Change Order No.: 1 Date: 7/21/2026
Project: 2023-113 Upgrade Lift Station 20
CCUA Bid No.: 2024/2025-A11
CCUA Project No.: 24003RR
Vendor: DB Civil Construction.LLC Owner: Clay County Utility Authority
4475 US 1 South,suite 707
St Augustine,Fl
(386)256-7460
Engineer of Record: Jones Edmunds and Associates,Inc.
13545 Progress Boulevard,Suite 100
Alachua,Florida 32615
(352)377-5821
ORIGINAL CONTRACT TIMES ORIGINAL PREVIOUS CO CURRENT CO
NTP 12/8/2025
DAYS ADD 74
SUB.COMP. 180 6/6/2026 8/19/2026
FINAL COMP. 210 7/6/2026 9/18/2026
INCREASE OR
DECREASE IN
ITEM DESCRIPTION OF CHANGE(S) QTY. UNIT PRICE CONTRACT PRICE
Contract Increase
1 1 50.00
I 50.00
Contract Decrease
TOTAL INCREASE $0.00
TOTAL DECREASE S0.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER 50.00
ORIGINAL CONTRACT PRICE $1,514,087.00
Net Increases by Change Orders(prior to this change order) $0.00
Net Decreases by Change Orders(prior to this change order) $0.00
Total Net Change by Change Orders(prior to this change order) $0.00
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER S1,5]4,087.00
NET CHANGE RESULTING FROM THIS CHANGE ORDER S0.00
CONTRACT PRICE INCLUDING THIS CHANGE ORDER $1.514,087.00
This document shall become an amendment to the contract and all provisions of the contract will apply hereto.
Accepted by: Date: 7/21/2026
Engineer of Rec•rd
Accepted by: % Date: 7�Z/—zoo
V dor
Accepted by: MP" Date: ZO26 07-z I
gri
DB CIVIL CONSTRUCTION
4475 US-1 South, Suite 707
St Augustine, FL 32086
REQUEST FOR INFORMATION
RFI No. #05-Rev 1
Project Lift Station#20 Upgrades Project Date: 07/13/26
Contract No.: 24/25-All Bid No. ITB#2024/2025-A11
Area Involved Contract Time Extension
Drawing No.
Information Requested:
SUBMITTAL#6-This is to formally request a contract Time Extension for the Lift Station#20 due to delays associated with the review,
correction,and approval process of Submittal#6 pertaining to the Xylem pump equipment.The initial submission of Submittal#6
remained under review for approximately 5 weeks before comments were received. The submittal then required two additional revisions
and resubmittals to address comments and obtain final approval. These extended review cycles delayed the manufacturing and
procurement of the Xylem pump equipment by approx.9 weeks,directly impacting the project critical path and remaining beyond the
Contractor's reasonable control. Accordingly,we respectfully request a contract time extension of 45 calendar days for this instance.
This will result in Substantial Completion to be July 21,2026 and Final completion to be August 20,2026.
CONTROL PANEL DELIVERY-During procurement time of the Control Panels for this project,DB Civil was notified by our Subcontractor,
RCM,that the Control Panel delivery would be delayed beyond the 12 week delivery schedule given by the panel vendor,Xylem. DB Civil
and RCM conveyed this information Clay County during progress Meetings No.3 and No.4. The date for shipping was adjusted by the
vendor several times from May 2026 through July 2026, and has now committed to July 13,2026. Xylem provided a letter,attached,
stating the shipping date was delayed due to a specified transducer component being on back order. The inability to procure a key
component of the Control Panel by Xylem,has delayed the manufacturing,shipping,installation of said panel.
DB Civil and RCM anticipate receiving the control panel by July 21,2026. On July 10,2026,DB Civil submitted an updated Schedule
reflecting the July 21st delivery as well as the remaining activities to complete the project. Based on our updated schedule,Substantial
Completion will be on August 21,2026 and Final Completion will be Sept 18,2026. Based on this information,DB Civil request an
extension of 31 calendar days in addition to the above requested 45 calendar days,creating a total of an additional 76 calendar days be
added to the Contract time. This will result in Contract Substantial Completion Date to be August 21,2026 and Contract Final Completion
Date to be September 18,2026.
Submitted By: John Robbins
Date Answer Requested By:
(Attachments I
Please find RFI response attached.
Thank you
Reply By: D.Inkell/CCUA
Date: 07.17.2026
xylem
Rebecca Conwell
Senior Customer Support Coordinator
Florida Region
o:+856 746 7128 I m:+513 335 0705
rebecca.conwell@xylem_com
July 8,2026
Todd Lealy
RCM Utilities, LLC
1451 Pine Grove Road
Eustis, FL 32726
RE: Clay County Lift Station 20
Dear Todd,
This is to advise you that the control panel for this project has been delayed. The
transducer was put on backorder and did not arrive as expected. The new expected ship
date is now 7/13/26.
I apologize for any inconvenience this has caused. I will keep you updated if there are any
other changes. In the meantime, please don't hesitate to contact me.
Sincerely,
kthecca)Co w-e a
Rebecca Conwell
Senior Customer Support Coordinator
Florida Region
o: +8567467128 I m: +513 335 0705
rebecca.conwell(a�xylem.com
. 6 aeon,... N•,.6M u.. OnA 1�..,.ea{ 1 a-•.rA:A (.f..-Itl4 IA.-.r:n breams ( t.AA .� AN2u•� 1710
pnitYA I I . a(�,�L�u•I wj•,1_La1.m ILLIS . w114.[ j1.1 41�01, /II ,�aII. m 111 I u 1u�13 l A 1311 a l•u1 r.fla 1a_•I 1 n]i+il m 1710 X 1a?n�rjujrl nJIm
f LS6 no CC IAA Up0ele7-10-2G .. . ., I...,.1,', ro - ►I 6,15
15-Jan-26 A,START UP
•A1000 PRECON MEETING o 21-Nov25A 24-Nov-25A NI Ir((OV MEETING
•A1010 NIP D 08-Dec-25A � [„`N9 y .QL62S A._
,�PXCmNVgEo
•A1030 SURVEYCADOFILESFOR SURVEY S 02-Dec•25A 03-Dec-25A 111/01f A41P01s1S{'I-SU0uU
•A1040 SET UP MOT I 08-Jan-26A 09-Ian-26A �7 SET UP MOT
•Al.0 1 a,a'IC11 110( ,p ,, ,.A .11E.EROSION%M M
, -19-Mari26 A,SUBMITTALS
•A1060 WETWEII/MANHOLE 10 25-Nov-25A 10-Dec-25A �i Y4E/Wllt/Myf•LNf
•A1070 PIPING 10 18•Dec-25A 02-Feb-26A ^ •/PIPING
•A1080 UFTSTAITON MECHANICAL 10 18.0ec•25A 19-Mar-26A L t UFTSTAIR7N MECHANICAL
•A1090 UFT STATION ELECTRICAL 10 1B-0ec-25A 13-Feb-26A ^ /,)I(�7AI _
•A1100 UFTSTATION PUMPS&PANEL 10 05-Jan-26 A 17-Mar-26 A {l UFTSTATION PUMPS&RANG.
• 1!ua II ..1.1 -_. -_�.. _.•� �lll_.;A41 IX N
a 70•Jo146.AccansfroN
•A1110 UI1UIY PIPE MATERIALS 4 27-Jan-26A 05•Mar-26A I tall I 1,411.1.4118111.
•A1120 WETWELL/MANHOLE IN WEEKS) 40 10-Dec-25 A 10Feb•26 A g WVTWIWpt1N.r01 W11611
-A1130 UFT STAITON MECHANICAL 15 10-Mar-26A 09-Aor-26A 11 MB 1•
•A1140 UFFSTATION ELECTRICAL 15 20-Mar-26A 09-Aor-26A L.1_-.JOrJ.PILU g.91
lF—SI—KVAL((1 RCA L
•A1150 UPI STATION PUMPS 60 17-Mar-26A 104N 49A RSIAI
Li,FT
■.A I uR 1nnONM . ._ � � .-. J UTT5111110N PANELS
114.4I.26,CONST RUCTI O N
•A1155 SURVEY IAIOUT 5 08-Jan-26 A 17-AUA-26 LSURVEY lAYOUT
•A1160 DEMOSITE/MOVE&SIOREGENERATOR 15 08-Jan-26 A 05-Feb-26 A •"E JOSIILN/(PaI IC STORE GENFRAT011
•A1161 HOT TAP-TIE IN 3 02-Feb-26A 03 Feb 26A 110T•W•TIE IN
•A1170 INSTALL WET WELL 20 12-Feb-26A 19-Feb•26A -NIN11 Ht11911 UIEI WELL
-A1180 INSTALL MECHANICAL 10 15-Jun-26A 26-Jun-26A 1'T INSIAIIMICI IcAL
•A1190 INSTALLELECTRICAL 5 17-Jun-26A 26•Jun-26A -Immil1,ASML(uL CAl
•A1200 INSTALIPUMPS 8 15Uun-26 A 26 Jun.26 A ..mm INa
•A1201 CONCRETE WORK 5 13-J01-26A Ft-Jul-26 CaLnt11 WO,.
.O A1202 INSTALL PANELS 5 21-Jul-26 27Ju1-26 17,5tAll►A1415
.0 A1220 UFT STATION START UP 10 28.Jul-26 10-Aue•26
. IIR 5T4110.151
Ca A1230 BACKRLLEXISITNG LS 5 11-.uA-26 17-AuA-26 1-Q KAHN iALXlIl/f X61tN015
A+A1235 DRIVEWAY/FENCE/511E51O14E 25 20-1u1-26 21-Au1-26 NEIN4 I.O%Wnr/lI WfAIIf t1ONC
•• A . SUASIAVOA4 0141111.0.1 0 - • Slab,IANIW...PaIPI100N,
..,A1240 CLEAN UP•PUNCH LIST 5 21-AUA-26 27•AU6-26 WAN U►OUNC311t5T
I.A1250 AS 10 21-Au-26 03-Seo-16 �1>.&34
• �I
•A1260 DEMOBILIZATION 5 21-Aun-26 17-Aue-26 GIA1270 FINAL COMPLETION 0 W.-Sep-2P f1f/Al COAOU
A42ual level of EDoN , .•summary I Actual Wok Clay County Utility Authority DB Civil Construction
I Remaining
I Critical
Remaining Work Lift Station #20 SCHEDULE UPDATE-JULY 2026
•Mileslane
Alachua • Jacksonville • Sarasota Jon esEdmunds,
Tampa • Titusville • Winter Haven
ENGINEER'S RFI COMMENTS
JONES EDMUNDS PROJECT NO.: 03742-015-01 RFI DESCRIPTION: Contract Time Extension Request
JONES EDMUNDS RFI NO.: 5A CONTRACTOR RFI NO.: 5. R1
DATE RECEIVED: 07.13.2026 DATE REVIEWED: 07.15.2026 REVIEWED BY: D. Inkell/CCUA
COMMENTS
1. The Contractor is requesting that additional Contract Days be added to the Contract due to
material delivery delays. Jones Edmunds has reviewed the attached supporting
documentation that included a letter from Xylem, the control panel manufacturer, informing
the Contractor of a backorder resulting in unforeseen delay.
Additionally, the Contractor has provided a revised construction schedule that has taken in
account for the previous requested time of 45 days and the unforeseen delay resulting with
29 additional days. Jones Edmunds recommends that the Contractor be granted 74-additional
days to the current contract.
END OF COMMENTS
\\jea.net\pan02\WORKSPACE\03742-Clay County Utility Authority\Projects\015-01-LS20Upgrades\Design&Construction\Construction
Services\RFIs\05A Contract Time Extension Request\Engineer's RFI Review_05A.docx