If permanent wetland impacts are greater than 0.1 acres,then an Individual State ERP and Individual USACE Permit will be required, and Tetra Tech will request additional funding. 14. It is anticipated that the project will meet the FDEP criteria for exempt activities and will not require an FDEP General Permit. If an FDEP General Permit is required, Tetra Tech will request additional funding. 15. Storm Water Pollution Prevention Plans (SWPPP) and National Pollutant Discharge Elimination System (NPDES) permits are not included in this scope of services and are assumed to be a part of the awarded Contractor's responsibilities. 16. It is assumed that the project will be bid and constructed as one (1) project. 17. It is assumed that this project is bid as a traditional design-bid-build project and not a Construction Manager at Risk(CMAR) or other alternative delivery method. 18. It is assumed that there are no funding requirements (loans, grants, appropriations, etc.) that would require additional design, coordination, etc. to complete the project as defined. 19. If project is required to be rebid for any reason, additional bidding services may be necessary. JJW/North Clay Reclaimed Transmission Pipelines ICI TETRATECH Tt#200BP CCUA -10- 11/21/2025 "� IV. COMPENSATION SUMMARY The total compensation for the above-described services is$635,313 for Tasks 001 through 008 to be provided on a Lump Sum basis. A fee breakdown is provided below, and a detailed breakdown is included as Attachment C. Services will be invoiced to CCUA on a monthly basis. Amount 001. Project Coordination Services $30,173 002. Field Services $192,138 003. Preliminary Engineering Services $74,213 004. Final Design Services $219,740 005. Permitting Services $26,549 006. Bid Support Services $17,341 007. Construction Administration Services $49,039 008. Construction Services (Time & Materials Items) $26,120 Total Price: $635,313 General Contingency(10%) $63,531 Total Price (with Contingency): $698,844 Note: Subconsultant proposals provided in Attachments D and E. JJW/North Clay Reclaimed Transmission Pipelines ( )TETRA TECH Tt#200BP CCUA -11- 11/21/2025 l V. SCHEDULE This schedule is based off an assumed notice to proceed (NTP) date of December 16, 2025. Any modifications to the NTP date would affect the dates listed below. Milestone Duration Cumulative Date (Weeks) Duration (Weeks) Notice to Proceed 12/16/2025 Kickoff Meeting 3 3 1/6/2026 Surveying* 6 9 2/17/2026 Ecological Assessment* 8 11 3/3/2026 Geotechnical Investigation* 10 13 3/17/2026 Basis of Design 5 14 3/24/2026 30% Design Review Meeting 2 16 4/7/2026 75% Design Submittal 14 30 7/14/2026 75% Design Review 2 32 7/28/2026 Permit Application Submittals& RAI Responses 6 38 9/8/2026 100% Design Submittal (Bid Package) 6 44 10/20/2026 Bidding 8 52 12/15/2026 Construction NTP 2 54 12/29/2026 Materials Procurement& Mobilization 8 62 2/23/2027 Pipeline Installation &Testing 40 102 11/30/2027 Substantial Completion 8 110 1/25/2028 Final Completion 8 118 3/21/2028 Note: Schedule assumes a 2-week review of all deliverables by CCUA. JJW/North Clay Reclaimed Transmission Pipelines ICI TETRATECH Tt#200BP CCUA -12- 11/21/2025 �"� ATTACHMENT B CLAY COUNTY UTILITY AUTHORITY NORTH CLAY RECLAIMED WATER TRANSMISSION PIPELINES PROJECT INFORMATION SHEETS JJW/North Clay Reclaimed Transmission Pipelines ( 1 TETRA TECH Tt#200BP CCUA 11/21/2025 l ���'�` CO`'"r� Clay County Utility Authority - Reclaim Water System ill Recommended Project Information Sheet G� 272-5999 'eitYAUnko* Transmission Pipeline Isolation Projects Project 1: Transmission Pipeline from Spencer's RWF to Oakleaf RWF (6,500 ft LF of20"PVC C905) The Spencer's Water Reclamation Facility (WRF) supplies water to the Oakleaf Plantation distribution area through a 16-inch transmission pipeline connected to a distribution network. However, because the transmission line is connected to the distribution system, it must maintain specific operational constraints and network pressures. The restrictions limit its ability to operate solely as a dedicated transmission line. To overcome this challenge, CCUA will install a 6,500 feet of 20-inch pipeline parallel to the distribution system. This new pipeline will be a dedicated transmission line, bypassing the distribution system connections. The project will allow the transmission line to operate independently and effectively distribute water to the Oakleaf Plantation distribution zone, ensuring a reliable and uninterrupted supply of water. PROJECT Project Improvements • 6,500 feet of 20-inch diameter C900 PVC pipe • Install necessary valves and cleanout fixtures CLAY • Temporarily bypass roughly 70 homes during the installation • Install new asphalt pavement • Reconstruct sidewalks and yards — j BEGIN PROJECT `� S'v i .•ji..........7. \N / 117:---- —'s‘k /11I tit r I 1 ..i�, I e I Crane - ' I \\ \�‘ -Proposed pipeline \� �\ Distribution network END PROJECT - Existing transmission pipeline I__ I Project area Project Cost: $3.18 million Construction: 7-8 months Project Mission:to provide its customers with reliable reclaimed water.To achieve this,CCUA is committed to investing in its infrastructure and improving its operations.These upgrades will help optimize the transfer and distribution of water, which means that the reclaimed water can be delivered more reliably.By doing this,CCUA will be able to reduce unnecessary river discharges and avoid using augmentation wells,which is better for the environment. o CO`'"r� Clay County Utility Authority - Reclaim Water System �I Recommended Project Information Sheet GT�72-5999 �� ,��TY 2-5999 ` Transmission Pipeline Isolation Projects Project 2: Oakleaf RWF Connection to Challenger Drive (2,800 ft LF of 12" PVC C905) Two water reclamation facilities (WRFs)supply water to the Oakleaf Plantation distribution area via transmission pipelines that merge at a set of diversion valves, forming a single transmission pipeline that stretches to the Old Jennings Road (OJR) WRF. However, a 12-inch connection to a neighborhood at Kindlewood Drive along this transmission line limits its capacity to serve solely as a dedicated transmission line. To ensure a dependable and uninterrupted reclaimed water supply, CCUA will install 2,800 feet of 12-inch pipeline parallel to Challenger Drive, beginning at Kindlewood Drive and extending to the First Coast Expressway (SR 23), connecting the neighborhood to the Oakleaf distribution system. This undertaking will allow the transmission line to function independently and proceed unobstructed to the OJR WRF without any residential connections. PROJECT Project Improvements 1 4- • 2,800 feet of 12-inch diameter C900 PVC pipe • Install necessary valves and cleanout fixtures CLAY • Disconnect one major lateral at Kindlewood Dr. • Reconstruct sidewalks, curbs, and ditches • BEGIN PROJECT • 0 1 1 1 II 5 j 1 1 — - p.r' p 1 xiu2ale ` dk/ `llplanta!ion Pc + r 7--):— , •s -----4____---1, ' END PROJECT v _ a -Proposed pipelineo N N r — Distribution network 8 - C O ) - Existing transmission pipeline J �__ I Project area \ = LL n --I, Project Cost: $0.96 million Construction: 3-4 months Project Mission:to provide its customers with reliable reclaimed water.To achieve this,CCUA is committed to investing in its infrastructure and improving its operations.These upgrades will help optimize the transfer and distribution of water, which means that the reclaimed water can be delivered more reliably.By doing this,CCUA will be able to reduce unnecessary river discharges and avoid using augmentation wells,which is better for the environment. �,,,,'N CO`'"r� Clay County Utility Authority - Reclaim Water System rat Recommended Project Information Sheet G� 72-5999 /T}'AUTNO* Transmission Pipeline Isolation Projects Project 3: Transmission Pipeline North of OJR RWF (4,300 ft LF of 12" PVC C905) To ensure a reliable and consistent reclaimed water supply, CCUA has identified a need to install 4,300 feet of 12-inch pipeline that bypasses residential connections along the transmission pipeline en route to the Old Jennings Road (OJR) Water Reclamation Facility. The current transmission line along SR 23 has several residential connections, which limits its capacity to function solely as a dedicated transmission line. The proposed new pipeline will begin at White Bark Plantation Drive, traverse a wooded path onto Whisper Creek Boulevard, and terminate just east of Challenger Drive. This project will connect the neighborhood to the northern OJR distribution system, allowing the transmission line to function independently and proceed unobstructed to the OJR WRF, free from any residential connections, ensuring an uninterrupted supply of reclaimed water. .- Project Improvements PROJECT • 4,300 feet of 12-inch diameter C900 PVC pipe • Install necessary valves and cleanout fixtures CLAY • Disconnect one major lateral at Whisper Creek Blvd. • Reconstruct sidewalks, curbs, and ditches --\ END PROJECT %�� i ; \ j , - -� j \\ \ �' 77- ---T \ _ _ _ \� ^ \ -Proposed pipeline \ \\` Distribution network BEGIN PROJECT - Existing transmission pipeline /_ I-- I Project area /-i`\ Project Cost: $1.47 million Construction: 4-5 months Project Mission:to provide its customers with reliable reclaimed water.To achieve this,CCUA is committed to investing in its infrastructure and improving its operations.These upgrades will help optimize the transfer and distribution of water, which means that the reclaimed water can be delivered more reliably.By doing this,CCUA will be able to reduce unnecessary river discharges and avoid using augmentation wells,which is better for the environment. ATTACHMENT C CLAY COUNTY UTILITY AUTHORITY NORTH CLAY RECLAIMED WATER TRANSMISSION PIPELINES DETAILED FEE BREAKDOWN JJW/North Clay Reclaimed Transmission Pipelines ( 1 TETRA TECH Tt#200BP CCUA 11/21/2025 l ® Revision Date: Labor Plan ATTACHMENT C Price Proposal Nov 21,2025 7Resource North Lake Reclaimed Water Transmission Pipelines Bill Rate> 300.00 250.00 200.00 195.00 135.00 160.00 120.00 Proj Area> Submitted to:Clay County Utility Authority(CCUA)(Attn:Joe Paterniti,P.E.) Pricing by Resource Total _ m o e t fi '6 `ts Task Pricing Schedule Labor Hrs a d d Labor Subs Travel/ODCs Totals Project Phases/Tasks From Thru Months 2,430 106 66 `756 192 ` a d 768 548 `44 449,200 183,198 2,915 635,313 001-Project Coordination Services 146 18 - 84 - 32 - 12 29,843 - 330 30,173 A.Kickoff Meeting,Minutes,&Site Visit 12/15/25 01/15/26 1.0 8 4 4 2,048 110 2,158 B.Data Request 12/15/25 03/24/26 3.2 6 2 4 1,459 1,459 C.Additional Field Visits(3) 12/15/25 10/31/26 10.3 16 4 12 3,771 220 3,991 D.Project Coordination 116 8 - 64 - 32 - 12 22,566 - - 22,566 Project Schedule 10/01/25 03/31/28 29.4 26 2 a 16 4,694 4,694 Project Status Reports 10/01/25 03/31/28 29.4 46 2 16 16 12 7,967 7,967 General Project Coordination 10/01/25 03/31/28 29.0 44 0 00 9,905 9,905 002-Field Services 38 6 - 32 - - - - 8,610 183,198 330 192,138 A.Topographic Surveying 18 2 - 16 - - - - 3,990 159,525 110 163,625 Topographic Surveying 01/01/26 04/01/26 2.9 - 159,525 159,525 Coordination 01/01/26 04/01/26 2.9 18 2 16 3,990 110 4,100 B.Ecological Services 10 2 - 8 - - - - 2,310 8,073 110 10,493 Ecological Services 01/01/26 04/01/26 2.9 - 8,073 8,073 Coordination 01/01/26 04/01/26 2.9 10 2 8 2,310 110 2,420 C.Geotechnical Engineering 10 2 - 8 - - - - 2,310 15,600 110 18,020 Geotechnical Engineering 01/01/26 04/01/26 2.9 - 15,600 15,600 Coordination 01/01/26 04/01/26 2.9 00 8 2,310 110 2420 003-Preliminary Engineering Services 412 12 16 112 24 128 120 - 74,213 - - 74,213 A.Conceptual Design 12/15/25 04/07/26 3.6 100 4 40 8 48 17,980 17,980 B.Conceptual Design Drawings 12/15/25 04/07/26 3.6 304 4 16 68 16 80 120 54,147 54,147 C.Conceptual Design Review Meeting 12/15/25 04/07/26 3.6 8 4 2,086 2,086 004-Final Design 1,236 24 48 292 80 404 360 28 219,135 - 605 219,740 A.Engineering Drawings 852 8 - 196 48 240 360 - 148,008 - 385 148,393 75%Design Drawings 04/07/26 10/20/26 6.3 564 0 128 33 160 200 97,692 275 97,967 100%Design Drawings 04/07/26 10/20/26 6.3 288 0 68 16 80 120 50,316 110 50,026 B.Technical Specifications 240 9 - 72 24 120 - 20 40,824 - - 40,824 75%Technical Specifications 04/07/26 10/20/26 6.3 158 2 48 16 80 12 26,838 26,838 100%Technical Specifications 04/07/26 10/20/26 6.3 82 2 24 8 00 0 13,986 13,986 C.EOPCC 54 2 - 16 8 28 - - 9,597 - - 9,597 75%EOPCC 04/07/26 10/20/26 6.3 29 1 8 4 16 5,082 5,082 100%EOPCC 04/07/26 10/20/26 6.3 25 1 8 4 12 0,515 4,515 D.QA/QC 54 6 48 - - - - - 14,490 - - 14,490 QA/QC 04/07/26 10/20/26 6.3 54 6 08 10,490 14490 E.Review Meetings 36 9 - 8 - 16 - 8 6,216 - 220 6,436 75%Review Meeting and Tracking Log 07/14/26 08/14/26 1.0 18 2 4 8 4 3,108 110 3,218 100%Review Meeting and Tracking Log 10/20/26 11/20/26 10 18 4 8 4 3,108 110 3,218 005-Permitting 146 6 - 48 16 60 16 - 26,439 - 110 26,549 A.FDEP Coordination on Reclaimed Water 09/01/26 12/15/26 3.4 6 2 4 1,470 1,470 B.FDEP ERP 09/01/26 12/15/26 3.4 29 1 8 4 12 4 5,187 5,187 C.USACE Nationwide Perma 37 1 - 12 4 16 4 - 6,599 - 110 6,704 USACE Nationwide Permit 09/01/26 12/15/26 3.4 - - Coordination 09/01/26 12/15/26 110 6,704 D.Clay County Right of Way Permit 09/01/26 12/15/26 3.4 37 1 12 4 16 4 6,594 6,594 E.FDOT Utility Permit 09/01/26 12/15/26 3.4 37 1 12 9 16 4 6,594 6,594 006-Bid Support 90 8 - 32 6 24 20 - 17,231 - 110 17,341 A.Prepare Bid Documents 10/20/26 12/15/26 1.8 22 2 4 8 8 3,948 3,948 B.Answer Questions/Prepare Addenda 10/20/26 12/15/26 1.8 34 2 16 9 8 4 6,615 6,615 C.Attend PreBid Meeting 10/20/26 12/15/26 1.8 6 2 4 1,470 110 1,580 D.Bid Evaluation&Rec.of Award 10/20/26 12/15/26 1.8 7 1 4 2 1,565 1,565 E.Prepare Conformed Documents 10/20/26 12/15/26 1.8 21 1 4 8 8 3,633 3,633 007-Construction Administration Services 224 26 2 108 4 48 32 4 47,609 - 1,430 49,039 A.Pre-Construction Meeting 01/01/27 03/31/28 14.7 6 2 4 1,559 110 1,669 B.Construction Progress Mtgs/Site Visits(14) 01/01/27 03/31/28 14.7 64 8 56 15,142 1,100 16,242 C.Payment Application Review 01/01/27 03/31/28 14.7 26 2 8 16 4,854 4,854 D.Substantial Completion Inspection 01/01/27 03/31/28 14.7 12 4 8 3,118 110 3,228 E.Final Completion Inspection 01/01/27 03/31/28 14.7 12 4 8 3,118 110 3,228 F.Prepare Record Drawings 01/01/27 03/31/28 14.7 62 4 2 8 4 16 24 4 11,758 11,758 G.Regulatory Certifications 01/01/27 03/31/28 14.7 42 2 16 16 8 8,061 8,061 008-Construction Services(Time&Materials Items) 138 6 - 4s 12 72 - - 26,120 - - 26,120 A.Shop Drawing Review(15) 01/01/27 03/31/28 14.7 66 2 24 9 36 12,292 12,292 B.Clarifications&RFIS(10) 01/01/27 03/31/28 14.7 46 2 16 9 24 8,707 8,707 C.Assist with Change Orders(5) 01/01/27 03/31/28 14.7 26 2 8 4 12 5,122 5,122 Totals 10/01/25 03/31/28 29.4 2,430 106 66 756 142 768 548 94 449,200 183,198 2,915 635,313 Tetra Tech-Confidential and Proprietary Page 1 of 1 Printed 11/21/2025 ATTACHMENT D CLAY COUNTY UTILITY AUTHORITY NORTH CLAY RECLAIMED WATER TRANSMISSION PIPELINES SURVEY SUBCONSULTANT SCOPE (DEGROVE) JJW/North Clay Reclaimed Transmission Pipelines ( 1 TETRA TECH Tt#200BP CCUA 11/21/2025 l DE R V E SURVEYORS, INC. November 18, 2025 Daniel D. Hill, P.E. Tetra Tech 8880 Freedom Crossing Trail, Suite 101 Jacksonville, Florida, 32256 Subject: Surveying and Mapping Services — Clay County Utility Authority - Reclaim Water System Dear Mr. Hill: The following is a proposal for surveying and subsurface utility designation services in support of the referenced Reclaimed Water Main project. Project Limits Project 1 - Transmission Pipeline from Spencer's RWF to Oakleaf RWF From the Spencer's Reclaimed Water Facility, west along Wandering Oaks Drive, to the intersection with Trellis Trail, south along Trellis Trail to Canopy Oaks Drive, West on Canopy Oaks Drive, to the intersection with Oakleaf Village Parkway, south along Oakleaf Village Parkway to the Waterford Ranch at Oakleaf neighborhood. /w it ., , wt i/, . i -:.-1_g 14.4 a""`ZR;fr41,,44_Z1 A 4Yi:rdI'4't rs . 4. . ' ' ;ii r l►/tie ra it 1:1.A- S, o .4pe:; , ,; 4- ‘: J� ` ,K!%1 IIP to"it - 1 . r Iry'.,,t, 110:.'NA'7/ •',%/,, , //,/„/,/ ' ' 1/ \\,,,,c, Map - Project 1 2131 CORPORATE SQUARE BLVD. JACKSONVILLE, FLORIDA 32216 (904)722 0400 • FAX(904)722 0402 DEGROVE@DEGROVE.COM Project 2 - Oakleaf RWF Connection to Challenger Drive From just west of the intersection of Kindlewood Drive with Old Cardman Highway, west along Kindlewood Drive to the intersection with Challenger Drive, north along the area east of Challenger Drive right of way to the CCUA Property. 0 ' ' Tie-in i .ONO.1111..NM '. _.. III 1 0 J. Ct d t - c - \ . .. _ . '1 i • 1 a 44 . W --,_,.._.... _ a Y `T+ -icy �1.. • i `i •-• k tl 1 — -1 ib.,......-.4_,..... \------' . , , cl- ; .., imipt, .-".--4L . ..,,,,,[ 4., k I\ . L ll1 -I/ 1 , , -r _ ' _Awl AV . - - rr I ,..,, ,.....sta.,..0,,,,,, - -; - II I 1 •!��k- - ~F I 1 1 L. , , 1.1..41.....____..., Map - Project 2 Project 3 - Transmission Pipeline North of OJR RWF From a retention pond just East of Challenger Drive, southeast tn Heather Glen Lane, south along Heather Glen Lane, k} the intersection with Whisper Creek Boulevard, east along Whisper Creek Boulevard to the intersection with a Right-of-way for an undeveloped section of Brannan Mill Boulevard, southeasterly along the undeveloped section Of Brannan Mill Boulevard t0 where it becomes paved, t0 just south Of Brannan Mill Boulevard intersection with VVhit8b@rk Plantation Drive. VV 40. 10 OF rd. its CUA property IP Aft �kiw Mop - Project 3 Scope of Work 1. General: The survey will establish horizontal and vertical control and determine existing site conditions for design considerations in the construction of the reclaimed water main. The result of the survey shall be the completion of a topographic survey along the route of the proposed reclaimed water main. The survey will be completed under the supervision and direction of a Surveyor and Mapper licensed in the State of Florida. 2. Vertical and Horizontal Control: Degrove shall establish and depict on the survey multiple temporary benchmarks using a closed level loop from an established benchmark referenced to the NAVD 1988 Datum. A clearly defined survey control lines shall be field established along the route. Control points defining the survey control lines will be monumented. The SURVEYOR shall establish horizontal control at the site based on Florida State Plane Coordinates NAD 83. Third Order accuracy shall be required for the horizontal control. All temporary benchmarks shall have horizontal control to define their location. 3. Survey Requirements: The SURVEYOR shall perform a topographic survey of the road ROWs and CCUA Property and Easements shown in the Figures above. In addition, the SURVEYOR shall perform a topographic survey 10 feet outside of, but contiguous to, the ROWs on each side of the road ROWs. For Challenger Drive, only the area east of the road will be surveyed. The survey shall include the areas indicated below and as required by this SCOPE OF WORK. It shall show all above and below grade fixed improvements along the route (buildings, fences, signs, light poles, signals, utilities, markers, trees, landscaping, etc). The full topographic scope of work shall be undertaken on all side street intersections for a minimum of 25 feet each way from main exterior ROW line (not centerline). A. Features to be located include, but are not limited to, the following: 1. Apparent right-of-way boundary limits and widths and parcel ownership lines and addresses for any properties adjacent to the project route will be included in the survey. 2. Apparent easement limits and widths. Specific easement rights with respect to underground water and sewer utilities. 3. Type and width of pavement, with street corner radius. 4. Apparent boundary lines. 5. Apparent property lines. 6. Fences, gates, hedges, center of trees over six inches and large bushes (type and sizes of all indicated). NOTE: IDENTIFY LIVE OAK TREES SEPARATE FROM OTHER OAK TREES. 7. Driveways and sidewalks, type and width indicated. 8. Houses and structures (if located within the scope of work) and slab elevation. 9. Street, road and railroad crossings, rail iron, and include street names or railroad owner's name. 10. Location and identify overhead and underground utilities, including water, sanitary sewer, reclaimed water, storm sewer, force main, electrical lines, utility and traffic poles, guy wires, transformers, gas mains, telephone lines, fiber optic lines, cable TV lines, traffic signal lines, in conformance with ASCE 38-22 utilizing quality levels B, C and D. The following information should be indicated as applicable: size, type (service), material, direction, invert elevations, pressure, phase, and whether in-use, abandoned, or plugged. See Section C below. 11. Manholes, valves and valve boxes, catch basins, ditch bottom inlets and grates, junction boxes, and culvert end sections. Downstream and upstream manholes, catch basins, and inlet/rim and invert elevations shall be provided, for all pipelines crossing the area of interest. 12. Top of bank and toe of slope of ditches and swales and inverts of culverts. 13. Ponds to the edge of water 14. Type and width of existing curb and gutter, with flowline. 15. Existing water meters and water service lines. 16. All buildings, structures, trees, landscaping, and obstructions within this SCOPE OF WORK. 17. Include addresses for all houses, buildings, and properties. 18. Location of test hole (VVH) locations as performed by Degrove. 19. The location of soil borings performed by others (Tetra Tech's Geotechnical Subconsultant). Coordination with Tetra Tech's Geotechnical Subconsultant will be required. 20. The location of wetland flags along the project route (flags to be set by Tetra Tech's Environmental Subconsultant). Coordination will be required to locate the wetland flags within 1 to 2 days of the flagging. 21. The SURVEYOR shall locate Endangered species flags along the project route (flags to be set by Tetra Tech's Environmental Subconsultant), including but not limited to gopher tortoise. B. Elevations and Cross Sections: Degrove shall provide elevations for the following specific items required for vertical control: 1. Elevations shall be taken every 100 feet on station and shall include centerline, edges of pavement, gutter elevations, top of curb, front and back of sidewalks, top of bank and toe of slope of swales and ditches, right-of-way lines, all changes in grade between 100-foot stations, and throughout the intersections of roadways (especially at the intersection of the baselines, road centerline intersections, approaches, and curve radii). 2. All rim, invert, and bottom elevations of storm, gas, fiber optic, telephone, and sanitary sewer manholes; catch basins and storm grates; and the top of the operating nut of all utility valves. Also provide pipe materials and sizes for sanitary sewer, storm sewer lines, and water mains. If any structure cannot be accessed to obtain the information, the SURVEYOR shall notify CCUA, or the proper authority, well in advance of the scheduled completion date. CCUA, or the proper authority, will try to provide access to those structures. C. Subsurface Utility Designation and Verified Vertical and Horizontal (VVH) location: 1. Identify the horizontal location of subsurface utilities within the project boundaries. The location will be marked on the ground and identified as to type. The existence and location of the subsurface utilities will be determined through the use of electromagnetic and ground penetrating radar. Subsurface utility designation shall be in accordance with Standards for a Quality Level B Utility Investigation as defined by the American Society of Civil Engineers (ASCE) Publication 38-22. 4. CAD Requirements: A. Degrove shall provide all digitized data in AutoDesk Civil 3D. The survey shall be plotted at a scale of 1" = 20'. A signed and sealed Surveyors Report will be provided at the conclusion of the survey. Produce a working 3D surface model within the project scope defined by the boundaries established from geographic references, point data, area of easements and ROW's. 5. Deliverables: A. A signed and sealed surveyors report will be provided. B. An electronic file containing all of the information required by this scope. 6. Fee Breakdown: The fee proposal for the above scope of work shall is as follows: A. Topographic Survey: Project 1 - Transmission Pipeline from Spencer's RWF to Oakleaf RWF: $47,000.00 Project 2 - Oakleaf RWF Connection to Challenger Drive: $13,500.00 Project 3 - Transmission Pipeline North of OJR RWF: $35,600.00 B. Subsurface Utility Designation (ASCE 38-22 Levels B, C, D): Project 1 - Transmission Pipeline from Spencer's RWF to Oakleaf RWF: $21,300.00 Project 2 - Oakleaf RWF Connection to Challenger Drive: $4,500.00 Project 3 - Transmission Pipeline North of OJR RWF: $18,500.00 C. Subsurface Utility Test holes (VVH) locations (ASCE 38-22 Level A) for 15 VVH's in pavement/sidewalk: $10,125.00 ($675.00 each). D. Subsurface Utility Test holes (VVH) locations (ASCE 38-22 Level A) for 20 VVH's in grass/dirt $9,000.00 ($450.00 each). Thank You for the opportunity to submit this proposal. We look forward to working with you on this project. Regards, 6,X2OL Gordon R. Niles, PSM, CH President ATTACHMENT E CLAY COUNTY UTILITY AUTHORITY NORTH CLAY RECLAIMED WATER TRANSMISSION PIPELINES GEOTECHNICAL SUBCONSULTANT SCOPE (ARDAMAN) JJW/North Clay Reclaimed Transmission Pipelines ( 1 TETRA TECH Tt#200BP CCUA 11/21/2025 l — - Ardaman & Associates, Inc. November 12, 2025 Proposal File No. 25-60-386 MONO Geotechnical, Environmental and Materials Consultants Tetra Tech 201 E. Pine Street, Suite 1000 Orlando, Florida 32801 Attention: Mr. James J. Wallace, P.E. Subject: Proposal for Subsurface Soil Exploration and Geotechnical Engineering Evaluation Reclaim Water Main Improvements Old Jenning's, Oakland and Spencer's RWF Middleburg, Clay County, Florida Dear Mr. Wallace: As requested,we are pleased to present this proposal for conducting a subsurface soil exploration and geotechnical engineering evaluation for the subject project. Based on information supplied by you, the proposed construction includes approximately 10,000 linear feet of new 12-inch and 20-inch PVC pipeline at three separate locations. We understand that the pipelines will be installed using open cut methodology with a typical depth of soil cover of around 4 or 5 feet. In addition, we understand that one portion of pipeline may need to be installed using the horizontal directional drilling (HDD) construction technique. The scope of our work will include determining if the bearing capacity and other soil characteristics are suitable to construct the proposed pipelines. For the proposed cut and cover pipelines, we will provide geotechnical engineering recommendations for the removal of unsuitable soils along the alignments, trench stability, pipe bedding, use of excavated soils, the need for dewatering, thrust resistance, and backfill and compaction requirements. We will also estimate the normal seasonal high groundwater table at the boring locations. The following summarizes our proposed scope of work and associated fees for conducting the subject exploration. 8008 S.Orange Avenue(32809),Post Office Box 593003,Orlando,Florida 32859-3003 Phone:(407)855-3860 Fax:(407)859-8121 Florida: Bartow,Cocoa,Fort Myers,Miami,Orlando,Port St.Lucie,Sarasota,Tallahassee,Tampa,West Palm Beach Louisiana: Baton Rouge,New Orleans,Shreveport Texas: Houston Tetra Tech Proposal File No. 25-60-386 -2- FIELD EXPLORATION The field exploration program will include the following: Name Description Number of Depth Below Ground Borings Surface (feet) TPI Project 1 6,500 I.f. of 20" PVC 17 Auger 10 TPI Project 2 2,800 I.f. of 12" PVC 8 Auger 10 TPI Project 3 4,300 I.f. of 12" PVC 12 Auger 10 Contingency HDD 3 SPT 40 The SPT borings will be drilled using a procedure similar to the Standard Penetration Test outlined in ASTM D-1586. The borings will be sampled at 18-inch intervals to 10 feet deep and at 5-foot intervals below 10 feet. The auger borings will be drilled using a 4-inch diameter truck-mounted continuous flight auger or a 3-inch diameter hand bucket auger. Each sample will be removed from the sampler or auger in the field and then examined and visually classified by our crew chief. Representative portions will be sealed and packaged for transportation to our laboratory for further analysis as required. Water level observations will be made in the boreholes during the drilling operation. LABORATORY PROGRAM Routine laboratory visual classification will be performed along with specific classification tests deemed necessary (i.e., percent fines and organic content). ENGINEERING ANALYSIS AND REPORT Engineering analysis of data obtained will be made to evaluate general subsurface conditions and to develop engineering recommendations to guide site preparation and foundation support for the pipelines. In addition, we will provide an estimate of the normal seasonal high groundwater table at the boring locations. Our recommendations for the pipelines, together with data developed during the exploration, will be submitted in a written report upon conclusion of the study. We note that information provided relative to the potential HDD portion of pipeline will be provided for informational purposes only since this construction technique is proprietary in nature. MI Ardaman&Associates,Inc. — _ Tetra Tech Proposal File No. 25-60-386 -3- COST ESTIMATE The costs associated with the aforementioned tasks are estimated as follows. The total cost will not be exceeded without prior authorization. Stake Borings and Coordinate Utility Locations with Sunshine State One-Call by Senior Eng. Technician; 14 hours @ $95.00/hour $1,330.00 Mobilize Drilling Crew and Equipment; 1 mobilization @ $650.00/mob. $650.00 Auger Borings; 37 Borings x 10 I.f. @ $15.00/l.f. $5,550.00 SPT Boring; 3 borings x 40 I.f. (0 - 50 I.f.) 120 I.f. @ $19.50/I.f. $2,340.00 Setup/Moving between boring locations; 7 hours @ $285.00/hour $1,995.00 Laboratory Classification Testing; estimate $396.00 Senior Engineer; 1 hour @ $207.00/hour $207.00 Assistant Project Engineer; 15 hours @ $150.00/hour $2,250.00 CADD Draftsperson; 8 hours @ $92.75/hour $742.00 Technical Secretary; 2 hours @ $70.00/hour $140.00 TOTAL $15,600.00 TERMS AND CONDITIONS The total cost is based on the unit prices as shown on the attached fee schedule (see Attachment 1). This proposal is subject to the following: (1) access to boring locations is to be readily available to our truck-mounted drilling equipment, (2)the proposed number of borings and the boring depths will be adequate, (3) undisturbed samples and consolidation tests on fine grained soils are not budgeted into the total cost, (4) Ardaman & Associates will not take responsibility for damages to underground structures and/or services that are not located by Sunshine State One-Call, (5) exploration or evaluation of the environmental (ecological or hazardous/toxic material related) condition of the site and subsurface is not included, (6) this proposed exploration is a relatively shallow exploration and is not intended to be an evaluation for sinkhole potential, (7) Maintenance of Traffic(MOT)other than simple cones and men working Mr Ardaman&Associates,Inc. — _ Tetra Tech Proposal File No. 25-60-386 -4- signs is not required to perform the field work, and (8) permits are not required to work on the subject sites. CLOSURE We appreciate the opportunity to submit this proposal and look forward to working with you on this project. If this proposal meets with your approval, please indicate your acceptance by providing authorization to proceed. Please call if you have any questions or require additional information. Very truly yours, ARDAMAN &ASSOCIATES, INC. Colin T. Jewsbury, P.E. Orlando Branch Manager CDC/CTJ/Ims 25-60-386 Tetra Tech-Water Main Improvements,Old Jenning's,Oakland,and Spencer's RWF,Middleburg.docx (2025PP) Ardaman&Associates,Inc. - _ Attachment 1 1. Mobilization of Crew and Equipment Varies 2. Standard Penetration Test (SPT) Borings: (a) $19.50/I.f. (0 - 50 ft. depth) (b) $23.25/I.f. (50 - 100 ft. depth) (c) $31.75/I.f. (100 - 150 ft. depth) 3. Auger Borings/Wash Borings $15.00/l.f. 4. Install Temporary Casing 0 to 50 feet $13.50/l.f. 50 to 100 feet $16.50/I.f. 5. Additional SPT Samples (a) $46.00/Additional Sample (0 - 50 ft. depth) (b) $55.00/Additional Sample (50 - 100 ft. depth) 6. Undisturbed Samples (Shelby Tube) $250.00/each 7. Grouting boreholes $6.50/I.f. 8. Add 10% to Unit Rates for Drilling with Mudbug Equipment 9. Cone Penetration Tests $18.50/I.f. 10. Muck Probes Staffhour Rates 11. Groundwater Level Piezometer $35.00/I.f. 12. Double Ring Infiltrometer Test $790.00/each 13. Field Permeability $415.00/each 14. Laboratory Testing: (a) Incremental Consolidation Test $850.00/test (b) Atterberg Limits $150.00/set (c) Sieve Analysis $80.00/each (d) Percent Fines $47.50/each (e) Natural Moisture Content $19.00/each (f) Organic Content $45.50/each (g) Unit Weight/Classification of Undisturbed Sample $90.00/each (h) Permeability Test $415.00/each 15. Engineering Analysis and Report Preparation: Principal Engineer (P.E.) $247.00/hour Senior Engineer (P.E.) $207.00/hour Senior Project Engineer (P.E.) $190.00/hour Project Engineer (P.E.) $170.00/hour Assistant Project Engineer $150.00/hour Staff Scientist $131.00/hour Engineering Assistant $119.00/hour Sr. Engineering Technician $95.00/hour Engineering Technician $80.00/hour CADD Draftsperson $92.75/hour Technical Secretary $70.00/hour 16. Standby of drill crew and equipment for reasons beyond our control or difficult access $285.00/crew-hour *Unit prices effective until December 31, 2025