HomeMy WebLinkAbout10.e LB 2026-2027-05 CIP Program Performance Management Policy CLAY COUNTY UTILITY AUTHORITY RESOLUTION NO. 2026/2027-05 A RESOLUTION OF CLAY COUNTY UTILITY AUTHORITY, AN INDEPENDENT SPECIAL DISTRICT OF THE STATE OF FLORIDA ("AUTHORITY"), INCORPORATING FINDINGS; ADOPTING THE AUTHORITY'S CAPITAL IMPROVEMENT PROGRAM PERFORMANCE MANAGEMENT POLICY; PROVIDING FOR CONFLICTS, SEVERABILITY, AND EFFECTIVE DATE. WHEREAS, the AUTHORITY intends to maintain a sustainable Capital Improvement Program("CIP") to maintain the operational and fmancial performance of the utility; and WHEREAS, the AUTHORITY wishes to adopt its "Capital Improvement Program Performance Management Policy" (herein so called, which may also be referred to as "CIP Performance Management Policy" or simply "CIP Policy") in the form as attached hereto as Exhibit "A" and hereby incorporated by this reference, establishing reasonable and sustainable CIP Performance Management Measures to guide planning, budgeting, decision making, performance, and reporting. NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF SUPERVISORS OF THE AUTHORITY AS FOLLOWS: SECTION I. The foregoing findings are incorporated herein by reference and made a part hereof. SECTION II. The AUTHORITY hereby adopts the Capital Improvement Program Performance Management Policy attached hereto as Exhibit "A" as its official Capital Improvement Program Performance Management Policy relating to all of the subject matter set forth therein. SECTION III. All other resolutions or part of resolutions in conflict with any of the provisions of this Resolution are hereby repealed. SECTION IV. If any section or portion of a section of this Resolution proves to be invalid, unlawful, or unconstitutional, it shall not be held to invalidate or impair the validity, force, or effect of any other section or part of this Resolution. SECTION V. This Resolution shall become effective immediately upon its passage and adoption. 1 CCUA Resolution No.2026/2027-05 DULY ADOPTED by the Board of Supervisors, Clay County Utility Authority, on this 6th day of October, 2026, effective as of October 1, 2026. CLAY COUNTY UTILITY AUTHORITY, BY ITS BOARD OF SUPERVISORS By: ,Chairman ATTEST: APPROVED AS TO FORM AND LEGALITY: By: By: Janice Loudermilk, Secretary Grady H. Williams, Jr., LL.M., Clay County Utility Authority General Counsel (Seal) 2 CCUA Resolution No.2026/2027-05 0,0 COU,\,,` �fl s4YAUTto* POLICY & PROCEDURES Capital Improvement Program Performance Management Policy Effective Date: October 1, 2026 Revision Date: N/A Section 1. Purpose 1.1. Clay County Utility Authority(the Authority)intends to sustain a Capital Improvement Program(CIP)to maintain the operational and financial performance of the utility. To achieve this purpose, the Authority's Management defines within this policy the CIP Performance Management Measures they shall report to the Board of Supervisors to comply with the adopted CIP Performance Management Resolution No. 2026/2027-05 Section 2. Policy 2.1. The Authority establishes with this policy reasonable and sustainable CIP Performance Management Measures to guide planning, budgeting, decision making, performance, and reporting. Section 3. Goals and Objectives 3.1. The Authority's Management intends to lead the utility in sustainably and responsibly achieving and maintaining specific CIP Performance Management Measures. In achieving and maintaining these measures, the Authority will accomplish the objectives listed below. 3.1.1. Use industry accepted measures to monitor and report on the Authority CIP performance. 3.1.2. Establish and/or maintain sufficiently high bond and/or credit ratings to assure access to affordable credit and low borrowing costs. 3.1.3. Guide the Authority's Board of Supervisors and leadership regarding debt management. 3.1.4. Guide the Authority leadership and management regarding expected CIP budgeting, performance, and reporting. 3.1.5. Establish appropriate levels of CIP funding, contingencies, and reserves for project expenditures. 3.1.6. Establish appropriate levels of CIP funding for renewal and replacement expenditures as well as forecast system expansions. 3.1.7. Establish expectations for processes and performance reporting of projects within the CIP. 3.1.8. Establish CIP Performance Management Measures, the Authority's management shall report to the Board of Supervisors on an established monthly, quarterly, or annual basis. 3.1.9. Maintain flexibility to address capital and financial needs of the utility. Section 4. Definitions Page 1 of 7 Capital Improvement Program Management Policy 4.1. Asset Management System(AMS): The system the Authority uses to track data related to the physical plant and field infrastructure to deliver potable water, wastewater, and reclaimed water services. 4.2. Capital Improvements: The improvement of land and fixed assets to deliver water, wastewater, and reclaimed water services. 4.3. Capital Improvement Program (CIP): the Authority's five-year program identifying, planning, budgeting, and reporting on CIP projects and their respective performance related to their scope, schedule, and budget. 4.4. Capital Project Review Committee(CPRC): A committee of Authority staff comprised of the Executive Director, Chief Engineer, Chief Operations Officer, Chief Financial Officer, Assistant Chief Engineer, and the Assistant Chief Operations Officer. The CPRC reviews the initiation and performance of projects listed in the CIP. 4.5. CIP Budget:the sum of all the individual CIP project budgets along with a Management Reserve amount in either a single fiscal year or total over a five (5) year period. 4.6. Contingency: Budgeted funds intended for unexpected or unforeseen expenditures during a fiscal year or within the development of a CIP project. 4.7. Equivalent Residential Connection (ERC): The representation of water, wastewater, and reclaimed water demands for an equivalent residential home connecting to the utility systems operated and maintained by the Authority. Refer to the Authority's latest edition of the adopted Service Availability policy for the current water, wastewater, and reclaimed demands that make-up the ERC definition. 4.8. Management Reserve: The funding identified within the CIP to serve as a contingency fund should individually project contingencies be exhausted. 4.9. Project Need Identification: When Authority staff identify the need for a CIP Project to address renewal, rehabilitation, or replacement of existing infrastructure or the expansion of Authority infrastructure to meet service availability demands of the community. 4.10. Project Concept Development: When Authority staff begin to develop project concepts or scope of work to address the needs stated in the Project Need Identification phase of a CIP project. 4.11. Project Basis of Design: The phase of a CIP project when Authority staff prepare either a technical memorandum or report stating the design objectives as well as performance and regulatory requirements. 4.12. Project Budget: The total cost of all planned expenses for a single CIP project to include Authority staff time and Professional Consultants performing geotechnical explorations and testing, surveying, engineering design, construction inspection or administrative services, as well as Contractors performing the physical construction of capital infrastructure. 4.13. Project Cash Flows: The estimated timing of CIP project expenditures over time whether monthly or fiscal year timeframes. 4.14. Project Design: The phase of a CIP project when either Authority staff or consultant prepares a technical design including drawings, calculations, specifications, and permit applications for construction of capital infrastructure. Page 2 of 7 Capital Improvement Program Management Policy 4.15. Project Procurement: The phase of a CIP project after the completion of the Project Design to engage a responsive and qualified contractor to construct the designed capital infrastructure. 4.16. Project Construction:The phase of a CIP project when a contractor under a construction contract physically builds capital infrastructure. 4.17. Project Close-out: The end of a CIP project occurs when Certification of Completion of Construction (CoCs) are filed with regulatory agencies, the constructed assets are accepted by the Authority and placed into operation, and Authority staff files final project documents to complete the project process removing the project from the CIP and placing the assets within the financial system. 4.18. Project Manager / Representative: The individual of the Authority's staff responsible for planning, executing, and closing projects. Section 5. Forecasting 5.1. The Authority's Development Services shall maintain forecasts of population growth looking forward with one (1), five (5), ten (10), fifteen (15), and twenty (20) year intervals. 5.1.1. The Authority shall update forecasts of population growth at least annually. 5.2. The Authority's population growth forecast looking forward one (1) year shall be consistent with the growth in customer accounts used to set the annual operating budget. 5.3. The Authority shall consider information from the Authority's pace of meter installations, Developer Agreements, Master Utility Agreements, Development Services inquiries as well as publicly available information from Clay County's Building Department, the University of Florida's Bureau of Economic and Business Research(BEBR), and the United States Census Bureau in developing forecast models. 5.4. The Authority shall maintain records of average and peak potable water demands from the Water Treatment Plants (WTP), wastewater flows to the Water Reclamation Facilities (WRFs), and reclaimed water demands from the Reclaimed Water Storage Facilities. 5.4.1. The Authority staff will base forecasts of customer potable water demands, wastewater flows, and reclaimed water demands on rolling five (5) year averages along with standard deviations and variances. 5.4.1.1. The forecasts will provide potable water demands, wastewater, flows, and reclaimed water demands in industry standard units such as ERC per Thousand Gallons (kGal.), Million Gallons per Day (MGD), etc. 5.5. The Authority shall use the forecasts of population growth and related potable water demands, wastewater flows, and reclaimed water demands to inform identification of expansion projects within the CIP. Section 6. Asset Management 6.1. The Authority shall maintain an Asset Management System (AMS) of all existing operational potable water,wastewater, and reclaimed water infrastructure. 6.2. The Authority shall use the AMS to inform the CIP regarding the renewal, rehabilitation, and replacement project needs related to existing infrastructure. Page 3 of 7 Capital Improvement Program Management Policy 6.3. The Authority staff must consider the following items to inform planning, scoping, design development, and decision making related to the renewal, rehabilitation, and replacement of existing infrastructure. 6.3.1. Asset Life Cycle 6.3.2. Condition assessments of the asset 6.3.2.1. Repair and maintenance activities on the asset 6.3.3. Risk and consequence of failure analysis of the asset Section 7. CIP Management 7.1. Management shall establish each fiscal year a summary of CIP budgeted projects expected to be advanced during a fiscal year and over a five-year period. 7.2. Management shall also prepare a list of known and anticipated CIP needs for a ten-year period. 7.3. Typical CIP Project Design Development Phases needed to develop a reasonable scope, schedule, and budget. 7.3.1. Need Identification 7.3.2. Concept Development 7.3.3. Basis of Design 7.3.4. Design 7.3.5. Procurement 7.3.6. Construction 7.3.7. Close-out 7.4. CIP Project Budgets 7.4.1. The Authority's Management shall use a standardized and documented process for development of individual CIP project budget when the need for the project has been identified by staff. 7.4.1.1. For projects that span multiple fiscal years, the Authority shall develop the total project budget first then provide information related to planned expenditures within individual fiscal years. 7.4.2. Management shall establish a CIP Engineering Project Number and Financial Job Number when a CIP Project is created at the Project Concept Development Level. 7.4.3. Project budget contingencies: Authority Management shall build budget contingencies within each individual project budget to address levels of accuracy in the cost estimating and the uncertainty of developing information. Individual project budget contingencies will align with the recommended contingencies, but may vary, based upon level of uncertainty in the project development phase listed below. 7.4.3.1. Project Concept Development: 50% 7.4.3.2. Project Basis of Design: 40% 7.4.3.3. Project Design: 30% 7.4.3.4. Project Procurement: 10% Page 4 of 7 Capital Improvement Program Management Policy 7.4.3.5. Project Construction: 10% 7.4.3.6. Changes in the project contingencies as a project develops will not require formal change management process, so long as the project's scope, schedule, and total budget do not change. 7.4.3.6.1. Changes in a project's scope, schedule, and/or total project budget require a formal documented changed management process. 7.4.4. Change Management: The Authority's Management shall use formal processes for documenting changes in individual CIP project scope, schedules, and budgets. 7.4.4.1. The Authority's Project Manager shall be responsible for ensuring all project documentation is kept within the project files. 7.4.4.2. CIP Project Change Orders shall be processed consistently with the Authority's current Procurement Policy and contract requirements. 7.4.4.3. Use of the Management Reserve: The Authority intends for the Management Reserve (Section 8)to serve as a funding source of last resort for CIP projects. Should a CIP project experience a projected budget shortfall during the course of a project, the Authority's Project Manager shall initiate the formal Change Management process. 7.4.4.4. The Authority's Project Manager is expected to manage project changes within a reasonable amount of time from when they occur (e.g. 30 days). 7.4.4.4.1. The Authority's prohibits the practice of waiting until the end of a project to execute a single Change Management process to encompass all changes that occurred during a project. 7.4.5. CIP Project Planned Pace of Expenditures (Cash Flow) 7.4.5.1. The Authority's Project Manager shall prepare and maintain an estimated pace of expenditure for each CIP Project. 7.4.5.2. The Authority's Project Manager shall coordinate the CIP project planned pace of expenditure with the Chief Engineer, Chief Financial Officer, and the Executive Director within the CPRC. 7.4.5.2.1. Management shall use the CIP project budgets along with the planned pace of expenditures to inform decisions regarding CIP financing. 7.4.5.3. The CIP planned pace of expenditures shall inform the larger CIP especially considering projects spanning more than one fiscal year. 7.4.5.4. The Chief Engineer shall coordinate with the Chief Financial Officer regarding the planned pace of total CIP expenditure remaining consistent with the forecast cash flows over five (5) years. 7.4.6. CIP Project Close-out 7.4.6.1. The Project Manager shall reconcile the Project Budget with all contracts, Purchase Orders, and Change Orders prior to final completion and acceptance of a CIP Project. 7.4.6.1.1. The Project Manager shall use a documented Change Management process to adjust the Project Budget consistent with the final amounts of all contracts, purchase orders, and Change Orders. Page 5 of 7 Capital Improvement Program Management Policy 7.4.6.1.2. Any surplus funds in a Project Budget shall be transferred into the Management Reserve upon the Project Close-out of the CIP Project by the Chief Financial Officer. 7.4.6.2. Upon the documented final completion and acceptance of a CIP Project,the Authority's Project Manager shall provide the Chief Financial Officer and Risk and Safety Manager a written Notice of Completion and Project Close- out within 30 calendar days of approval of the final payment. 7.4.6.2.1. In the event a CIP Project is planned or designed,but the Authority's Management decides not to construct, the Authority's Project Manager shall provide the Chief Financial Officer a written Notice of Completion and Project Close-out within 30 calendar days from approval of the final payment. 7.4.6.2.2. The Chief Financial Officer shall close the CIP Project financial job numbers upon receipt of the Notice of Completion and Project Close-out. 7.4.6.2.3. The Risk and Safety Manager shall notify, in writing, the Authority's Insurance Agent of the CIP Project completion and acceptance placing the constructed assets into operational service. 7.4.6.2.3.1. The Risk and Safety Manager shall confirm with the Insurance Agent the constructed assets are added to the list of insured assets. Section 8. Management Reserve 8.1. Authority Management shall include a Management Reserve each fiscal year of roughly 5% of the sum of the CIP project budgets within the total annual CIP budget. 8.2. The CIP Management Reserve shall not accumulate over time. Section 9. Inflation Indexing using the Consumer Price Index(CPI) 9.1. The Authority recognizes the need to maintain purchasing power over the course of time. To address this issue, The Authority's Management shall consider changes in the PPI and CPI as published by the United States Bureau of Labor Statistics when preparing and updating project budgets. 9.2. The Authority's Management may consider other inflationary measures in the preparation of project budgets so long as the source of such inflationary measures are from documented and standardized source related to the utility or associated industry Section 10. Reporting Requirements and CIP Financial Performance Management Measures (FPMM) 10.1. Management shall provide the Board of Supervisors an annual report by the first meeting in September detailing the CIP project efforts at the beginning of the fiscal year and the work completed by the end of the fiscal year. 10.1.1. If CIP Projects are not initiated as planned,Authority staff shall disclose the reason for the delay and explain in writing any adjustments in CIP scheduling and budgeting. 10.2. Management shall provide the Board of Supervisors quarterly reporting on the progress of the CIP projects. Page 6 of 7 Capital Improvement Program Management Policy 10.2.1. The quarterly reporting shall include the currently approved CIP project budget and schedules along with the elements listed in Section 7 7.3. 10.2.1.1. CIP Project Budget 10.2.1.1.1. The original Board approved project budget 10.2.1.1.2. The number of approved project budget changes/amendments 10.2.1.1.2.1. The dollar ($) value and percentage (%) changed of the approved project budget changes/amendments 10.2.1.1.3. The current Board approved project budget 10.2.1.2. CIP Project Contracts 10.2.1.2.1. The total value of contracts within the approved project budget 10.2.1.2.1.1. The total value invoiced against the approved project contracts 10.2.1.2.1.1.1. The percent (%) complete against the entire project budget including variances ($ value and % complete). 10.2.1.2.1.1.2. The percent (%) complete against the respective contracts including variances ($ value and % complete). 10.2.1.2.1.1.3. The total earned value against the approved project budget (% complete) including variance ($ value). 10.2.1.3. CIP Project Schedules 10.2.1.3.1. Total Project Schedule with Variances (days and% complete) 10.2.1.3.1.1. Contract schedules within the Project with Variances (days and% complete) CHANGE LOG Date of Change Description of Change Page 7 of 7