HomeMy WebLinkAbout14.a FYI Meadowbroork WTP Improvements Approved CO No. 1 C,%'i COU^,),,
CLAY COUNTY UTILITY AUTHORITY
MEMORANDUM
TO: Jeremy D. Johnston, MBA, PE
FROM: Joe Paterniti, P.E.
DATE: January 23,2026
RE: Change Order No. 1 an Additional Valve required to maintain operation During
Construction.
The Contractor submitted the attached Change Order No. 1 for $21,665.77 to replace an
additional non-functioning valve necessary to maintain plant operations during the replacement
of existing pumps, as outlined in the construction contract. Staff included an $ 80,000.00 -
allowance for the replacement of nonfunctioning valves in the existing construction contract.
The contractor previously utilized a portion of the allowance to install 3 replacement valves at a
cost of$75,796.49. This left $4,203.51 in the allowance. A fourth valve is now required at a cost
of$21,665.77. Staff is requesting your signature on Change Order No. 1 to increase the
construction contract by $17,462.26 ($21,665.77—4,203.51). An additional 20 days will be
added to the contract duration with CO. No. 1.
Please review the attached, and feel free to let me know if you have any questions or concerns.
Joseph Paterniti
Assistant C Engineer
Clay County Utility Authority
3176 Old Jennings Road
Middleburg, FL 32068
(904)213-2412 (Direct)
(904)424-1280 (Cell)
jpaterniti@clayutility.org
.I CO(J Clay County Utility Authority
Working together to protect
3176 Old Jennings Road
public health,conserve our
Middleburg,Florida 32068-3907 natural resources,and
Gj Telephone(904)2l3 5999 create long-term value for♦ ��
/�/ �\ our ratepayers.
TYAUlNi Facsimile (904)213-2498
Change Order No.: 1 Date: 2/20/2026
Project: Meadowbrook WTP Improvements
CCUA Bid No.: 2024/2025-A 10
CCUA Project No.: 1101-0062
Vendor: Petticoat-Schmitt Civil Contractors,Inc. Owner: Clay County Utility Authority
6380 Phillips Hwy
Jacksonville,Fl
(904)693-2190
Engineer of Record: Carollo Engineering Inc.
200 East Robinson St.,Suite 1400
Orlando,FL 32801
(407)487-4642
ORIGINAL CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 11/15/2025
DAYS ADD 20
SUB.COMP. 540 5/9/2027 5/29/2027
FINAL COMP. 570 6/8/2027 6/28/2027
INCREASE OR
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) OTY. UNIT PRICE CONTRACT PRICE
Contract Increase
1 Replacement of Non Functioning Valve 1 $1 7,465 77 $17,462.26
Contract Decrease
TOTAL INCREASE $17.462.26
TOTAL DECREASE $0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $17.462.26
ORIGINAL CONTRACT PRICE $5.197,000.00
Net Increases by Change Orders(prior to this change order) $0.00
Net Decreases by Change Orders(prior to this change order) $0.00
Total Net Change by Change Orders(prior to this change order) $0.00
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $5.197.000.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER $17,462.26
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $5.214,462.26
This document shall become an amendment to the contract and all provisions of the contract will apply hcrc:n
2026.02.23
Accepted by: 09:53:1 0-05'00' Date:
Engince S >f Recor .
/Accepted by: ?F Date: 212 V' 4mimmi.-„asup
Accepted by: r"�, Date: a3
O% n��
Project: Meadowbrook WTP Improvements
CCUA Bid No.: 2024/2025-A10 CCUA Project No.: 1101-0062
Summary of Change Orders
Date Description Contract Net Increase Net Decrease Revised Contract
Original Contract Price: $5,197,000.00
12/17/2025 Change Order No. 1: Replacement $17,462.26 $0.00
of Non-Functioning Valve
Summary of Totals: $5,197,000.00 $17,462.26 $0.00 $5,214,462.26
8014 Bayberry Rd
1.1ft® petticoat Jacksonville, FL 32256
Ir= (904) 751-0888 Phone
Schmitt (904) 751-0988 Fax
REQUEST FOR INFORMATION
To: CCUA and Carollo Location: Jacksonville,FL
From:Petticoat-Schmitt Civil Contractors, Inc.
RFI No. 5
roject Meadowbrook WTP Improvements Date: 02/13/26
Area Involved 12"Inserta Valve Behind HSPS Building
Drawing No. See drawing below
Information Requested:
Due to the discovery of additional nonfunctioning valves,PSCC proposes to install one 12-inch Inserta Valve on the discharge side of the
HSPS.The proposed location is at the northeast corner of the HSPS building.Installation of this valve is necessary to isolate and stop flow,
allowing for the installation of a 12-inch cap at the 45-degree bend in the line so that demolition activities may proceed.
-1L.
Valve Location
12'G.V.&V:B (BROKLN)
(1)24"X.24-TEE a ,,
24"X12"RED. . o (1) N
J1 (1) 12"TEE
T (1) 12"PLUG
1TDIP : 1213
v 24 01P r
•
OI % t , j//J// 13-7'
/: //// /, // ( / E
PUMP HOUSE UM &
'CONTROL BLDG. No 2 . /
////////// //y
Submitted By: Dean McCurdy
Date Answer Requested By: 02/20/26
Reply:
Reply By:
Date:
CHANGE ORDER REQUEST
COR# 1 JOB# 25253
DATE 2116/2026
TO: Clay County Utility Authority
3176 Old Jennings Road
Middleburg,Florida 32068
Project# 1101-062
Reference: RFI#5-12"Inserta Valve,NE Corner of HSPS
RFP#
Unless otherwise clarified,this proposal expires 30 calendar days after the date above.
Description: Change Order No.1—12"Inserta Valve(NE Comer of HSPS Building)
Due to the discovery of additional nonfunctioning valves,PSCC proposes to install one 12-inch Inserta Valve on the discharge side of the HSPS.The proposed location is at
the northeast corner of the HSPS building. Installation of this valve is necessary to isolate and stop flow,allowing for the installation of a 12-inch cap at the 45-degree bend in
the line so that demolition activities may proceed.
We propose an ADD TO our contract of: $21,665.77 Upon acceptance of this proposal.
Extension of cons ct time with this extra 20 working days(Based on a standard 5 day work week).
This;moose'does nol include any
X 1 S for extension or acceleration but Inc
1 j,t 2 nriht to ask for these costs al a later
Petti o -S rr�(t Civil Contractors.Inc. to date is expressly reserved.
N/A 2 Extension cost is included
to this proposal.
Acceleration cost to maintain
N/A 3 project schedule is included
in this proposal.
Owner Approval Date
1. MATERIALS:
ITEM QUAN TITY U/M PER UNIT TOTAL
Valve Box Risers 1.00 EA $104.00 $104.00
Concrete Collar 1.00 EA $22.00 $22.00
$0.00
$0.00
0.00 $0.00
0.00 $0.00
0.00 $0.00
Extension sheet attached
Subtotal $126.00
Consumables 4% of Sub-total (1) $5.04
SUBTOTAL 1 $131.04
2.SUBCONTRACTS:
ITEM QUANTITY U/M PER UNIT TOTAL
$0.00
Colt- Inserta Valves 1.00 EA $13,875.00 $13,875.00
Colt-Mobilization 1.00 EA $250.00 $250.00
$0.00
$0.00
$0.00
SUBTOTAL 2 $14,125.00
3. CONSTRUCTION EQUIPMENT:
ITEM HR/DAY/WK U/M RATE TOTAL
$0.00
Loader 2.00 DY $129.00 $258.00
Truck-Super 2.00 DY $29.00 $58.00
Truck-Foreman 2.00 DY $36.00 $72.00
$0.00
$0.00
SUBTOTAL 3 $388.00
4. FIELD LABOR
Description RATE HOURS TOTAL
Super 128 16 $2,048.00
Foreman 89 16 $1,424.00
Operator 45 16 $720.00
$0.00
$0.00
$0.00
$0.00
Total labor $4,192.00
Hand Tools/Safety 5.00% $209.60
SUBTOTAL 4 $4,401.60
DIRECT COST SUBTOTAL $19,045.64
5. GENERAL CONDITIONS: 12.00% (1+4) $565.32
6. MISCELLANEOUS:
Insurance: 1.00% of Direct Cost $190.46
Taxes. (State&Local Sales) 6.00% of 1 &3 $31.14
Total (6) $221.60
7. CONTRACT EXTENSION COST
20 Working Days Extended X Daily Rate Total (7) $0.00
8. MARKUP: 5.00% On Subcontractor $706.25
15.00% On Self-Perform $856.13
10. BOND: 1.25% Total (10) $270.82
TOTAL $21,665.77